Energy, Sustainability and Carbon

Future Homes Standard transition on a small site

7 min readBy PlanScope Editorial Team

A three plot site can end up with one house on the old standard and two on the new one, because the transitional test is when work started on each individual building.

Building Regulations transitional arrangements for the 2021 Part L uplift worked building by building, not site by site. That single feature is what a small developer needs to understand, because it means a three plot site can end up with one house built to the old standard and two to the new one, and the decision point is when work started on each individual building rather than when the site started.

The Future Homes Standard is expected to follow the same structure. Check the commencement position and the exact wording on gov.uk before you rely on it, because the standard has been consulted on and the detail of implementation and transition is set out in the Approved Document rather than in press coverage.

What changes between the current uplift and the standard

The 2021 uplift to Approved Documents L and F, in force from 15 June 2022, raised the target emission rate, introduced a primary energy target, tightened fabric standards and brought in the requirement to design new and replacement heating systems in existing dwellings to a maximum flow temperature of 55 degrees Celsius where practical. Approved Document O on overheating arrived at the same time and applies to new dwellings.

The Future Homes Standard takes that further towards a dwelling with no fossil fuel heating, a low temperature heat emitter system, solar generation on most house types and a fabric standard that makes a heat pump viable without oversized plant.

For a self-builder the practical differences are three. The heat source changes from a boiler to a heat pump, which needs an external unit and a hot water cylinder. The emitters get larger. And the specification becomes less forgiving of design decisions made for appearance, because glazing area, orientation and form factor all feed the calculation.

How transitional arrangements are normally structured

The pattern used in 2022 had two limbs. A building notice, initial notice or full plans had to be given to the building control body before the commencement date, and work on each individual building had to start within twelve months of that date.

Limb 2021 uplift version Why it matters on a small site
Notice or plans submitted Before 15 June 2022 One submission can cover the whole site
Work started on the building Before 15 June 2023 Applied per building, not per site
Scope of the saving The individual building only Later plots fall under the new standard
Evidence expected Building control records of commencement A site diary is not enough on its own

Read the Approved Document rather than a summary, because the wording of the second limb is where the argument happens.

Building notice and commencement timing

The notification duties sit in the Building Regulations 2010. You must notify the building control body before work starts, and the notice periods for the various stages are set out in the regulations.

What counts as the start of work for transitional purposes is not the same as a material operation for planning purposes. Planning law treats a trench, a peg and a bit of groundwork as a material operation that implements a permission. Building control bodies generally expect meaningful progress on the building itself before accepting that work has started, and a strip of excavation across three plots will not usually be accepted as commencement of all three.

Record it properly. Dated photographs, delivery notes, a signed site record and the building control inspection record all help, and the body that will have to defend the position on inspection is the one to ask in advance.

Plot by plot against whole site commencement

A self-builder with four plots and a single building control submission has four separate transitional positions. Plot one started and inspected in good time keeps the earlier standard. Plot four, started eighteen months later, does not.

Two consequences follow. The design cannot be identical across the plots unless it is designed to the later standard throughout, because the later plots will need a different heating system, different emitters and possibly a different glazing specification. And the sale or build programme has to be set with that in mind, since the plot that slips is the one that gets the more expensive specification.

The straightforward answer on a small site is to design every plot to the higher standard from the outset. It avoids two sets of drawings, two sets of calculations and the risk that a delay on plot three turns into a redesign. It also avoids the awkward conversation where two identical houses on the same street have different running costs.

Heating system implications for a single plot

A heat pump brings three physical requirements that have to be on the planning drawings rather than added later.

The external unit needs a position with airflow clearance, away from neighbouring windows, with the noise calculation done. On a new dwelling built under a planning permission, the permitted development right for heat pumps is not the relevant route, because the dwelling is being built to approved drawings and adding an external unit that is not shown may breach the condition requiring compliance with them. Show it.

The cylinder needs a cupboard. A 200 litre unvented cylinder with its associated valves takes a footprint that a boiler did not, and retrofitting it into a designed plan usually costs a bedroom cupboard.

And the emitters need wall space. A room sized for a double panel radiator at 70 degrees needs a substantially larger surface at 45, which means either underfloor heating or a rethink of the furniture layout.

Interaction with Approved Document O is the part people miss. Reducing heat loss and increasing glazing on a south elevation improves the energy result and worsens the overheating one, and an Overheating Risk Assessment using the dynamic method may be needed where the simplified method fails.

Cost and specification consequences

The cost shift is in the plant, the emitters and the generation rather than in the walls. Fabric improvements at this level are incremental changes to insulation thickness and detailing. The heat pump, cylinder, larger emitters and solar array are new items with new costs, and the airtightness and thermal bridging detailing needs site supervision to achieve on a small build.

Where a local plan policy requires an Energy Statement or a Sustainability Statement, the submission has to show the energy hierarchy and the carbon reduction against the relevant baseline. For a single self-build plot outside London, that requirement is less common than people expect, and the building regulations route does the work.

Practical sequencing decisions

  1. Settle the heating strategy before the planning application, so the external unit, the cylinder and the emitter sizes are designed in rather than added
  2. Get a room-by-room heat loss calculation at design stage rather than at installation stage
  3. Submit the building control application early and keep the record of the submission date
  4. If relying on transitional arrangements for any plot, confirm with the building control body in writing what it will accept as commencement for that building
  5. Design all plots to the later standard unless you are confident every one will start in time
  6. Check the overheating position alongside the energy result, not after it

And take one honest view on risk. Transitional arrangements are a saving provision rather than an entitlement, and a dispute about whether work started on plot three is one you will probably lose on the evidence. Where a plot is marginal, build it to the higher standard and remove the question.

Ground source systems raise separate consenting questions set out in ground source heat pumps and borehole permitting, and combining roof mounted generation with drainage and biodiversity is covered in biosolar roofs.

PlanScope can draft the energy and sustainability sections of a planning submission from a postcode and a set of answers, flagging where calculations are needed rather than inventing figures. The energy modelling itself needs a suitably qualified assessor. Reports should be reviewed before submission and PlanScope does not guarantee planning approval. This is general guidance, not legal advice. Verify the current Approved Document L and O editions and any Future Homes Standard commencement and transitional wording on gov.uk before relying on them.

Frequently asked questions

Do transitional arrangements apply to a whole site?

No. The 2021 Part L transitional arrangements worked building by building: a notice or full plans had to be submitted before the commencement date, and work on each individual building had to start within twelve months. A strip of excavation across several plots will not usually be accepted as commencement of all of them.

What counts as starting work for Building Regulations purposes?

Not the same as a material operation for planning. Planning law treats a trench and some groundwork as implementing a permission. Building control bodies generally expect meaningful progress on the individual building, and the safest course is to get written confirmation from your building control body of what it will accept.

Should I design every plot to the later standard?

On a small site, usually yes. It avoids two sets of drawings and calculations, removes the risk that a delay on one plot forces a redesign, and avoids two identical houses on the same street having different running costs. Transitional arrangements are a saving provision rather than an entitlement.

Does a heat pump need to be shown on the planning drawings?

On a new dwelling, yes. The permitted development right for heat pumps is not the relevant route when the dwelling is being built to approved drawings, and adding an external unit that is not shown risks breaching the condition requiring compliance with them. Show the unit, its clearances and its position relative to neighbouring windows.

How does the energy standard interact with overheating?

They pull against each other. Reducing heat loss and increasing south-facing glazing improves the energy result and worsens the overheating one. Approved Document O applies to new dwellings, and where the simplified method fails, a dynamic thermal model under the alternative method is needed instead.

Sources and further reading

future homes standardpart lbuilding regulationsself buildheat pumpoverheating

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Energy, Sustainability and Carbon

View all →
Energy, Sustainability and Carbon7 min read

Grid capacity and a rural renewable scheme

On a constrained network the connection offer tells you what scheme is worth applying for. Treating it as an engineering matter for after permission is how capacity gets wasted.

Read article →
Energy, Sustainability and Carbon7 min read

BREEAM energy credits and the condition that secures them

A condition requiring a certified rating is really a condition requiring the low carbon specification to survive value engineering. How to set it up so it does.

Read article →
Energy, Sustainability and Carbon8 min read

Energy statements for a major refurbishment

A refurbishment energy statement has a real baseline and a constrained set of measures. How to establish both, and how to set up the demolition comparator honestly.

Read article →
Energy, Sustainability and Carbon8 min read

The energy hierarchy applied to a single self-build

One house does not need a major scheme's carbon modelling. What the local validation list actually asks for, and how to answer it in two or three pages.

Read article →
Energy, Sustainability and Carbon6 min read

Renewable energy requirements on employment units

A renewables percentage applied to a shell and core warehouse depends entirely on what it is measured against. How to settle the definition and draft a condition that can be complied with.

Read article →
Energy, Sustainability and Carbon7 min read

Solar panels on a pitched roof: permission and policy

Class A of Part 14 allows roof-mounted solar on a house, including the front slope and in conservation areas, subject to a 0.2 metre projection limit and conditions on appearance.

Read article →