Battery storage alongside a solar scheme

6 min readBy PlanScope Editorial Team

Electricity storage is determined locally whatever its capacity. Co-locating it with solar changes the application in four places: fire safety, night-time noise, compound layout and decommissioning.

A battery storage planning application sits with the local planning authority whatever the capacity, because electricity storage was taken out of the nationally significant infrastructure regime in England and Wales and left with councils. Co-locating storage with a solar farm changes the application in four places: fire safety, noise from inverters and cooling plant, the layout required to fight a fire in a container yard, and the decommissioning position for equipment with a shorter life than the panels around it.

The planning principle is usually the easy part. The detail is where these schemes stall.

How storage is treated in planning terms

A battery energy storage system has no use class. It is assessed as a sui generis use or, where it is ancillary to the generating station, as part of that development. Most authorities prefer a single application covering generation and storage together with a description that names both, because a storage element described loosely as ancillary plant invites an argument later about what was permitted.

Capacity does not change the decision maker. Storage facilities other than pumped hydro were removed from the Planning Act 2008 regime, so a large battery yard is a local application even where a solar array of comparable output would not be. Thresholds for solar generation have moved, so check the current figure rather than working from an older one.

Where the storage is bolted onto a consented solar scheme after the event, the route is usually a fresh full application rather than a variation, since the character of the development changes.

Fire safety and the evidence authorities expect

This is the issue that attracts objections, and the objections are often better informed than applicants expect.

The concern is thermal runaway in a lithium-ion cell propagating through a module and then a container, with flammable off-gassing before ignition. The planning response is a battery safety management plan covering the chemistry proposed, the detection and suppression designed in, separation distances between containers, the approach to off-gas venting, and what the fire and rescue service is expected to do if it attends.

Consult the fire and rescue service early and record the response in the submission. Authorities take a service that has engaged and is content far more seriously than an applicant's assurance that the technology is safe. Where the authority asks for a full fire engineering document, that is a report type where a professional with fire engineering competence is legally expected, and a drafted document is a starting point for that professional rather than a substitute.

Three site questions follow from the fire case and belong on the layout rather than in the text.

  • An emergency water supply of stated capacity, whether a tank, a lagoon or a hydrant, with the draw point reachable by an appliance.
  • Separation distances between containers and from the boundary, dimensioned on the plan.
  • Containment for firewater run-off, so that what is used to fight a fire does not reach a watercourse.

Noise from inverters, transformers and cooling

Storage runs at night, and that is what distinguishes its noise case from a solar array's.

Inverters, transformers and the air conditioning serving the battery containers all produce sound with a tonal character, and transformer hum attracts an acoustic feature correction under BS 4142. The assessment compares the rating level at the nearest residential receptor with the measured background sound level, and rural night-time background levels are low. A site that passes comfortably in the afternoon can fail at 2am.

Design responses in rough order of usefulness: set the plant back from the boundary, orientate cooling units away from receptors, specify quieter units at procurement rather than assuming attenuation later, use acoustic barriers close to the source, and only then consider operational restrictions, which operators resist because the market they serve runs overnight. A Noise Impact Assessment with a night-time baseline survey is the document that settles it, and taking the baseline in a quiet season matters as much as the equipment data.

Layout, landscape and the land underneath

Containers are tall, rectangular and industrial in a way that panels are not. A solar array reads as a low horizontal field. A battery yard reads as a small industrial compound, and the landscape argument has to be made separately for it.

A Landscape and Visual Impact Assessment prepared to the third edition of the landscape institute guidelines covers the receptors and viewpoints agreed with the officer. Put the compound in the least exposed part of the site, use existing landform rather than relying on new planting that takes 15 years to perform, and show the compound in the photomontages rather than only the panels.

Agricultural land quality is the other site-level question. Where the proposal takes best and most versatile land, national policy expects poorer quality land to be used in preference, and the evidence is an Agricultural Land Classification survey carried out by a soil scientist on ground that is not waterlogged. Survey timing is a programme risk worth planning for.

Biodiversity net gain applies, and a compound of hardstanding and gravel delivers none of it, so the gain has to come from the land around the development. A Biodiversity Net Gain Assessment using the statutory metric has to be completed by a competent person under the Environment Act 2021 regime, with the biodiversity gain plan approved by the authority before development begins.

Decommissioning, restoration and the life of the equipment

Batteries have a shorter working life than panels, and cells get replaced during the permission. Say so, because an authority that believes the containers are permanent will condition them as permanent.

Useful decommissioning conditions cover three things. A trigger, usually a stated period after the equipment ceases to export or store electricity. A scope, listing what is removed and to what depth foundations are grubbed out. And a restoration specification with an aftercare period, which on agricultural land means soil handling that leaves the field usable.

A financial guarantee is sometimes requested. Whether an authority can require one depends on the obligation tests, and the arguments usually land in a section 106 rather than a condition. Expect the question on a large scheme.

The submission in practice

The core application documents still apply, and the technical set usually adds the battery safety management plan, the noise assessment with a night-time baseline, the landscape and visual work, ecology and biodiversity net gain, agricultural land classification where relevant, a construction traffic plan for abnormal loads, and drainage covering both the compound and the firewater containment.

Grid connection is a commercial matter rather than a planning requirement, and an authority cannot refuse for want of a connection offer. It will come up at committee anyway, so having a position on deliverability saves time. The same applies to the question of what happens to the cells at end of life, which is where our note on solar canopies over car parks and the wider site reuse question meets the same objection.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

Browse the 66 report types to see which documents a co-located storage and generation scheme is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

Does a large battery storage scheme go to the Planning Inspectorate?

No. Electricity storage other than pumped hydro was removed from the nationally significant infrastructure regime in England and Wales, so a battery facility is determined by the local planning authority whatever its capacity. Thresholds for solar generation itself have changed, so confirm the current figure for the generating element before assuming both parts follow the same route.

What fire safety evidence does a battery application need?

A battery safety management plan setting out the cell chemistry, detection and suppression, separation distances between containers, off-gas venting and the expected role of the fire and rescue service. Consult that service early and include its response. The layout also needs an emergency water supply with an access point for an appliance and containment for firewater run-off.

Why is noise harder for storage than for solar?

Storage operates at night, and rural night-time background sound levels are low. Inverters, transformers and container cooling produce tonal sound, which attracts an acoustic feature correction under BS 4142. A scheme that passes against daytime background levels can fail against the night-time baseline, so the survey has to cover the quiet period.

Does biodiversity net gain apply to a battery compound?

Yes, subject to the usual exemptions. A compound of hardstanding and gravel delivers no habitat units of its own, so the 10 per cent gain has to come from land around the development or from off-site units. The statutory metric must be completed by a competent person and the biodiversity gain plan approved by the authority before development begins.

How long should a decommissioning condition run?

Tie it to a trigger rather than a fixed date, usually a stated period after the equipment stops exporting or storing electricity. The condition should also list what is removed, to what depth foundations are taken out, and the restoration specification with an aftercare period. Batteries have a shorter life than panels, so say in the application that cells will be replaced during the permission.

Sources and further reading

battery storagesolarrenewable energynoise assessmentfire safetylandscape

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Energy, Sustainability and Carbon

View all →
Energy, Sustainability and Carbon7 min read

Energy statement baselines: Part L against policy targets

A Part L pass and a policy percentage improvement are different measurements and should never share a table. How each is built, why carbon factors changed the answers, and what the reconciliation paragraph needs to say.

Read article →
Energy, Sustainability and Carbon7 min read

Urban greening factor: calculating a score that passes

The urban greening factor is a weighted average across the whole red line area, not just the landscaped parts. Here is how the weightings work, where the score is won, and how to present a calculation an officer can check.

Read article →
Energy, Sustainability and Carbon7 min read

Whole life carbon thresholds: which schemes are caught

The trigger for a whole life carbon assessment is not floor area. In London it is referability to the Mayor; outside London it is the adopted local plan, or nothing at all.

Read article →
Energy, Sustainability and Carbon8 min read

Solar panels on a listed building: what is possible

Solar on a listed building turns on visibility, fixing detail and reversibility rather than on the panels. The slopes least likely to be refused, and the documents consent needs.

Read article →
Energy, Sustainability and Carbon7 min read

Embodied carbon in a retrofit against a new build

A retrofit against new build carbon comparison turns on four module groups, the structural appraisal behind the reuse case, and the grid decarbonisation assumption nobody states.

Read article →
Energy, Sustainability and Carbon8 min read

Fabric first against renewables: where the money goes

Fabric first is right for the first few thousand pounds and wrong for the last few. Work out the crossover for your own plot with SAP sensitivity runs rather than borrowing someone else's league table.

Read article →