Class Q prior approval: assembling the submission

7 min readBy PlanScope Editorial Team

Class Q submissions fail on missing evidence. The gateway tests, the agricultural history bundle, the structural conclusion officers need and the drawing pack.

A Class Q prior approval submission is refused more often for missing evidence than for bad design. The council has 56 days, it can only consider the matters the Order lists, and if the structural position or the agricultural history is not proven on the papers, the answer is no. Assembling a Class Q prior approval submission is therefore a document exercise as much as a design one, and the order in which you build the file matters.

Confirming the building qualifies

Class Q sits in Part 3 of Schedule 2 to the Town and Country Planning (General Permitted Development) (England) Order 2015, and it permits the change of use of an agricultural building and land within its curtilage to dwellinghouses, together with the building operations reasonably necessary to convert it.

The gateway tests come first, and any one of them ends the matter.

  • The building must not be listed, and must not be a scheduled monument.
  • The site must not be on article 2(3) land, which takes out conservation areas, National Parks, National Landscapes and World Heritage Sites.
  • The building must have been in agricultural use as part of the relevant qualifying period set by the Order.
  • The scheme must sit within the numerical limits on dwellings and floorspace.

Class Q was amended with effect from 21 May 2024, and the current limits allow a larger number of dwellings and a higher total floorspace than the original version, with a cap on the size of each individual dwelling. Read the consolidated Order on legislation.gov.uk before you rely on any figure, including one quoted in an older article or a planning consultant's template, because the thresholds and the qualifying date have both moved.

Evidence of the agricultural use history

This is the part landowners underestimate. An assertion that the building "has always been agricultural" carries no weight. What works is a bundle:

  1. Rural payments or subsidy records naming the holding and the relevant years.
  2. Invoices for feed, fertiliser, seed, livestock or contracting work referable to the building.
  3. Veterinary records or movement records where livestock were housed.
  4. Dated photographs showing agricultural use, ideally with machinery or stock visible.
  5. Aerial imagery from the relevant years.
  6. A statutory declaration from the owner or a former farm manager, setting out the history in dates.

Where the building was let, the tenancy agreement and rent records do useful work. Where the use ceased some years ago, say so plainly and address the qualifying date directly rather than hoping the officer does not check.

The structural report and what it must show

Class Q allows conversion. It does not allow rebuilding dressed as conversion, and that distinction has been the subject of appeal and High Court consideration. The practical consequence is that the building must be capable of taking the conversion works without substantial reconstruction.

A structural appraisal should state the existing construction, frame type and condition, the foundations as far as they can be established, whether the frame can carry the loads of the proposed roof, floors and openings, what remedial work is needed, and a clear statement that the building is capable of conversion. Where a new frame, new foundations and new walls are needed, the honest conclusion is that Class Q does not apply and a full application for a replacement building is the route.

Keep the engineer's drawings consistent with the architect's. A Structural Survey that describes a steel portal frame while the proposed sections show new blockwork carrying the roof is the inconsistency officers notice first.

Drawings of existing and proposed

The drawing pack should leave nothing to inference. Include a site location plan with the red line and the curtilage identified, a block plan showing the building, access, parking and any residential curtilage proposed, existing plans and elevations measured on site, proposed plans and elevations at the same scale, and a demolition drawing showing exactly which elements of the existing fabric are removed.

That last drawing is the one that decides borderline cases. Shade what stays, shade what goes, and give the percentages of external wall and roof being retained. An officer who can see that 85 per cent of the frame and envelope is retained has an easy decision to make.

Design and external appearance

Design is one of the matters for prior approval, so it is assessable, but the test is narrower than in a full application. Officers are looking at whether the external appearance is acceptable in its rural context rather than applying the whole of a design guide.

What tends to work on a former agricultural building is restraint. Keep the large openings where the doors were, use recessed glazing rather than flush, keep materials simple and agricultural in character, avoid domestic detailing such as fake shutters and porches, and keep the curtilage small and undemonstrative with a simple gravel yard rather than a suburban garden with fencing and ornamental planting.

A short statement explaining those choices helps. It does not need to be a full Design and Access Statement, which is not required for prior approval, but two or three pages setting out the approach to the elevations, materials and curtilage is worth writing.

Transport, flooding, noise and contamination information

The Order lists the matters the council may consider, and each needs a proportionate answer in the file.

Matter What to provide
Transport and highways Access geometry, visibility splays measured on site, parking layout, and a short note on trip generation
Noise Distance to working farm buildings, grain driers, livestock housing and roads, with mitigation where needed
Contamination History of the building's use, fuel and chemical storage, sheep dip, asbestos, and a desk study where indicated
Flooding Flood zone from the published map, finished floor levels and any resistance measures
Location or siting Access to services, the practicality of residential use in that location
Design and external appearance Elevations, materials and curtilage treatment

Two of those are the usual killers on working farms. Noise and odour from the adjoining agricultural operation can make residential use unsuitable, and a grain drier 20 m from a proposed bedroom window is a genuine problem rather than a drafting one. And a site in Flood Zone 3 will usually need a Flood Risk Assessment and may still fail.

Where the visibility splay cannot be achieved from the existing farm access, a Transport Statement showing what can be achieved, with the land available to deliver it, is better than silence. Where fuel tanks, a workshop or asbestos sheeting are present, a desk study referencing a Land Contamination Phase 1 approach is proportionate, and land contamination work requires a suitably qualified and experienced person under the standards councils apply.

Fee, forms and the determination period

The application is a prior approval application submitted with the prescribed fee, which is indexed, so check the current fee schedule rather than an old figure. The determination period is 56 days from the day after a valid application is received, and if the council fails to determine within it, the development may proceed subject to the Order's conditions.

Three procedural points worth knowing. The council will consult neighbours and the parish council. It can request further information, and the 56 days does not restart, so a file with gaps is a file that runs out of time. And a refusal can be appealed, with the appeal considering only the matters the Order permits.

Build the bundle in this order: gateway checks, agricultural history evidence, structural appraisal, measured survey, drawings including the demolition drawing, then the technical notes on transport, noise, contamination and flooding, then the short design statement. A Planning Statement pulling those threads together in six or seven pages makes the officer's report easy to write, which is the outcome you want.

This is general guidance, not legal advice; permitted development rights change, and the position should be checked against the current Order and with your local planning authority or a qualified professional. A lawful development certificate is the only formal way to confirm that works or a use are lawful. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How many dwellings does Class Q allow?

The limits were raised with effect from 21 May 2024, allowing a larger number of dwellings and a higher total floorspace than the original version, with a cap on each individual dwelling. Because the thresholds and the qualifying date have both changed, take the figures from the consolidated Order on legislation.gov.uk rather than from an older summary.

What evidence proves the agricultural use?

A bundle rather than a statement. Rural payments records, invoices for feed, fertiliser or contracting, livestock movement or veterinary records, dated photographs, aerial imagery and a statutory declaration setting out the history by year. Tenancy agreements and rent records help where the building was let to someone else.

Can a derelict barn be converted under Class Q?

Only if it can take the conversion works without substantial reconstruction. Class Q permits conversion, not rebuilding, and appeal and court decisions have drawn that line firmly. Where new foundations, a new frame and new walls are needed, apply for a replacement building instead and expect to argue the countryside policy tests.

What can the council actually consider?

Only the matters the Order lists: transport and highways, noise, contamination, flooding, whether the location makes residential use impractical or undesirable, and design and external appearance. Broader policy objections are outside the scope, which is why a file that answers each listed matter directly is hard to refuse.

What happens if the council misses the 56 days?

The development may proceed subject to the conditions in the Order, which is why the clock matters. Requests for further information do not restart it, so submitting an incomplete file works against you. Keep a dated record of the valid submission and the acknowledgement.

Sources and further reading

class qpermitted developmentbarn conversionprior approvalrural planning

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →