Checklist for a written representations appeal bundle

7 min readBy PlanScope Editorial Team

A paper appeal is read once, in order, without you there. Here is how to structure the statement of case, build a numbered core documents list and index the bundle so every assertion is checkable.

A written representations appeal is won or lost on a bundle the inspector reads once, in order, without you in the room. So the written representations appeal checklist that matters is not a list of forms. It is a discipline about what goes in, how it is indexed and how each assertion in the statement of case points to a page the inspector can find in under five seconds. Get that right and a modest case reads as a careful one.

Choosing written representations over a hearing

The Planning Inspectorate selects the procedure against its published criteria, and you state a preference with reasons on the appeal form. Written representations suits a case where the issues are capable of being understood from documents and a site visit.

Push for a hearing or an inquiry where the decisive issue needs testing. Contested highway safety evidence, a viability dispute, a heritage balance with competing expert views, or an authority whose reason for refusal rests on an assertion you want to probe. Where the dispute is about the application of policy to facts both parties agree on, written representations is quicker and the inspector gets the same material.

One practical signal. If your case needs the inspector to disbelieve something the council has said, you want the opportunity to question it. If your case needs the inspector to read a policy properly, paper is enough.

The deadline and the start date

Two dates control everything. The deadline for lodging the appeal runs from the date on the decision notice, and the Inspectorate issues a start date once it validates the appeal, with the timetable attached.

Most section 78 appeals must be lodged within six months of the decision notice date. Householder and minor commercial appeals have twelve weeks. Work backwards from that date, because the full case normally goes in with the appeal rather than later.

Stage What you file Practical note
Lodging Appeal form, grounds or statement of case, application documents, decision notice, drawings, ownership certificate Incomplete appeals are returned, and the clock does not stop while you fix them
Start date Nothing Read the timetable the day it arrives and diarise every date
Authority's stage Nothing from you Read the questionnaire and statement for new or withdrawn reasons
Final comments A short reply on points of difference Not a second statement, and not a place for new evidence

Structuring the statement of case

Follow the decision notice. Take the reasons for refusal in their numbered order and give each one its own section, because any other structure forces the inspector to reassemble your argument.

Within each section, a reliable pattern is this. State the reason as written. Identify the development plan policy and the national policy relied on, naming the National Planning Policy Framework edition. Set out the facts. Then state the conclusion on that reason and the weight it should carry.

Keep the site description and planning history in a single early section and never repeat them. Put the policy list in an appendix rather than quoting at length in the text. And resist the temptation to argue matters the authority did not refuse on, because every paragraph spent on an undisputed point dilutes the ones that matter.

Where the application was supported by a Planning Statement and a Design and Access Statement, the appeal statement should build on them rather than restate them. Say where the earlier document dealt with a point, cite the paragraph and move on.

Core documents and how to reference them

A core documents list is the single highest-value piece of housekeeping in a paper appeal. It is a numbered schedule of everything the inspector may need, with each item given a reference you then use throughout the statement.

  • Decision notice and officer report, including the committee minute where members departed from the recommendation
  • Application form, ownership certificate and the drawings as submitted, with revision numbers
  • Supporting documents submitted with the application, listed individually rather than as a bundle
  • Development plan extracts, limited to the policies in dispute, with the adoption date
  • Any supplementary planning document or design guide relied on
  • Appeal decisions you rely on, with the appeal reference and date
  • Technical reports commissioned after refusal
  • Photographs, with a plan showing the viewpoint and the date each was taken

Reference by document number and page, not by document name alone. A statement that says "see CD7, page 12" is checkable. A statement that says "as set out in the drainage report" is not, and an inspector working through twenty documents will not hunt.

Date-stamp photographs and say which season they show. A February site visit against August photographs of a screened boundary is one of the more common unforced errors in amenity appeals.

Dealing with interested party representations

The authority forwards the representations made on the application and the Inspectorate notifies interested parties, who may write in during the appeal. Read them all, then triage.

Answer material planning points with evidence. Note briefly, once, that the remainder are not material: loss of a private view, effect on property values, boundary ownership, the identity of the applicant, and matters governed by other regimes such as party wall or rights of light. Do not answer them individually.

Where an objection raises something material that the council did not refuse on, deal with it properly. An inspector who spots an unanswered material point will consider it whether or not it appears in the reasons for refusal. Where pre-application engagement took place, a short account of it helps, and the approach set out in a neighbour engagement template gives you something to point to.

Conditions, obligations and costs applications

Submit a schedule of suggested conditions with the appeal. Inspectors expect it, it signals that you have thought about implementation, and it gives you influence over the wording of conditions you will have to live with. Draft them against the six tests in the Planning Practice Guidance on conditions: necessary, relevant to planning, relevant to the development, enforceable, precise and reasonable in all other respects.

Where an obligation is needed, get the draft deed or unilateral undertaking in during the timetable rather than after it. An appeal allowed subject to an obligation that was never completed is a decision nobody can implement.

If you intend to apply for costs, make the application in writing within the timetable and set out the behaviour, the limb of the guidance and the wasted expense. It belongs in a separate document, not buried in the statement of case.

Where the issue is really a drafting problem with an existing permission rather than a refusal, check whether a non-material amendment request solves it faster than an appeal.

An illustrative bundle index

The following index is illustrative, for a refused pair of dwellings on an infill plot with three reasons for refusal.

  1. Statement of case, paginated, with a contents page and a one-page summary of the case on each refusal reason
  2. Appendix A: core documents list, numbered CD1 to CD18
  3. CD1 to CD4: decision notice, officer report, committee minute, application form and certificate
  4. CD5 to CD9: drawings as submitted, by number and revision, with a site location plan at a stated scale
  5. CD10 to CD12: development plan policy extracts in dispute, with the adoption date on each
  6. CD13 to CD15: arboricultural report, surface water drainage note and highway technical note commissioned after refusal
  7. CD16 to CD18: two appeal decisions relied on, and the authority's own design guide extract
  8. Appendix B: photograph sheets, each with a viewpoint plan and date
  9. Appendix C: schedule of suggested conditions
  10. Separate document: application for an award of costs, if one is being made

Paginate continuously, submit a single searchable file per document, and name files so they sort in the order of the index. Small discipline, measurable effect.

If you are rebuilding the evidence base for the appeal, you can see which reports the case is likely to need and draft the supporting statements as a starting point for your own review.

This is general guidance, not legal advice. Check the position with a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What documents must go in with the appeal?

The appeal form and grounds, the application form and ownership certificate, the drawings as submitted with their revision numbers, the decision notice and the supporting documents that went to the council. Incomplete appeals are returned and the lodging deadline does not pause while you fix them, so check the list before submitting.

What is a core documents list?

A numbered schedule of every document the inspector may need, each given a reference used throughout the statement of case. It lets you write see CD7 page 12 instead of naming a document and hoping the inspector finds the passage. It is the most useful piece of housekeeping in any paper appeal.

Should I submit suggested conditions?

Yes. A schedule of suggested conditions shows you have thought about implementation and gives you influence over wording you will have to live with. Draft them against the six tests in the Planning Practice Guidance: necessary, relevant to planning, relevant to the development, enforceable, precise and reasonable in all other respects.

How should I handle neighbour objections?

Answer the material planning points with evidence. Note once, briefly, that the remainder are not material planning considerations, covering matters such as loss of a private view, property values and boundary ownership. Where an objection raises a material point the council did not refuse on, deal with it properly, because the inspector will consider it anyway.

Can I put new evidence in the final comments?

No. Final comments are a short reply on the points of difference with the authority's statement, not a second statement of case and not a route for new technical evidence. Anything your case depends on belongs in the material submitted with the appeal itself.

Sources and further reading

planning appealswritten representationsstatement of caseappeal bundlechecklistplanning inspectorate

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →