Forward visibility on a bend for a new access

7 min readBy PlanScope Editorial Team

A perfect junction splay will not save an access if a driver coming round the bend cannot see it. How forward visibility is measured, the obstruction and ownership traps, and why relocating often wins.

Forward visibility bend access problems are the quiet killer of rural self-build applications. The junction visibility splay out of your drive can be perfect and the application still fails, because a driver coming round the bend on the main road cannot see your access, or the car emerging from it, in time to stop. That is a different geometric test, measured along the carriageway rather than out of the access, and it is tested against the same stopping sight distance derived from measured speeds.

The good news is that it is usually fixable. But the fix often involves land you do not own.

What forward visibility measures

Junction visibility asks what a driver in the access can see. Forward visibility asks what a driver on the through road can see ahead of them as they travel round the curve.

The measurement is taken along the carriageway, conventionally along the centre of the nearside lane, between two points separated by the required stopping sight distance. The line between those points has to be clear of obstruction. On the inside of a bend, that line cuts across the verge, the bank, the hedge or the wall, which is exactly where the obstruction sits.

The required distance is the same stopping sight distance used for a junction splay, derived from the measured speeds rather than the posted limit. On a lane signed at 60 mph where traffic runs at 28 mph, the distance needed is modest. On a 30 mph road where traffic runs at 34 mph, it is longer than the standard table for the limit suggests.

Setting it out on the inside of a bend

The drawing is simple to produce and simple to check, which is why authorities take it seriously.

  1. Establish the measured 85th percentile speed for each direction of approach and convert it to a stopping sight distance.
  2. Plot the centre line of the nearside lane on a scaled topographical survey through the full extent of the bend.
  3. Take a point on that line at the position of the hazard, usually the access itself.
  4. Step back along the line by the stopping sight distance to the driver's position.
  5. Draw the straight line between those two points, and sweep it through intermediate positions to produce the envelope that must be clear.
  6. Show every obstruction inside that envelope, with its height and its ownership.

The envelope, not the single line, is what matters. A hedge trimmed to clear one sight line can still break the view from a position five metres further back, which is why the sweep has to be drawn rather than sampled.

Annotate the drawing with the speed survey date, the source of the sight distance figure and the heights used for driver eye and object. Authorities reject access drawings that assert visibility without showing the derivation far more often than they reject the geometry itself.

Verges, banks and hedgerows in the way

The typical rural obstruction is a hedge on a raised bank, and it presents three separate problems.

Height is the obvious one. A hedge cut to 0.9 metres on a bank 0.8 metres above carriageway level still blocks the sight line. The bank has to come down, and that is earthworks on someone's land rather than a trim.

Ownership is the second. Hedges on the boundary may belong to the adjoining landowner, to the highway authority, or to nobody with a clear title, and the verge is frequently highway even where it looks like part of the field. Ask the highway authority to confirm the extent of highway land before you assume anything.

Protection is the third. A hedgerow may be an important hedgerow under the Hedgerows Regulations 1997, in which case removal requires notice to the local planning authority, which can refuse it. Trees in the hedge may be protected by a Tree Preservation Order or by conservation area status. Birds nesting in the hedge are protected during the breeding season, which runs from March to August, so timing matters.

Removing obstructions you do not own

Three mechanisms exist, and they vary in reliability.

The highway authority has powers to deal with vegetation that obstructs the highway or interferes with visibility, including serving notice on an owner to cut back hedges and trees under the Highways Act 1980. Authorities use those powers for existing safety problems, not usually to enable a private development, so do not plan around them.

An agreement with the adjoining owner is the ordinary route: a deed granting the right to cut back and maintain, or the purchase of a strip. Get it in writing before determination, because an authority will not grant permission on the strength of an expectation.

Works within the highway itself, including lowering a bank or regrading a verge, need the highway authority's agreement and are usually delivered under a highway works agreement that follows the permission. The note on section 278 agreements explains how that sequencing works.

Obstruction Who controls it Realistic route
Hedge on your own frontage You Cut back and maintain, secured by condition
Hedge on a neighbour's boundary Adjoining owner Deed of easement or purchase
Raised bank within the highway Highway authority Highway works agreement
Protected tree in the hedge line Authority via the order Application to the authority, may be refused
Important hedgerow Authority via the 1997 Regulations Hedgerow removal notice, may be refused

Relocating the access as the better answer

Moving the access is often the solution that costs least and takes least time, and it is the one applicants resist longest because the original position is usually the most convenient.

Look for a position where the carriageway is straight, where the frontage is set back from a bank, or where an existing field gate already has a history of use. Even twenty metres along a frontage can transform the geometry on a bend, because the sight line no longer has to cut across the inside of the curve.

Test two or three positions before settling. An access that needs no third party land, no bank reduction and no hedgerow removal notice will be determined far faster than one that needs all three, even if it means a longer driveway.

Where a scheme has multiple plots, consider a single shared access at the best geometric position rather than separate accesses at convenient ones. Highway authorities prefer fewer access points, and the visibility case only has to be made once.

What to submit

For a single dwelling the access package is normally a speed survey, an access and visibility drawing showing both the junction splay and the forward visibility envelope with dimensions, a plan showing land ownership and control over everything inside those envelopes, evidence of any third party agreement, and a short written derivation. A Transport Statement is the usual home for that material on a small scheme.

Record protected vegetation properly. Where trees or hedges inside the envelope are protected or have amenity value, the application should include a tree survey so the authority can weigh the loss against the highway benefit rather than discovering it at the site visit.

The refusal reasons this answers

Two reasons recur on small access applications in the countryside: inadequate visibility for the speed of traffic, and reliance on land outside the applicant's control. Both are evidential.

A speed survey answers the first by establishing the real design speed. A drawing with an ownership overlay answers the second, or proves that it cannot be answered from the proposed position, which is the point at which relocation becomes the obvious move rather than a concession. Where the main road is a trunk road, the position is different again and the strategic road network authority becomes a statutory consultee, as set out in the note on when National Highways objects.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How is forward visibility different from a visibility splay?

A visibility splay measures what a driver in the access can see along the main road. Forward visibility measures what a driver travelling on the main road can see ahead as they round the curve, taken along the centre of the nearside lane. On the inside of a bend that line crosses the verge, bank or hedge.

What distance is required?

The stopping sight distance for the measured speed of traffic, derived from an 85th percentile speed survey rather than the posted limit. Manual for Streets tabulates the lower speed values and the Design Manual for Roads and Bridges applies at higher speeds, with the authority's own adopted standards taking precedence.

Can the council make a neighbour cut their hedge for my access?

The highway authority has powers under the Highways Act 1980 to require owners to cut back vegetation obstructing the highway, but it uses them for existing safety problems rather than to enable a private development. Plan on a written agreement with the owner or on relocating the access instead.

What if the hedge is a protected hedgerow?

Removal of an important hedgerow needs a hedgerow removal notice to the local planning authority under the Hedgerows Regulations 1997, and the authority can refuse it. Trees within the hedge may be covered by a Tree Preservation Order, and nesting birds are protected between March and August.

Is it better to move the access than to clear the obstruction?

Often, yes. Twenty metres along a frontage can remove the need for third party land, bank reduction and a hedgerow notice at once, and an application with none of those will be determined far faster. Test two or three positions before settling on the most convenient one.

Sources and further reading

forward visibilityaccesshighwayshedgerowsruralself build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking8 min read

Highway drainage for a new rural access

Highway authorities treat run-off and material transfer onto a rural lane as a safety matter. The design comes down to the levels in the first few metres and the consent position for the roadside ditch.

Read article →
Transport, Highways and Parking7 min read

Car club and travel voucher contributions

The money is simple. The on-street bay needs a traffic regulation order the developer cannot deliver, and the operator may never come forward.

Read article →
Transport, Highways and Parking7 min read

Gated accesses and emergency service override

Three bodies have a view on a gated access: the highway authority, the fire service and the waste service. Design for all three before the driveway is drawn.

Read article →
Transport, Highways and Parking7 min read

Blocking back and queue length at a junction

A capacity ratio tells you how hard an arm is working. Only the queue in metres, compared against measured storage, tells you whether the junction behind will block.

Read article →
Transport, Highways and Parking7 min read

Which design vehicles to test in a swept path analysis

A tracking drawing is only as good as the vehicle chosen. The routine and occasional movements to test, and the parked car case most submissions omit.

Read article →
Transport, Highways and Parking8 min read

Requesting and reading collision data for an access

A highway safety objection is answered with recorded collision data for a defined area and period. How to get it, how to read it, and what it cannot tell you.

Read article →