Building Safety Regulator gateways for planning teams

6 min readBy PlanScope Editorial Team

A planning permission does not bind the Building Safety Regulator, and a gateway decision can leave permitted drawings out of date. How to keep the two tracks aligned.

Planning teams meet the building safety gateways planning regime at one point, Gateway One, and then hand the building to a process that runs on a different clock with a different regulator. Understanding what happens after you leave matters, because Gateways Two and Three can force design changes that the planning permission does not allow.

The regime comes from the Building Safety Act 2022 and the regulations made under it. Gateway One sits at planning, Gateway Two before construction starts, and Gateway Three before occupation. Only the first is a planning process at all.

The three gateways and where planning sits

Gateway One is the planning stage. For a relevant building, article 9A of the Development Management Procedure Order 2015 requires a fire statement with the application, and the Health and Safety Executive, acting as the Building Safety Regulator, is a statutory consultee. The output is an ordinary planning permission, informed by the regulator's response.

Gateway Two is a building control approval application made to the Building Safety Regulator before building work on a higher-risk building may start. The regulator, rather than a local authority building control team or an approved inspector, is the building control authority for these buildings.

Gateway Three is the completion stage. A completion certificate application goes to the regulator, and the building cannot be occupied until the certificate is issued and the building is registered.

The definition of a higher-risk building for construction purposes broadly follows the height and storey test at planning, being at least 18 metres or seven storeys with two or more residential units, so most buildings that needed a Fire Statement will also go through Gateways Two and Three. The two tests are not word for word identical, which is why the question of whether a scheme is a relevant building at planning stage is answered separately from whether it is a higher-risk building at construction stage. Which planning applications need a fire statement deals with the planning side of that question.

Where the two regimes disagree about the same building

The height and storey tests read similarly, but they were written for different purposes and they are applied by different bodies at different moments in a project's life.

Three mismatches recur. A scheme whose topmost storey sits marginally below 18 metres at planning can cross the threshold once the finished floor level is set against the as-built ground level. A building that contains educational accommodation is a relevant building at planning but may not be a higher-risk building for construction purposes. And a phased scheme can have a single planning permission covering blocks that are treated differently at Gateway Two.

Resolve the categorisation in writing at the outset, and record the reasoning in the design team's risk register. An assumption carried from the planning application into the construction programme is the most common cause of a late and expensive discovery.

What Gateway Two requires before construction

The application is a full building control approval application supported by design and construction information that shows the building will comply with the building regulations. That means developed design, not planning-stage information.

The practical shift is in maturity. A scheme that would historically have started on site with the structural package complete and the facade still being developed cannot do that here. The regulator assesses the application as submitted, and a submission with gaps is more likely to be rejected than queried.

Statutory determination periods apply, measured in weeks rather than days, and extensions are commonly agreed between the regulator and the applicant. Treat the period in the regulations as the floor rather than the expectation, and confirm the current periods before fixing a programme.

Work must not start before approval. There is no equivalent of starting on the strength of a building notice.

Change control during construction

Once approval is granted, changes are controlled. The regulations distinguish changes that must be notified from those that need the regulator's approval before they are made, and the categories are defined by the effect of the change rather than by its cost.

This is the part planning teams most need to understand, because a change forced by a planning condition lands in the same system. Discharging a materials condition with a different cladding specification, or agreeing a revised balcony detail with the case officer, can be a change requiring the regulator's approval, and the sequence matters. Agreeing it with planning first and with the regulator afterwards can leave a scheme with a permission it cannot lawfully build.

Keep a single change register covering both regimes. One column for the planning consequence, one for the building safety consequence, one for who has agreed what and when.

Gateway Three and occupation

The completion certificate application goes to the regulator with as-built information, including the golden thread of building information that has been maintained through construction. The regulator may inspect. Occupation before a completion certificate is issued and the building is registered is an offence.

For a developer, the exposure is commercial rather than technical. Sales completions, tenancy start dates and funding milestones all sit on the far side of a decision the developer does not control. Build float into the programme at this point rather than at the start.

What a gateway problem does to a planning permission

A gateway refusal does not revoke a planning permission, and a planning permission does not oblige the regulator to approve anything. The two consents are independent, and a scheme needs both.

The awkward outcomes come from divergence. Where the regulator requires a second stair, a wider firefighting shaft, a different external wall build-up or a change to the ground floor layout, the permitted drawings no longer describe the building. Depending on the scale, the answer is a non-material amendment under section 96A, a section 73 application to vary the approved plans condition, or a fresh application.

Timing makes it worse. A section 73 application takes eight weeks for a minor scheme and longer for a major one, and it may attract fresh consultation responses on matters unrelated to fire safety. That is why single-stair questions and external wall specifications are better resolved before the planning application is submitted than after.

Six habits keep the tracks aligned:

  1. Fix the evacuation strategy and stair arrangement before the planning drawings are frozen, not during Gateway Two design development
  2. Ask the fire engineer to review the draft conditions on the planning permission before the decision is issued, particularly materials and detailed design conditions
  3. Write conditions in performance terms where possible, so that a compliant variation does not automatically require a planning amendment
  4. Maintain one drawing register serving both submissions, with a single revision sequence
  5. Budget for one section 73 application on any higher-risk scheme, because divergence is common
  6. Record the regulator's Gateway One response and check the final design against every point in it before the Gateway Two submission

The reform programme here is still settling, and further changes to procedure and timescales have been signalled. Follow developments on the planning law timeline and verify the current position with the regulator before relying on any particular period.

Where PlanScope drafts supporting documents for a scheme of this kind, it produces AI-assisted drafts structured to UK planning policy, with site facts flagged rather than invented. Fire engineering and building control submissions require qualified professional input. You can see how the planning-stage documents fit together on the report index.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Which gateway is the planning stage?

Gateway One. For a relevant building, article 9A of the Development Management Procedure Order 2015 requires a fire statement with the planning application and the Health and Safety Executive is consulted as the Building Safety Regulator. Gateways Two and Three are building control processes run by the regulator, outside the planning system entirely.

Can work start once planning permission is granted?

Not for a higher-risk building. Building work may not begin until the regulator has granted building control approval at Gateway Two. There is no equivalent of starting on a building notice, so a planning permission on its own does not allow construction to start on these buildings.

What happens if the regulator requires a design change?

The permitted drawings may no longer describe the building. Depending on scale, the fix is a non-material amendment under section 96A, a section 73 application to vary the approved plans condition, or a fresh application. Budget for one section 73 on any higher-risk scheme, because divergence between the two consents is common.

Does a gateway refusal cancel planning permission?

No. The consents are independent. A refusal at Gateway Two or Three leaves the planning permission in place but means the scheme cannot lawfully be built or occupied as approved. Equally, a planning permission places no obligation on the regulator to approve the building control application.

When can a higher-risk building be occupied?

Only after a completion certificate has been issued at Gateway Three and the building has been registered. Occupation before that point is an offence. Because the decision sits with the regulator rather than the developer, sales completions and tenancy start dates should carry float at that stage of the programme.

Sources and further reading

building safetygatewayshigher risk buildingsfire statementsection 73regulation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Law Updates

View all →
Planning Law Updates6 min read

Local validation lists: what authorities may require

A local list item only bites if it was published within two years and is reasonable for your scheme. How to check, and what to do when validation disagrees.

Read article →
Planning Law Updates8 min read

Temporary stop notices and how long they last

A temporary stop notice halts an activity on display, with no right of appeal, and now lasts up to 56 days in England. Here is what it can and cannot prohibit.

Read article →
Planning Law Updates7 min read

Appeal procedures compared: written, hearing and inquiry

You state a preference and the Inspectorate decides. Here is how the three appeal procedures are allocated, what each demands, and how to argue for the one you want.

Read article →
Planning Law Updates8 min read

Prior approval procedure and the deemed grant trap

The 56 day deemed grant under paragraph W runs from receipt, permits only what was submitted, and waives none of the class conditions. How to use it safely.

Read article →
Planning Law Updates7 min read

Permitted development conditions and the effect of a breach

A breached condition in the General Permitted Development Order leaves the whole extension unauthorised, not just the non-compliant part. What follows and how to fix it.

Read article →
Planning Law Updates7 min read

The standard method for local housing need explained

Local housing need now starts from existing stock rather than household projections. The result is a minimum for plan making, not a target, a ceiling or a test for any single application.

Read article →