Energy, Sustainability and Carbon

Embodied carbon in retention against demolition

6 min readBy PlanScope Editorial Team

A retrofit first case is won on how the options appraisal is framed, not on the final carbon figure. Here is how to set the comparison up and what evidence survives committee.

The retention against demolition argument is won or lost on how the comparison is framed, long before anyone calculates a carbon figure. Compare a deep retrofit of the existing building with a new build of the same floor area on the same site, over the same study period, delivering the same functional performance, and you have an options appraisal a planning committee can use. Compare a modest refurbishment against a larger, better new building and you have two different projects with two different carbon totals, which proves nothing.

Authorities have become quick at spotting the second version. A growing number of adopted plans and supplementary documents expect a retrofit first case, and the ones with teeth ask for the appraisal before they ask for the carbon number.

Framing the comparison so it means something

Fix four things at the start and state them in the assessment.

The functional unit. Floor area, or usable area, or capacity measured some other way. If the new build delivers a third more area, the comparison has to normalise for that or present both absolute and normalised figures.

The study period. Sixty years is the convention in the recognised whole life carbon methodology, and using anything else needs a reason.

The modules assessed. Upfront embodied carbon in modules A1 to A5, in use emissions in the B modules including replacement cycles, end of life in the C modules, and benefits beyond the boundary in module D reported separately rather than netted off.

The options. Three or four, running from light refurbishment through deep retrofit and part retention to full demolition and rebuild. Two options looks like a case being built rather than a question being asked.

What retention typically saves

The savings sit in the substructure and the frame. Foundations, basements, slabs and structural frames are heavy, material intensive and carbon intensive, and they dominate the upfront embodied carbon of most buildings. Keeping them avoids the demolition emissions, the transport and disposal of the arisings, and the manufacture of their replacements.

Facade retention saves less than people assume, because facades are usually replaced or heavily reworked anyway for thermal performance, and the temporary works needed to hold a retained facade carry their own emissions.

The other side of the ledger is that retention rarely means keeping everything. A realistic retrofit involves new services throughout, a new envelope, new cores in many cases, and structural strengthening where loading or stability requires it. The Whole Life Carbon Assessment has to include all of that alongside the elements avoided.

The operational penalty, and why it is shrinking

The standard argument for demolition is that the existing building performs poorly and always will, so the operational emissions over 60 years outweigh the embodied carbon saved by keeping it.

That argument has been weakening, and the reason is grid decarbonisation. As the electricity grid decarbonises, the emissions attributable to operating an electrically heated building fall, which compresses the operational difference between a good retrofit and an excellent new build. Embodied carbon, by contrast, is spent now at today's emissions intensity. An appraisal that applies a flat grid factor across the whole study period will overstate the operational case for demolition, and a reviewer who knows the methodology will say so.

State the grid decarbonisation assumption explicitly, with the source and the trajectory used, and run a sensitivity case. That single paragraph does more for credibility than another decimal place on the embodied figure.

The constraints that do favour rebuild

There are buildings where retention is the wrong answer, and the appraisal is stronger for saying so clearly.

  • floor to ceiling heights too low to accommodate modern services and daylight requirements without losing storeys
  • structural capacity insufficient for the intended loading, where strengthening approaches the cost and carbon of replacement
  • deleterious materials or extensive asbestos requiring removal that compromises the structure
  • a grid or core arrangement that cannot deliver accessible, efficient layouts
  • a fabric whose condition means a shortened remaining life even after intervention

Evidence each of these with a Structural Survey and a condition survey rather than with assertion. A structural engineer's statement that a frame cannot take the additional load is evidence, and a developer's view that the building is tired is not.

The weakest ground is viability dressed as constraint. If the real reason is that retention delivers less area, say so and argue it on planning terms, because a committee will find the inconsistency between the technical case and the scheme drawings.

Presenting the appraisal

The document that works is short and sequential: the options considered, the assumptions common to all of them, the whole life carbon results by module for each, the operational performance of each, the planning benefits and harms of each, and a reasoned conclusion. Put the detailed calculation in an appendix.

Include a pre-demolition audit of the existing building so the materials that could be reused or recycled are quantified, which is what a Pre-redevelopment Audit covers, and set out the circular economy measures for whichever option is preferred. In London, a Circular Economy Statement is required for referable development and the expectations are set out in Greater London Authority guidance.

Where the scheme also generates significant new infrastructure, the carbon embedded in roads, drainage and utilities belongs in the picture as well, a point covered in our note on carbon in the infrastructure a scheme has to build.

Illustrative example: a 1970s office building with a concrete frame, 2.6 metre floor to ceiling heights and a failing curtain wall. The appraisal compares a deep retrofit retaining frame and substructure against full redevelopment delivering 30 per cent more floor area. Retention shows materially lower upfront embodied carbon, the retrofit achieves operational performance within a few per cent of the new build once the grid trajectory is applied, and the difference in area is argued separately as a planning matter. Illustrative only.

Evidence that survives committee

Three things make the difference when the report reaches a committee.

An independent review of the whole life carbon assessment, commissioned by the applicant or the authority, removes the suspicion that the numbers were chosen. Some authorities now require it for major applications.

Consistency between documents. If the structural report says the frame is sound and the carbon appraisal assumes replacement of the frame in a retention option, someone will notice.

And a conclusion that engages with the answer the analysis produced. An appraisal that runs the numbers, finds retention preferable on carbon, and then recommends demolition for reasons that were never assessed, is the version that gets deferred.

One honest uncertainty. There is no single national policy test that requires retention, and the weight given to embodied carbon still varies between authorities. What has changed is the expectation that the question is asked properly, with a methodology a reviewer can follow.

This is general guidance rather than legal advice. Check the position with your local planning authority or a qualified professional before relying on it, and note that whole life carbon assessment work should be prepared by a suitably qualified assessor.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. Browse the report types to see the documents a redevelopment case usually needs.

Frequently asked questions

What should a retention against demolition appraisal compare?

Three or four options on a common basis: light refurbishment, deep retrofit, part retention and full redevelopment. Fix the functional unit, the study period, the modules assessed and the performance standard before calculating anything, and normalise for any difference in floor area between options or present both absolute and normalised results.

Which parts of a building carry the most embodied carbon?

Substructure and frame dominate upfront embodied carbon in most buildings, which is why retaining foundations and structure delivers the largest savings. Facade retention saves less than expected, because facades are usually replaced or heavily reworked for thermal performance and the temporary works needed to hold a retained facade carry their own emissions.

How does grid decarbonisation affect the argument?

It weakens the operational case for demolition. As the electricity grid decarbonises, the emissions from operating an efficient electric building fall over the study period, compressing the difference between a good retrofit and a new build. Embodied carbon is spent at today's emissions intensity, so state the grid trajectory used and run a sensitivity case.

When is demolition the better answer on carbon grounds?

Where floor to ceiling heights cannot accommodate services and daylight, where structural capacity is insufficient and strengthening approaches the carbon of replacement, where deleterious materials require removal that compromises the structure, or where the remaining life of the fabric is short even after intervention. Evidence each point with a structural and condition survey.

Do I need an independent review of the carbon assessment?

Some authorities now require independent review of whole life carbon assessments on major applications, and offering one is useful even where it is not required. It removes the suggestion that assumptions were selected to reach a preferred answer, and it usually shortens the consultation stage because the reviewer has already dealt with the obvious questions.

Sources and further reading

embodied carbonretrofitwhole life carbondemolitioncircular economysustainability

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Energy, Sustainability and Carbon

View all →
Energy, Sustainability and Carbon7 min read

Grid capacity and a rural renewable scheme

On a constrained network the connection offer tells you what scheme is worth applying for. Treating it as an engineering matter for after permission is how capacity gets wasted.

Read article →
Energy, Sustainability and Carbon7 min read

BREEAM energy credits and the condition that secures them

A condition requiring a certified rating is really a condition requiring the low carbon specification to survive value engineering. How to set it up so it does.

Read article →
Energy, Sustainability and Carbon8 min read

Energy statements for a major refurbishment

A refurbishment energy statement has a real baseline and a constrained set of measures. How to establish both, and how to set up the demolition comparator honestly.

Read article →
Energy, Sustainability and Carbon8 min read

The energy hierarchy applied to a single self-build

One house does not need a major scheme's carbon modelling. What the local validation list actually asks for, and how to answer it in two or three pages.

Read article →
Energy, Sustainability and Carbon6 min read

Renewable energy requirements on employment units

A renewables percentage applied to a shell and core warehouse depends entirely on what it is measured against. How to settle the definition and draft a condition that can be complied with.

Read article →
Energy, Sustainability and Carbon7 min read

Solar panels on a pitched roof: permission and policy

Class A of Part 14 allows roof-mounted solar on a house, including the front slope and in conservation areas, subject to a 0.2 metre projection limit and conditions on appearance.

Read article →