Electric vehicle charging in new residential development

6 min readBy PlanScope Editorial Team

Charge point numbers are now mostly a building regulations matter. What the planning layer still adds, and the decisions that have to be made before the slab is poured.

Electric vehicle charging is now mainly a building regulations requirement rather than a planning one. Approved Document S sets the baseline for new homes with parking, and the planning question on most schemes is whether the local plan asks for more than that, and whether the layout you have drawn can physically deliver it.

The two regimes are read by different officers and discharged at different times, which is why schemes still arrive on site with a parking court, no ducting and a distribution board with no spare ways.

What the regulations require

For new residential buildings, each dwelling with an associated parking space is required to have a charge point. Where there are fewer spaces than dwellings, charge points are provided for as many spaces as there are, and cable routes are installed for the remainder.

Residential buildings undergoing major renovation with more than ten parking spaces attract a similar requirement, at a lower level, and new non-residential buildings with more than ten spaces need at least one charge point plus cable routes for a proportion of the remaining spaces.

Two details shape the design. The minimum charge point rating is 7 kW, which is a 32 amp single phase supply per point, and there is a cost cap: where the cost of the connection upgrade exceeds the stated figure per dwelling, the requirement reduces to cable routes rather than live points. The cap is set in the Approved Document and is the reason a large flatted scheme may lawfully be built with ducts and no chargers.

Houses with their own parking

This is the straightforward case. A driveway or garage serving one dwelling gets a point, and the only real design questions are position and cable management.

Put the unit where a car parked in the space can reach the socket without the lead crossing a footway or the front door approach. On a narrow frontage plot, that usually means the wall nearest the road rather than the wall nearest the meter, and the run back to the consumer unit has to be allowed for in the first fix.

Tandem parking is the arrangement that fails in use. Two spaces one behind the other with a single point means the rear car cannot charge without moving the front one, and a second point or a longer tethered lead should be designed in rather than retrofitted.

Where the drive is steep or awkward, the charging position interacts with turning and gradient, which is covered in private drive geometry: gradients, widths and turning.

Communal parking courts and flats

Flats are where the difficulty sits, because the parking is unallocated, the electrical supply is communal and somebody has to bill for the electricity.

Three models are used. Allocated spaces with points wired to individual flats, which is simple to bill and inflexible. Communal points on the landlord supply with a billing platform, which is flexible and needs a management company. And a hybrid, with a handful of live communal points and ducting to every other space.

Whichever is chosen, the decisions that have to be made before the slab is poured are the same: duct routes with draw cords to every space, a distribution position with spare ways, and space in the plant or substation area for future capacity. Retrofitting a parking court means digging it up.

Ownership and maintenance belong in the management arrangements rather than in a note on a drawing. Who owns the point, who maintains it, who sets the tariff and what happens when a unit fails are all questions the first management company will ask.

Passive provision and what it actually means

Passive provision is a cable route and capacity, not a socket. Local plan policies commonly ask for a percentage of spaces with active charging and passive provision for the rest, and the London Plan is the most widely quoted example of that split.

The trap is that passive provision done badly is worthless. A duct with no draw cord, a route that crosses a structural element, or a board with no spare ways all mean the future installation involves the same excavation the duct was meant to avoid. Specify the duct diameter, the draw cord, the chamber positions and the spare capacity, and show them on a drawing rather than in a sentence.

State the assumed future load. A parking court with twenty passive spaces and a supply sized for four is passive provision in name only, and the network operator's answer in five years will be a new connection.

Capacity, the network operator and smart charging

Apply to the distribution network operator early. The connection offer determines whether the scheme can support live points at all, and on constrained networks the offer can take months and come back with a reinforcement cost.

Load management is the usual answer. Smart charge points are required to have functionality that allows charging to be shifted away from peak periods by default, and a managed charging system across a parking court lets a modest supply serve many points by spreading the load overnight.

Say so in the application. A transport officer reading a scheme with forty spaces and a small supply wants to know how it works, and a paragraph on load management in the Transport Statement answers the question before it is asked. Where a Travel Plan is required, the charging strategy and any car club provision sit naturally alongside it.

Accessible bays

Accessible charging has its own specification, and it is not the same as putting a point next to a blue badge bay. The published specification covers the space around the bay, the height and force needed to operate the unit, kerb upstands, the weight of the cable, surface finishes and lighting.

Design at least one accessible charging bay into any communal court and more where the scheme includes wheelchair user dwellings. The interaction with the rest of the parking allocation is covered in accessible and motorcycle parking in a new scheme.

Cable management matters more here than anywhere else. A lead lying across a bay is a trip hazard for everyone and an obstacle for a wheelchair user, so overhead or bollard-mounted retraction earns its cost.

Conditions and discharge

Planning should not duplicate the building regulations, and many councils have stopped conditioning charge point numbers for that reason. Plenty still do, either because the local plan policy predates the regulations or because the policy asks for more than the baseline.

Where a condition is imposed, the discharge submission needs a layout plan showing each point and each passive space, the specification including output rating and socket type, the duct and cable route drawing, the electrical capacity and load management strategy, and the management arrangements for communal points.

Submit it with the other pre-commencement discharges rather than separately. And check whether the condition duplicates the regulations, because a condition requiring what Part S already requires can usually be resisted at the drafting stage, which is easier than varying it later.

Design the ducts before the levels are fixed, apply to the network operator before the planning decision, and write the management arrangements before the first flat is sold. Those three steps remove almost every problem this subject generates. Where the scheme is large enough to need one, PlanScope drafts the transport documents in minutes, structured to UK planning policy, with the survey data flagged. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Does every new home need a charge point?

Each new dwelling with an associated parking space is required to have one under Approved Document S, with cable routes provided where there are fewer spaces than dwellings. A cost cap applies: where the connection upgrade exceeds the stated figure per dwelling, the requirement reduces to cable routes rather than live points.

What is the minimum charge point rating?

7 kW, which corresponds to a 32 amp single phase supply for each point. The socket type is specified in the Approved Document. Anything slower does not meet the requirement, and specifying a lower rated unit to fit an existing supply is a common way to fail a building control inspection late in the programme.

What counts as proper passive provision?

A duct of stated diameter with a draw cord, on a route that avoids structural elements, running to a chamber at the space, with spare ways at the board and supply capacity sized for the assumed future load. Shown on a drawing, not described in a sentence. Anything less means digging the parking court up later.

How do charge points work in a communal parking court?

Either wired to individual flats for allocated spaces, or on the landlord supply with a billing platform, or a hybrid with some live points and ducting to the rest. Whichever model is used, duct routes, board capacity and plant space have to be designed before construction, and the management company needs the ownership and tariff arrangements written down.

Will the council still condition EV charging?

Some do and some no longer do, since planning is not meant to duplicate the building regulations. Where the local plan asks for more than the regulations baseline, expect a condition. Check at drafting stage whether a proposed condition simply restates Part S, because resisting it then is easier than varying it later.

Sources and further reading

electric vehicleschargingpart sparkingresidential designbuilding regulations

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking6 min read

Temporary traffic orders for construction works

A construction programme usually needs four separate highway permissions, each under a different power. What each one covers, how long it lasts and what happens when works overrun.

Read article →
Transport, Highways and Parking8 min read

Highway drainage for a new rural access

Highway authorities treat run-off and material transfer onto a rural lane as a safety matter. The design comes down to the levels in the first few metres and the consent position for the roadside ditch.

Read article →
Transport, Highways and Parking7 min read

Car club and travel voucher contributions

The money is simple. The on-street bay needs a traffic regulation order the developer cannot deliver, and the operator may never come forward.

Read article →
Transport, Highways and Parking7 min read

Gated accesses and emergency service override

Three bodies have a view on a gated access: the highway authority, the fire service and the waste service. Design for all three before the driveway is drawn.

Read article →
Transport, Highways and Parking7 min read

Blocking back and queue length at a junction

A capacity ratio tells you how hard an arm is working. Only the queue in metres, compared against measured storage, tells you whether the junction behind will block.

Read article →
Transport, Highways and Parking7 min read

Which design vehicles to test in a swept path analysis

A tracking drawing is only as good as the vehicle chosen. The routine and occasional movements to test, and the parked car case most submissions omit.

Read article →