Discharging a condition satisfies it as written. Section 73 grants a new permission without it. The difference decides your fee, your timetable and whether obligations still bind.

The discharge of conditions vs section 73 question comes down to one thing: are you satisfying the condition as written, or changing what it says. An application for approval of details submits the information the condition asked for. A section 73 application asks for permission to develop without complying with the condition, and grants a fresh permission with the condition removed or reworded.

Architects meet both on the same project, often in the same month, and the fee and timetable consequences of picking the wrong one are worse than they look.

What approval of details involves

Conditions requiring something to be submitted and approved are discharged by application to the local planning authority under the Development Management Procedure Order 2015. You identify the permission, list the conditions you are discharging, and submit the material each one asks for.

The authority either approves the details, refuses them, or asks for more. The determination period is eight weeks, though most straightforward discharges are decided faster where the submission is complete.

Two habits make this go well. Submit one application per group of related conditions rather than one covering everything, because a bundled application moves at the speed of its slowest consultee. And address each condition under its own heading with its own document list, so the officer can sign off the ones that are ready.

The decision does not change the permission. It records that a requirement has been satisfied.

When a condition cannot be complied with as drafted

Sometimes the condition asks for something the scheme can no longer deliver. The approved materials are discontinued. The approved window detail conflicts with the Part L calculation. The condition ties development to a drawing number that has been superseded.

That is section 73 territory. Section 73 of the Town and Country Planning Act 1990 allows an application to develop without complying with conditions previously imposed, and if granted it creates a new planning permission that sits alongside the original rather than replacing it.

Three limits are worth knowing before you start.

You cannot use section 73 to change the description of development. The Court of Appeal decision in Finney v Welsh Ministers settled that, and an application that would alter the description will be refused or treated as invalid.

You cannot use it to extend the time limit for implementation. Section 73(5) rules that out directly.

And the new permission is a separate permission, so any obligations under a section 106 agreement attached to the original do not automatically follow. A deed of variation is usually needed, and that is the step most often forgotten.

The Levelling-up and Regeneration Act 2023 inserted a further route, section 73B, allowing variations where the effect would not be substantially different from the existing permission, including changes to the description. Check the commencement position and any transitional arrangements before relying on it, because the practical availability of that route has moved.

Fees and determination periods for each

Feature Approval of details Section 73
What it does Satisfies a condition as written Grants a new permission without the condition, or with it reworded
Outcome Approval, refusal or request for more information A new planning permission with a new reference
Statutory period Eight weeks Eight weeks for minor development, 13 for major
Fee Set nationally, lower for householder applications The application fee for the relevant category of development
Section 106 Unaffected Usually needs a deed of variation
Conditions None imposed The full set is re-imposed on the new permission

Both fees are set by national regulations and indexed annually, so check the current schedule on the Planning Portal rather than working from last year's figure.

That last row in the table causes real trouble. A section 73 decision re-imposes all the conditions, which means every condition you had already discharged on the original permission has to be discharged again on the new one unless the decision notice says otherwise. Ask the case officer to carry the discharged conditions across, in writing, before the decision is issued.

Deemed discharge and where it applies

Section 74A of the 1990 Act allows some conditions to be treated as discharged where the authority has not determined the application in time. The applicant serves a deemed discharge notice no earlier than six weeks after the application was received, and the discharge takes effect after a further period unless the authority determines the application first.

It is narrower than it sounds. A list of excluded categories in the Development Management Procedure Order takes a range of conditions out of the regime, including those attached to environmental impact assessment development and several subject areas where the consequences of a default approval would be serious.

Use it as pressure rather than as a plan. Serving notice tends to produce a decision, which is usually what you wanted.

Pre-commencement conditions and building first

Since the Neighbourhood Planning Act 2017 amendments, a local planning authority cannot impose a pre-commencement condition without the applicant's written agreement. That gives you a moment of influence at decision stage that is worth using, because renegotiating afterwards is harder.

Where a pre-commencement condition does exist, the consequence of starting work without discharging it is severe. Operations carried out in breach of a condition precedent can be treated as not lawfully commencing the permission, which in turn means the permission may expire unimplemented. That is the doctrine practitioners refer to as the Whitley principle, and it is the reason a contractor's early start on a site strip is a real risk rather than a paperwork issue.

Breach of a condition after commencement is enforceable by breach of condition notice, against which there is no appeal.

Evidence packs that get approved first time

Officers reject discharge applications for predictable reasons. Build the pack against them.

  1. Quote the condition in full at the top of each section, so the officer does not have to find the decision notice.
  2. Provide exactly what the condition asks for, in the format it specifies, and say where each requirement is met.
  3. Include any consultee sign-off the condition depends on, such as the highway authority's acceptance of a construction management plan.
  4. Use drawing numbers and revisions that match the approved set, and list superseded drawings explicitly.
  5. Where a sample or physical material is required, arrange the site visit before submitting rather than waiting to be asked.
  6. Name a contact who can answer a technical query within a day.

Point three is where most delays come from. A condition requiring approval in consultation with another body is only as fast as that body, and sending them the material in parallel saves weeks.

Sequencing both on one project

The order matters when you need both. Where a section 73 application is coming, do not spend money discharging conditions on the original permission that will be re-imposed on the new one.

Where work has already started under the original permission and the section 73 permission will be implemented instead, take advice on which permission the development is being carried out under, because a hybrid position is difficult to unwind. And where the variation is small enough, consider whether a non-material amendment under section 96A does the job instead, which is quicker and costs less but cannot be used for anything material.

For the wider question of which consent route to use in the first place, our comparisons of prior approval and planning permission and of lawful development certificates and planning permission cover the choices upstream of this one, and outline or full permission for a small site deals with how many conditions you end up with in the first place.

A well-drafted Planning Statement accompanying a section 73 application should explain what has changed, why, and why the effect is acceptable. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

Does a section 73 permission replace the original?

No. It creates a new planning permission that sits alongside the original, and the developer chooses which to implement. Because it is a separate permission, obligations in a section 106 agreement attached to the original do not automatically apply to it, so a deed of variation is usually required.

Can section 73 be used to change the description of development?

Not on the traditional route. The Court of Appeal decision in Finney v Welsh Ministers confirmed that section 73 cannot be used to alter the description of development. The Levelling-up and Regeneration Act 2023 inserted a new section 73B intended to allow wider variations, and the commencement position should be checked before relying on it.

Do discharged conditions carry across to a section 73 permission?

Not automatically. A section 73 decision re-imposes the full set of conditions on the new permission, so conditions already discharged on the original may need discharging again. Ask the case officer in writing, before the decision is issued, to carry the discharged conditions across or to word them accordingly.

What is deemed discharge?

Section 74A of the 1990 Act allows certain conditions to be treated as discharged where the authority has not determined the application in time. The applicant serves notice no earlier than six weeks after submission. A list of excluded categories in the Development Management Procedure Order takes many conditions out of the regime.

What happens if work starts before a pre-commencement condition is discharged?

Operations carried out in breach of a condition precedent can be treated as not lawfully implementing the permission, which may leave the permission to expire unimplemented. That is a far more serious consequence than an enforcement notice, and it is why an early site strip by a contractor is a real risk rather than a paperwork point.

Sources and further reading

planning conditionssection 73discharge of conditionsarchitectscomparisonsplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →
Comparisons7 min read

Building notice or full plans application to building control

Two routes to building control approval under the Building Regulations 2010. What each involves, where a building notice is unavailable, and how completion certificates and regularisation work.

Read article →
Comparisons8 min read

Dropped kerb approval or permission for a front hardstanding

The crossover is licensed under the Highways Act 1980. The driveway behind it is permitted development only if it is porous or drains inside your boundary. Most people need both approvals.

Read article →
Comparisons7 min read

Strategic Environmental Assessment or Sustainability Appraisal

A local plan appraisal discharges two duties at once: strategic environmental assessment under the 2004 Regulations and sustainability appraisal under section 19(5). Only one has sharp legal teeth.

Read article →
Comparisons7 min read

Environmental permit or planning permission for a waste use

The Environment Agency permits the operation. The waste planning authority decides whether the use belongs there. Both are needed, and a registered exemption is not a planning permission.

Read article →