Professionals and Qualifications

Disclosure of draft technical reports in an appeal

8 min readBy PlanScope Editorial Team

Nobody can require your superseded drafts. What they can do is ask the council for everything you sent it, which is where most problematic drafts come from.

There is no general duty of disclosure in a planning appeal. You are not in civil litigation, there is no standard disclosure stage, and nobody can require you to hand over every superseded draft on your file. What you do have is a duty not to mislead, a Planning Inspectorate expectation that you put forward the full particulars of your case, and a third party's right to request what you sent the council under the environmental information regulations. Draft report disclosure in an appeal is governed by that combination rather than by any single rule.

The practical consequence is counterintuitive. The documents most likely to surface are not the ones an opponent demands from you. They are the ones you emailed to the case officer eighteen months ago.

What has to be disclosed and when

Appeals under section 78 of the Town and Country Planning Act 1990 run on a documents timetable set by the procedure. Written representations, hearings and inquiries each have their own rules, but the structure is similar: a statement of case, then supporting evidence, then in an inquiry proofs of evidence and appendices, all by stated deadlines.

What the Inspectorate expects is that your statement sets out the full particulars of the case you intend to put. Evidence introduced late can be refused, and an inspector can decline to take account of material produced at a hearing that should have been in the statement. That is a rule about completeness of your own case, not about producing your opponent's.

Separately, every document you submitted to the local planning authority during the application sits on the authority's file. It is almost certainly environmental information under the Environmental Information Regulations 2004, and the authority has to disclose it on request subject to the exceptions in those regulations. Objectors use this routinely. An earlier version of a noise survey, sent informally to an officer and then superseded, is obtainable by anyone who asks the council for it.

Drafts, privilege and the limits of it

Legal advice privilege protects communications between you and your lawyers for the purpose of giving or receiving legal advice. That is real and it holds.

Litigation privilege, which protects documents prepared for the dominant purpose of adversarial litigation, is a different and much less certain proposition in planning. Appeals to the Inspectorate are administrative determinations rather than litigation in the ordinary sense, and the application of litigation privilege to them should not be assumed. If the question matters to a document on your file, take specialist legal advice on it rather than relying on a general sense that drafts are privileged. They are usually not.

What protects an ordinary technical draft is something simpler: nobody has a right to ask for it, and it was never sent to the council. A draft that lived between consultant and client, was superseded, and never left the project team, is not disclosable by any route.

A draft that was sent to the authority is a different matter, and so is a draft that is referred to in a document you are relying on. Cite an earlier survey in your proof of evidence and you have put it in issue, and an inspector can ask for it.

Adverse findings and the duty not to mislead

This is where professional obligations do real work.

The RTPI Code of Professional Conduct requires members not to make statements that are misleading, and the RICS Rules of Conduct impose comparable duties. Anyone giving expert evidence at an inquiry is expected to give their own independent opinion and to refer to the material facts that detract from it. Those duties bite whether or not any disclosure rule applies.

So the position on a survey with an inconvenient result is not "can I withhold it" but "can I present my case honestly without it". Often the answer is no. A transport assessment that reports a junction capacity result without mentioning the earlier count that showed worse performance is not a complete account, and an inspector who learns about the earlier count from an objector will treat everything else in that evidence with suspicion.

The better approach is almost always to put the adverse material in and explain it. Surveys get superseded for good reasons: the wrong period was counted, the methodology changed, the scheme changed. Say that. An explained inconsistency is a technical matter. A discovered omission is a credibility matter, and credibility is the one thing you cannot recover mid-inquiry.

Where two reports in your own submission disagree, resolve it before you get to appeal. The same applies when the authority's own adviser takes a different view, and the approach set out in what to do when the council's expert disagrees with your consultant belongs at application stage rather than at the inquiry.

Requests from the authority

Authorities do ask. The common forms are a request for the earlier version of a report referred to in a later one, a request for the raw survey data behind a model, and a request for the ecologist's field notes.

Raw data requests are usually reasonable and usually worth meeting. A noise consultant's measurement records, a transport consultant's turning counts, an ecologist's survey forms: these are the evidence behind the conclusion, and refusing them invites the inspector to give the conclusion less weight. Supply them as an appendix.

Requests for drafts are different and can be declined, politely and with a reason: that the document is superseded, that the final version is before the inspector, and that the conclusions in the final version are the ones being relied on. Do that in writing so the record shows a considered position rather than evasion.

What you should not do is deny that a draft exists. If an objector has already obtained it from the council under an environmental information request, which happens, the denial is the problem rather than the draft.

How inspectors react to withheld material

Inspectors have no power to order disclosure in the way a court does, but they have the power that matters: they decide what weight to give evidence.

A pattern that recurs in appeal decisions is an inspector noting that a conclusion was not supported by the underlying data, or that a point put to a witness was not satisfactorily answered, and attaching reduced weight to that evidence as a result. Inspectors also have the power to require the attendance of witnesses and the production of documents at an inquiry under the relevant procedure rules.

Appeal decisions are indicative of how inspectors have approached these issues rather than binding precedent, but the pattern is consistent enough to plan around. Evidence that can be audited is given weight. Evidence that cannot is discounted.

There is also a costs dimension. Unreasonable behaviour in an appeal can lead to an award of costs, and obstructing a reasonable request for the data behind your own evidence is the kind of conduct that gets described that way.

Managing drafts during a project

Document discipline costs less than argument. Six habits cover most of the risk:

  1. Agree at the outset which documents go to the authority and which stay internal, and route everything through one person.
  2. Do not send working drafts to the case officer. Send a version marked as issued, with a revision and a date, or send a note instead.
  3. Where you need an officer's view on an emerging finding, put the question in a letter rather than attaching the half-finished report.
  4. Keep superseded versions, with a short note of why each was superseded. Destroying them is worse than holding them.
  5. Maintain a document register for the project: every version, its date, who it went to and whether it is current.
  6. When a finding changes materially, write a one-page explanation at the time. Reconstructing the reason two years later is unconvincing even when it is true.

The second habit is the one that saves the most trouble. Most problematic drafts reach the authority because a consultant wanted to be helpful.

Practical document discipline before an appeal

When an appeal is decided on, do a file review before the statement of case is drafted. List every version of every technical document, mark which went to the authority, and identify where the conclusions changed between versions.

Then decide, deliberately, what the appeal case relies on. Where a change of conclusion has to be explained, explain it in the statement rather than waiting to be asked at the hearing. Where a report has a named author whose competence may be questioned, make sure the report carries a named author and a date and that the author is available. Where the authorship has moved during the project, the record built up in changing consultant mid-application without losing evidence is what keeps the chain intact.

Finally, assume the objector has a copy of everything the council holds. Plan the case on that basis and the disclosure question mostly disappears.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. Where privilege or professional conduct is in issue, take specialist legal advice. If you need a qualified reviewer to check a technical report before it goes into an appeal, the professional directory is the route to a review and sign-off.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is there a duty of disclosure in a planning appeal?

Not a general one. Appeals are administrative determinations rather than civil litigation, so there is no standard disclosure stage. What applies instead is the expectation that your statement of case sets out the full particulars of your case, the professional duty not to mislead, and third party rights to request documents from the council.

Are draft consultant reports privileged?

Usually not. Legal advice privilege protects communications with your lawyers and holds firm. Litigation privilege is of uncertain application to Planning Inspectorate appeals and should not be assumed. What protects an ordinary technical draft is that nobody has a right to ask for it and it never left the project team.

Can objectors get hold of documents I sent the council?

Yes, in most cases. Documents held by the authority are almost certainly environmental information under the Environmental Information Regulations 2004 and must be disclosed on request, subject to the exceptions. Objectors use this routinely, so an informally emailed early draft of a survey is obtainable by anyone who asks.

Should I disclose a survey with an adverse result?

Usually yes, with an explanation. Surveys get superseded for good reasons, and an explained inconsistency is a technical matter. A discovered omission is a credibility matter, and credibility is what you cannot recover mid-inquiry. Expert witnesses are also expected to refer to material facts that detract from their opinion.

Can an inspector order me to produce a document?

Inspectors have power under the inquiry procedure rules to require the attendance of witnesses and the production of documents. More significantly, they decide what weight evidence carries. Evidence that cannot be audited against its underlying data is routinely given reduced weight, which achieves the same result as an order.

Should I supply raw survey data if the council asks?

Usually yes. Measurement records, turning counts and ecological survey forms are the evidence behind your conclusion, and refusing them invites the inspector to give the conclusion less weight. Unreasonable obstruction can also feature in a costs application. Requests for superseded drafts can be declined politely, in writing, with a reason.

Sources and further reading

planning appealsdisclosureexpert evidenceprofessional conductplanning consultant

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Professionals and Qualifications

View all →
Professionals and Qualifications7 min read

When two consultants' reports contradict each other

If the transport assessment counts 48 units and the energy statement counts 52, the officer concludes nobody checked. The fix takes an hour before submission.

Read article →
Professionals and Qualifications7 min read

When a council asks for the report author's CV

Validation lists increasingly ask who wrote a technical report and what they are qualified to do. A one-page competence statement answers it without putting personal data on the public register.

Read article →
Professionals and Qualifications7 min read

Fee structures for planning and survey work

Two quotes for the same job are rarely for the same scope. The four fee structures, the exclusions that generate unexpected invoices, and the questions that let a self-builder compare offers on the same basis.

Read article →
Professionals and Qualifications6 min read

Planning agents acting without indemnity insurance

Nothing in law stops someone calling themselves a planning consultant or requires them to hold insurance. The four checks to make before appointing, the redress routes that work, and the clauses that should stop you signing.

Read article →
Professionals and Qualifications6 min read

Who can sign off a remediation verification report

No licence exists for signing a remediation verification report, so councils judge the author instead. The competence officers look for, the records the report must carry, and why the strategy is the place to settle it.

Read article →
Professionals and Qualifications8 min read

Sub-consultant chains and who carries the risk

One contract, four organisations, and no direct claim against the author of the report that matters most. How sub-consultant chains allocate planning risk.

Read article →