Commuted sums and how they are calculated

6 min readBy PlanScope Editorial Team

Commuted sums come out of published formulas, so the arguments that work are about inputs, indexation base dates and payment triggers rather than about whether a sum is payable.

A commuted sum in planning is a payment made to the local authority instead of providing something on site. Most often it replaces affordable housing, but the same mechanism covers open space, play space, parking, highway maintenance after adoption and public art. The figure is rarely negotiable in principle, because it usually comes out of a published formula in a supplementary planning document, and the arguments that succeed are about inputs rather than about whether a sum is payable.

What a commuted sum replaces

The starting position in national policy is that affordable housing should be delivered on the site that generates the need. Off-site provision or a financial contribution of broadly equivalent value is acceptable only where it can be justified and where the agreed approach contributes to creating mixed and balanced communities.

That framing matters. A commuted sum is the exception, so the applicant has to make the case, and the case has to be about the site rather than about convenience.

The most common justifications are practical. A scheme too small to deliver a viable affordable unit. A site where a registered provider will not take one or two units because management costs make them unattractive. A conversion where the unit types do not meet affordable housing standards. A scheme where the tenure mix sought cannot be accommodated in the building form permitted.

Other commuted sums work differently. Open space and play space payments arise where a scheme cannot provide the quantum the standard requires within its own boundary. Highway commuted sums cover the cost of future maintenance once a new street is adopted, and they are calculated by the highway authority on its own basis rather than by the planning department.

Common formulas published in supplementary documents

Most authorities publish the method. Three approaches dominate for affordable housing.

Approach How the figure is built
Value gap Open market value of the units foregone, less the price a registered provider would pay, multiplied by the number of units
Cost of provision The cost of delivering the equivalent units elsewhere in the district, including land
Per square metre tariff A published rate per square metre of market floorspace, sometimes banded by value area

Open space and play space payments are usually a rate per person, per dwelling or per square metre of shortfall, with separate figures for capital provision and for a maintenance period of a stated number of years.

Find the document before you design the scheme. The formula tells you what the sum will be, which means it also tells you at what point providing on site becomes cheaper than paying. On some sites that calculation changes the layout.

Where the scheme falls under the national small sites threshold for affordable housing contributions, check whether the authority has adopted a lower threshold in designated rural areas, because that is a common trap on sites just outside a village. The relationship between those areas and the plan's settlement boundaries is worth checking at the same time.

Indexation and payment triggers

Two mechanical points decide what you actually pay.

Indexation ties the sum to a published index, commonly a construction tender price index or a house price index, running from a stated base date. The base date is negotiable and matters more than people expect. A sum indexed from the date of the supplementary planning document is larger than the same sum indexed from the date of the agreement.

Payment triggers set the cashflow. Common formulations are payment on commencement, payment on first occupation, payment on occupation of a stated proportion of the units, or payment in instalments tied to phases. On a scheme of any size, an instalment trigger linked to occupations is materially better than a single payment on commencement, because it aligns the outflow with sales receipts.

Ask for both in the heads of terms rather than at engrossment. Once a draft agreement has been circulated internally, changing the trigger takes longer than it is worth.

Arguing for a sum rather than on-site provision

Where you want to pay rather than build, evidence the reason.

  • Correspondence with registered providers declining the units, with their reasons stated.
  • A schedule showing why the unit sizes or types cannot meet the authority's affordable housing standards.
  • Management and service charge evidence where a small number of affordable units in a private block would carry disproportionate costs.
  • Design evidence where the building form cannot accommodate separate access or the required tenure separation.

An Affordable Housing Statement should carry this material and reach a clear conclusion rather than presenting options. Where the argument is that on-site provision makes the scheme unviable, that is a different case entirely and belongs in a Viability Assessment prepared on the authority's stated methodology.

Where a council will refuse a payment

Some authorities will not accept a commuted sum for affordable housing at all above a stated scheme size, on the ground that mixed communities are the policy objective and money does not deliver them. Others will refuse where they have no pipeline to spend it on, or where past sums have gone unspent.

That second point is the one applicants can use. Where a council cannot show how a sum would be spent, the obligation is harder to justify against the statutory tests, and the answer may be on-site delivery of something smaller rather than a payment at all.

Open space payments attract the same question. A payment for off-site provision needs an identified project, and an Open Space Assessment that identifies where the money goes strengthens the case for accepting a sum rather than squeezing an unusable strip of amenity land into the layout.

Securing it in the obligation

The agreement should state the sum or the formula, the index and base date, the trigger, the interest rate on late payment, the purpose for which the money may be spent, the period within which it must be spent, and what happens if it is not.

That last clause is the one to press for. A clawback provision returning unspent money after a stated period, commonly five or ten years, is standard in many authorities and reasonable in all of them. Without it the payment disappears into a reserve.

Also check whether the sum is index-linked from a date before the agreement is signed, whether VAT is payable, and whether a monitoring fee is charged on top. Each of those has produced an unwelcome surprise at completion for somebody.

Budgeting the cashflow

A commuted sum is an early cost and an uncertain one, because indexation moves it between appraisal and payment. Treat it as a fixed outflow at the trigger point, index it forward in the appraisal at the same rate as the agreement specifies, and hold the difference as a contingency.

On small schemes the sum can be a large proportion of the margin, which is why the calculation belongs in the appraisal before the land is bought rather than after permission is granted. And where the choice between paying and building is close, remember that on-site units are sold once, whereas the sum is paid regardless of how the market moves.

PlanScope drafts the supporting statements that sit behind a contributions package, including the affordable housing and viability documents, from your scheme details. Browse the report types to see what a residential application usually needs.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is a commuted sum in planning?

A payment to the local authority instead of providing something on site, most often affordable housing, but also open space, play space, parking and highway maintenance after adoption. National policy treats on-site affordable housing as the starting point, so a commuted sum is an exception the applicant has to justify by reference to the site itself.

How is an affordable housing commuted sum calculated?

Usually by a published formula in a supplementary planning document. Three approaches dominate: the gap between open market value and the price a registered provider would pay for the units foregone, the cost of delivering equivalent units elsewhere including land, or a published rate per square metre of market floorspace, sometimes banded by value area.

Why does the indexation base date matter?

Because it determines how much the figure grows before you pay it. A sum indexed from the date of the supplementary planning document will be larger at payment than the same sum indexed from the date of the agreement. The base date is negotiable, so raise it in the heads of terms rather than after a draft agreement has circulated.

Can I pay in instalments?

Often, if you ask early. Triggers range from payment on commencement to payment on occupation of a stated proportion of units, or instalments tied to phases. On any scheme of size, instalments linked to occupations align the outflow with sales receipts far better than a single payment on commencement. Agree it at heads of terms stage.

Can a council refuse to accept a commuted sum?

Yes. Some authorities decline payments above a stated scheme size on the ground that mixed communities are the policy objective and money does not deliver them. Where a council has no identified project to spend the money on, that weakens its case for the obligation, and smaller on-site delivery may be the better outcome.

Sources and further reading

commuted sumssection 106affordable housingdeveloper contributionsviability

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary8 min read

Root protection area: how the BS 5837 radius is set

The root protection area is a radius of 12 times stem diameter, capped at 707 m2. How to measure it, reshape it defensibly and show it on the drawings.

Read article →
Glossary7 min read

Material operations and the moment development begins

Development begins on the earliest date a material operation listed in section 56(4) is carried out. An undischarged pre-commencement condition can defeat an otherwise valid start.

Read article →
Glossary6 min read

Prior approval: the application that is not quite one

The permission already exists. A prior approval application only determines the matters the class lists, which is both the attraction of the route and its main trap.

Read article →
Glossary6 min read

Planning obligation: when a contribution may be required

Regulation 122 sets three statutory tests for any planning obligation. The most useful question in a contributions negotiation is which limb a given ask satisfies.

Read article →
Glossary7 min read

Section 73 application: varying a condition in practice

Section 73 lets you vary conditions on a permission you already hold, but it cannot touch the description of development and it will not buy you more time.

Read article →
Glossary7 min read

Certificate of lawfulness for a proposed use or operation

Section 192 asks whether a proposed use or operation would be lawful, not whether it would be acceptable. The authority has no discretion to refuse on the merits, and the onus of proof is on the applicant.

Read article →