Templates, Checklists and Examples

Foul Sewage Assessment outline and the capacity question

7 min readBy PlanScope Editorial Team

The question at the centre of a Foul Sewage Assessment is whether the receiving system can take the flow. A section-by-section outline that keeps the capacity evidence at the front.

A foul sewage assessment outline has one question at its centre: can the receiving system take the flow, and what is the evidence. Everything else in the document supports that. The national application form asks how foul sewage will be disposed of, and on anything larger than a single house the council will want more than a tick in the mains sewer box.

Write the assessment in seven sections, in the order below. It mirrors the way a case officer and a sewerage undertaker read it, and it keeps the capacity evidence at the front where it belongs.

Section one: the drainage hierarchy for foul flows

Open by working down the hierarchy and showing where your scheme lands. Connection to the public foul sewer comes first. Where that is not reasonably available, a package treatment plant is next. A septic tank discharging to a drainage field sits below that, and a cesspool, which stores rather than treats, is a last resort that councils and undertakers both dislike.

State the distance to the nearest public foul sewer, measured along a practicable route rather than as the crow flies, and say who owns the land in between. "No mains available" is not an argument on its own. Section 98 of the Water Industry Act 1991 gives a right to requisition a new public sewer, and an undertaker will point that out if your assessment implies the mains option was impossible when it was merely inconvenient.

Where the hierarchy takes you off mains, give the reason in one sentence and move on. A short honest explanation reads better than three paragraphs of justification.

Section two: confirming public sewer capacity

This is the section that decides the application. Record four things: the point of connection, the flow you propose to add, the undertaker's response on capacity, and the date of that response.

Foul flow should be calculated rather than asserted. Set out the population equivalent, the litres per head per day figure used, the resulting dry weather flow, and any peak factor applied. For a small residential scheme that is a five-line table. For a mixed scheme, show the commercial element separately, since trade effluent has its own consent route and different flow characteristics.

Do not conflate foul and surface water here. Separation is expected, surface water to a foul sewer is resisted, and keeping the two calculations in separate documents avoids the confusion that leads to a query. The boundary between the two documents is worth understanding, and the difference between a Foul Sewage Assessment and a Drainage Strategy is more than presentational.

Section three: the pre-development enquiry evidence

The undertaker's own words carry the weight, so reproduce them.

Submit a pre-development enquiry or developer services enquiry response as an appendix, and quote the material sentences in the body. What you want from that response is a statement on network capacity at the proposed connection point, any reinforcement required, an indication of timescale, and whether the undertaker would seek a condition. A response that says capacity is available without qualification effectively closes the issue.

Three points on handling it. Make the enquiry early, because responses take weeks and a stale one covering a different unit count invites a fresh consultation. Describe the scheme accurately in the enquiry, including phasing, since an undertaker assessing 40 units at once gives a different answer from one assessing 40 units over four years. And if the response is unfavourable, deal with it head-on in this section rather than hoping nobody reads the appendix.

Section four: non-mains options and their consenting

Where the scheme is off mains, the assessment has to show the discharge itself is lawful as well as showing that a plant will be installed.

A discharge to surface water from a new septic tank is no longer acceptable, so the off-mains answer is either a package treatment plant or a drainage field. Discharges may be able to proceed under the general binding rules made under the environmental permitting regime, subject to volume limits and location conditions, with a permit required where those rules are not met. The volume limits are lower for discharges to ground than to surface water, and sensitive locations remove the general rules option altogether. The detail of package treatment plants and the general binding rules is worth reading before you specify a unit.

For a drainage field, the assessment needs percolation test results and a field sized from them, with the separation distances set out in Building Regulations Approved Document H: at least 10 metres from a watercourse, 50 metres from any water abstraction point, and 15 metres from a building. Show the field on the layout plan with those distances annotated. A soakage test done in August on a clay site is the single most common weakness in an off-mains submission, so state the date and the ground conditions at the time.

Section five: pumped connections and their risks

Gravity is preferred and pumping is often unavoidable. Where a pumping station is proposed, the assessment should cover the station's location, the rising main route, storage volume for a pump failure, the alarm and telemetry arrangement, odour control, and who will own and maintain it.

Issue What the assessment should state
Emergency storage Volume provided and the retention period it gives
Adoption Whether the station will be offered for adoption and to what standard
Amenity Distance to the nearest habitable room, odour control, access for tankers
Maintenance The responsible body if adoption is refused, and the funding mechanism

Adoption is the part that changes the planning outcome. An unadopted pumping station left to a management company is a long-term liability that officers reasonably question, and the answer needs to be in the document rather than left to a condition.

Section six: phasing where reinforcement is needed

Where the undertaker identifies that network reinforcement is required, the assessment should propose the mechanism rather than waiting for the council to invent one.

  1. State the reinforcement needed and the undertaker's indicative programme.
  2. Identify the scheme capacity that can connect without reinforcement, if any.
  3. Propose a condition preventing occupation of the relevant phase until the reinforcement is complete and confirmed in writing by the undertaker.
  4. Confirm whether a requisition under section 98 has been made or will be, and by whom.
  5. Set out the fallback if reinforcement is delayed, and be honest where there is none.

A well-drafted Grampian condition offered by the applicant is almost always better than one written by an officer, because it will be tied to the right phase and the right trigger. Occupation is the usual trigger, and commencement of development is the one to resist, since it stops the scheme starting for reasons unrelated to construction.

Section seven: the conditions and agreements the undertaker asks for

Close the assessment with the list, so the officer can lift it into the decision notice.

Expect a requirement to separate foul and surface water, a prohibition on surface water entering the foul system, easements kept clear either side of any public sewer crossing the site, a build-over agreement where a structure sits over or close to a public sewer, and a condition tying occupation to any reinforcement. Where the site is in a nutrient neutrality catchment, the foul drainage route affects the nutrient budget, and the assessment should cross-refer to that work rather than duplicating it.

Finish with a short statement of what remains to be confirmed and when. A document that says clearly which figure is provisional is more use to an officer than one that presents an estimate as a measurement.

Draft your Foul Sewage Assessment with the enquiry response in hand, and see what each section has to prove before you start writing. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the drainage hierarchy for foul sewage?

Connection to the public foul sewer first, then a package treatment plant, then a septic tank discharging to a drainage field, with a cesspool as a last resort. State the distance to the nearest public sewer along a practicable route and who owns the land in between, because section 98 of the Water Industry Act 1991 allows a new public sewer to be requisitioned.

What evidence shows there is sewer capacity?

A pre-development or developer services enquiry response from the sewerage undertaker, appended in full and quoted in the body. It should address capacity at the proposed connection point, any reinforcement needed, indicative timescales and whether a condition would be sought. Make the enquiry early and describe the scheme accurately, including phasing, because a stale response invites a fresh consultation.

Can a new septic tank discharge to a stream?

No. A new discharge to surface water from a septic tank is not acceptable, so the off-mains answer is a package treatment plant or a drainage field. Discharges may proceed under the general binding rules made under the environmental permitting regime, subject to volume limits and location conditions, with a permit needed where those rules cannot be met.

How is a drainage field sized and sited?

From percolation test results, with the separation distances in Building Regulations Approved Document H: at least 10 metres from a watercourse, 50 metres from any water abstraction point and 15 metres from a building. Show the field and those distances on the layout plan, and state the date and ground conditions of the percolation test, because a dry summer test on clay is easily challenged.

What condition should I offer where reinforcement is needed?

A condition preventing occupation of the relevant phase until the network reinforcement is complete and confirmed in writing by the undertaker. Offer it yourself, tied to the right phase, rather than leaving an officer to draft it. Resist a trigger at commencement of development, because that stops construction starting for reasons unconnected with building the scheme.

Sources and further reading

foul sewagedrainagesewer capacitypackage treatment plantself build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →