Energy, Sustainability and Carbon

Evidencing a local plan renewable energy target

7 min readBy PlanScope Editorial Team

Whether a scheme meets an on site renewable target depends on what the policy measures and against what baseline. How to run the calculation and evidence a caveat.

A local plan renewable energy target looks like arithmetic and is usually a drafting exercise. Whether a scheme meets a policy requiring, say, a proportion of energy from on site renewable sources depends on what the policy measures, what baseline it measures against, and whether its feasibility caveat has been engaged with evidence rather than asserted. Get the reading of the policy wrong and a compliant scheme is reported as non compliant.

Start with the words, then the baseline, then the caveat. In that order.

Reading the policy wording precisely

Policies of this kind vary in four ways that change the answer.

What is measured. Energy, expressed in kilowatt hours, or carbon dioxide emissions, expressed in tonnes or kilogrammes. A policy targeting a percentage of energy from renewables is satisfied differently from one targeting a percentage reduction in emissions, because a heat pump running on grid electricity reduces emissions substantially while generating no energy on site.

Which energy. Regulated energy, meaning the fixed building services covered by the Building Regulations calculation, or total energy including unregulated loads such as appliances and lifts. The difference is large, and policies are often silent, in which case the supporting text or the authority's own guidance usually resolves it.

The baseline. Against the notional building in the current Part L calculation, against a stated earlier edition, or against a fixed figure in the policy. A target expressed against a superseded edition of Part L is a common drafting artefact in older plans, and how the authority treats it is a matter to settle at pre application stage.

And whether the requirement is absolute or qualified. "Development will provide" reads differently from "development will provide where feasible and viable". The second is the wording that most plans use, and most of the argument happens there.

The statutory basis for these policies is section 1 of the Planning and Energy Act 2008, which permits a local plan to include reasonable requirements for a proportion of energy used in development to be energy from renewable sources in the locality. Note the words "in the locality", which is what allows some authorities to accept off site provision.

Percentage targets and what they measure

Once the metric is settled, the calculation is mechanical, and the useful discipline is to show it as a table rather than a narrative.

Element Figure to state Source
Baseline regulated energy demand kWh per year Part L design stage calculation
Baseline emissions kg CO2 per year Same calculation, stated software and version
Demand after lean measures kWh per year Revised calculation
On site renewable generation kWp installed, kWh per year Array design with orientation and shading
Percentage achieved Against the policy metric Calculation shown
Residual shortfall If any, with the reason Options appraisal

Two traps. Quoting installed capacity in kilowatts peak as though it answered a question about energy, when the policy asks for a proportion of annual demand. And reporting the percentage without stating which denominator was used, which makes the figure unverifiable.

Name the software and its version. Assessment tools are updated and emission factors change between versions, so a figure without a version is not reproducible.

Feasibility and viability caveats in policy

The caveat is the most litigated part of these policies, and the reason is that applicants treat it as an exit and authorities treat it as a test.

A caveat requiring measures "where feasible" asks a technical question. Is the technology capable of being installed on this site, given the roof area, orientation, shading, structural capacity, grid connection and any constraint on the building. A caveat referring to viability asks an economic question, and on a scheme where other obligations are being negotiated it interacts with the wider viability position.

The distinction matters because the evidence differs completely. Feasibility is demonstrated with drawings and calculations. Viability is demonstrated with an appraisal, prepared to a recognised methodology, which the authority may have independently reviewed at the applicant's cost.

Do not conflate them. A statement that a target is "not viable" supported only by a roof area calculation will be read as a feasibility argument dressed in economic language, and an officer will ask for the appraisal.

Evidence needed to rely on a caveat

Relying on the caveat is legitimate. Relying on it without evidence is what loses applications.

For a feasibility argument, the material that works:

  • a roof plan showing the usable area after rooflights, plant, access zones, and any green roof required by other policies
  • orientation and pitch of each roof plane, with a shading analysis across the year
  • a structural note on the capacity of the roof as designed
  • the distribution network position where the array size approaches a connection threshold
  • for heritage constrained buildings, the conservation position on visible installations
  • an appraisal of each technology considered, with the reason each was excluded

That last item is the one officers look for and rarely find. A statement that photovoltaics are the only option considered, with no mention of solar thermal, heat pumps or a roof mounted alternative, reads as a decision taken before the assessment.

For a viability argument, the appraisal needs to be prepared to the recognised professional methodology and to isolate the cost of the renewable measures from the other matters in dispute. Where the scheme's viability case is being tested anyway, fold the renewable requirement into that exercise rather than running a separate argument. Phased sites raise their own sequencing problem, dealt with in our note on energy masterplanning on a phased site.

Interaction with national standards

Two points of friction recur.

Building Regulations set the minimum, and successive uplifts to Part L have narrowed the gap between national requirements and local targets. A scheme meeting the current Part L may already satisfy a local percentage target written against an earlier edition, and saying so with the calculation is the cleanest route to compliance.

Government has also periodically restricted the extent to which local plans may set energy standards for new housing beyond national requirements, through written ministerial statements, and the position has been revisited more than once. Where a policy predates such a statement, its status is a matter of argument rather than arithmetic, and the safe course is to demonstrate compliance on the numbers where you can and reserve the policy argument. Check the current position at the time of the application rather than relying on a precedent.

Recording the assessment for the officer report

Officers lift material into reports. Give them something liftable.

  1. A one paragraph statement of the policy requirement, quoting the operative words.
  2. The metric and denominator used, stated explicitly.
  3. The results table, with the percentage achieved.
  4. Where a caveat is relied on, a single paragraph identifying which caveat and summarising the evidence.
  5. A cross reference to where each piece of evidence sits in the submission.
  6. A conclusion in the author's own words on whether the policy is met.

That last point is worth insisting on internally. A document that lists figures without concluding leaves the officer to reach the conclusion, and an officer under time pressure who cannot find a conclusion sometimes writes that the policy position is unclear. The narrative belongs in the Energy Statement, with the broader policy coverage in a Sustainability Statement.

Where targets conflict with heritage or amenity

Some sites cannot meet the target without breaching another policy, and the honest submission says which.

Photovoltaics on the principal roof slope of a listed building, or on a prominent roof in a conservation area, engage the statutory duties on listed buildings and conservation areas, and those duties are not displaced by an energy policy. Similarly, plant sized to meet a renewable target can create a noise or roofscape problem that the amenity policies resist.

Where that happens, set out the conflict rather than ignoring the weaker policy. Identify the two policies, explain the physical constraint, state what the scheme does instead, and let the decision maker balance them. That is what the plan expects of a decision maker, and it produces a defensible officer report. External insulation raises the same tension on historic buildings, covered in our note on external wall insulation in a conservation area.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required, and compliance calculations need a competent assessor. This is general guidance and not legal advice, so check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

What is the statutory basis for local renewable energy requirements?

Section 1 of the Planning and Energy Act 2008, which allows a local plan to include reasonable requirements for a proportion of the energy used in development to be energy from renewable sources in the locality. The reference to the locality is what permits some authorities to accept off site provision.

Does the target apply to regulated or total energy?

It depends on the policy, and many are silent. Regulated energy covers the fixed building services in the Building Regulations calculation; total energy adds unregulated loads such as appliances and lifts. The difference is large, so resolve it from the supporting text or the authority's guidance and state the denominator you used.

How do I evidence a feasibility caveat?

With drawings and calculations: a roof plan showing usable area after rooflights, plant and any green roof, orientation and pitch with a shading analysis, a structural note, the network connection position, and an appraisal of each technology considered with the reason each was excluded. That last item is the one most often missing.

Can I rely on viability to avoid the target?

Only with an appraisal prepared to the recognised professional methodology, isolating the cost of the renewable measures from other matters in dispute, and expect the authority to have it independently reviewed at your cost. A roof area argument described as a viability case will be read as a feasibility argument in the wrong language.

Does meeting Part L satisfy a local percentage target?

Sometimes. Successive Part L uplifts have narrowed the gap, and a scheme meeting the current standard may already satisfy a target written against an earlier edition. Show the calculation against both, because that is the cleanest route to compliance and avoids a policy argument about the target's status.

What if the target conflicts with heritage policy?

Set the conflict out. The statutory duties on listed buildings and conservation areas are not displaced by an energy policy. Identify both policies, explain the physical constraint, say what the scheme does instead, and leave the balance to the decision maker rather than ignoring the policy you cannot meet.

Sources and further reading

renewable energylocal plan policyenergy statementviabilitypart l

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Energy, Sustainability and Carbon

View all →
Energy, Sustainability and Carbon6 min read

Embodied carbon of foundations and ground works

On brownfield sites the substructure can carry more embodied carbon than the frame above. How piling, rafts, ground improvement and mix design compare, and how to report substructure so the saving is reviewable.

Read article →
Energy, Sustainability and Carbon7 min read

Green roofs: what counts and what the drawings must show

A thin sedum blanket satisfies almost no current policy. What separates extensive, biodiverse and intensive roofs, how much attenuation credit to expect, and the drawings that discharge the condition.

Read article →
Energy, Sustainability and Carbon6 min read

Water efficiency standards and how to hit 110 litres

The tighter 110 litre standard applies only where a plan policy adopts it and a condition imposes it. How the water efficiency calculation works and which fittings decide the result.

Read article →
Energy, Sustainability and Carbon7 min read

Energy and carbon conditions: what gets discharged when

Energy and carbon conditions bite at different points in the programme. The triggers, the as-built evidence councils accept, and what to do when design changes break one.

Read article →
Energy, Sustainability and Carbon7 min read

Overheating risk in a loft conversion

Sloping rooflights collect more solar gain than vertical windows, and a converted loft has almost no thermal mass. Part O rarely applies, so the design has to deal with it.

Read article →