Energy, Sustainability and Carbon

Ground-mounted solar and best and most versatile land

7 min readBy PlanScope Editorial Team

Provisional ALC mapping is a risk indicator, not evidence. A detailed soil survey splitting grade 3a from 3b is what decides how hard the policy argument becomes.

A ground-mounted solar scheme on grades 1, 2 or 3a agricultural land is making a policy argument it does not have to make. Those grades are the best and most versatile land, and national policy expects their economic and other benefits to be taken into account, with poorer quality land preferred where development of agricultural land is shown to be necessary. Everything that follows in an application flows from where the site sits in that classification, which is why the survey comes before the layout.

The provisional mapping is not the answer. It is the reason to commission a survey.

How agricultural land quality is assessed

The Agricultural Land Classification grades land from 1 to 5 on the basis of physical limitations on agricultural use: climate, site factors such as gradient and flood risk, and soil properties including texture, depth, stoniness, wetness and droughtiness. Grade 3 is subdivided into 3a and 3b, and that subdivision is the one that matters, because 3a is within the best and most versatile category and 3b is not.

The published provisional ALC mapping was produced at a scale intended for strategic planning, typically covering large areas with a single grade and without the 3a and 3b split. It is useful for a first look and not usable as evidence. Overlay the site on the provisional mapping to understand the risk, then commission a detailed survey.

A detailed survey involves auger borings and soil pits on a grid across the site, field description of each horizon, and laboratory analysis where texture or stoniness is borderline. The method follows the revised guidelines and criteria published for grading agricultural land, and the work is done by a soil scientist rather than by an ecologist or a planner.

Why grade matters to the policy test

Where a site is mostly 3b, 4 or 5, the agricultural land argument is weak and the case turns on landscape and visual effects instead. Where it is substantially 1, 2 or 3a, the authority has to weigh the loss, and objectors will press the point.

Two arguments carry weight in response. The first is that the land is not lost: panels are mounted on piles, the ground between and beneath them remains in agricultural use as grassland, and sheep grazing continues through the operational life. That argument is stronger where the design supports it, with generous row spacing, no concrete bases, and stock-proof fencing that allows grazing.

The second is reversibility. A scheme with a defined operational period and a decommissioning scheme leaves the soil resource intact, which is a different proposition from building houses on the same field.

What does not help is an assertion that the land is poor quality without a survey to prove it. Councils have seen that too often.

The survey needed and its seasonal limits

Field survey for ALC can be carried out through most of the year, with one real constraint: soil cannot be properly described when it is waterlogged or frozen, and wetness class assessment is unreliable in extreme conditions at either end. Allow for weather delay rather than programming the survey for January and hoping.

Sampling density is the variable that gets squeezed. A density too low to support the 3a and 3b split invites a challenge from the authority's own adviser, and the whole report then carries little weight. Agree the grid spacing with the surveyor by reference to site size and variability, and show the boring locations on a plan in the report.

An Agricultural Land Classification report should present the grade map, the boring log, the classification reasoning for each grade boundary, and the proportion of the site in each grade as a figure in hectares. Councils usually expect that work to be signed by a suitably qualified soil scientist, and professional review is strongly advised before it goes in.

Landscape and visual evidence expected

Solar farms are low, extensive and reflective, and a landscape objection turns on extent and field pattern rather than height. The usual evidence is a Landscape and Visual Impact Assessment prepared to the third edition of the Guidelines for Landscape and Visual Impact Assessment, with a zone of theoretical visibility, agreed viewpoints and photomontages from them.

Four points recur in officer reports:

  • Visibility from public rights of way crossing or adjoining the site, which is usually more important than visibility from roads.
  • The effect on field pattern where hedgerows would be removed for access or cable routes.
  • Cumulative effect with other consented or operational schemes in the same landscape character area.
  • The adequacy of proposed screening in its first five years rather than at maturity.

That last one is where applications lose. A new hedge drawn at mature height on a photomontage is not mitigation for year one, and a condition requiring planting in the first available season does not change the physics.

Glint, glare and aviation safeguarding

Where a site lies near a licensed aerodrome, a gliding site or a military airfield, a glint and glare assessment is normally required, modelling reflections towards runway approaches, control towers and flight paths. The assessment also looks at nearby dwellings and roads, though the aviation receptors are the ones that produce objections from safeguarding consultees.

Mitigation is usually about panel orientation, tilt angle and screening, and occasionally about excluding part of a site. Raise it early with the aerodrome operator, because a safeguarding objection arriving in week ten of a determination is difficult to resolve inside the period.

Grid connection and cable route consents

The grid connection is frequently the part that defeats a scheme, and it is the part least often resolved at application stage. A connection offer sets the point of connection, the capacity and the date, and the route between the site and that point may cross land in other ownership.

Three separate consent questions arise. Whether the cable route needs planning permission or falls within the permitted development rights available to electricity undertakers. Whether a substation compound needs its own permission and where it sits visually. And whether highway works for a cable crossing need a street works agreement with the highway authority.

Describe the connection arrangement in the application even where it is consented separately. An officer who cannot see how the electricity leaves the site will ask, and the answer will take three weeks by email.

Decommissioning and the temporary permission

Most ground-mounted solar permissions are granted for a defined period, with a condition requiring removal of the equipment and restoration of the land within a stated time after generation ends. The period varies and is a matter for the authority, so propose one and justify it by reference to the design life of the equipment and the connection agreement.

A decommissioning and restoration scheme, secured by condition or obligation, should address removal of panels, frames, piles, cables and the substation, treatment of access tracks, reinstatement of soil profiles, and a timescale. Where soils are stripped at construction, the handling and storage method matters as much as the restoration specification, because compacted and mixed soil does not recover its original grade.

An illustrative example

A 30 hectare arable field is proposed for a ground-mounted scheme. The provisional mapping shows grade 3 across the whole field. A detailed survey with borings on a 100m grid finds 11 hectares of 3a on the drier southern slope and 19 hectares of 3b on heavier soils to the north. The layout is revised to concentrate panels on the 3b area, leaving a 3a margin in arable cropping, and the statement quantifies the best and most versatile land affected in hectares. This example is illustrative and the grading on any other site would differ.

The same logic about using the least constrained land first applies to other renewables on a holding, whether that is solar canopies over car parks or farm wind turbines within permitted development limits.

One honest uncertainty. Larger solar schemes can fall to be determined as nationally significant infrastructure under the Planning Act 2008 rather than by the local planning authority, and the generating capacity threshold for solar has been changed, so check the current figure before assuming the route.

This is general guidance, not legal advice. Agricultural land classification and landscape assessment are specialist disciplines, so take advice from qualified professionals and check the position with your local planning authority.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required. Enter your postcode on PlanScope to see which reports a rural energy scheme is likely to need.

Frequently asked questions

What counts as best and most versatile agricultural land?

Grades 1, 2 and 3a of the Agricultural Land Classification. Grade 3 is subdivided into 3a and 3b, and that split is decisive, because 3a falls within the best and most versatile category and 3b does not. Published provisional mapping does not usually show the subdivision, so a detailed survey is needed.

Can I rely on the provisional ALC map?

No. The provisional mapping was produced at a strategic scale, often giving one grade across a wide area and without the 3a and 3b split. Use it to understand the risk before buying or optioning land, then commission a detailed survey with auger borings and soil pits before fixing a layout.

Is a solar farm a permanent loss of agricultural land?

Not in the same way as built development. Panels are pile mounted, the ground between and beneath them can remain in grassland and be grazed, and a decommissioning scheme can restore the field. That argument works best where the design supports it with wide row spacing, no concrete bases and stock-proof fencing.

When can an ALC survey be carried out?

Through most of the year, but not when soils are waterlogged or frozen, because wetness class and soil description become unreliable. Programme the survey with weather contingency rather than relying on a midwinter window, and agree the boring grid spacing with the surveyor in advance.

Is a glint and glare assessment always needed?

Not always, but it is normally required where a site lies near a licensed aerodrome, a gliding site or a military airfield. The assessment models reflections towards runway approaches, control towers and flight paths, and towards nearby dwellings and roads. Engage the aerodrome operator early rather than waiting for a safeguarding objection.

Sources and further reading

solaragricultural landalcbmv landrural planninglvia

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Energy, Sustainability and Carbon

View all →
Energy, Sustainability and Carbon7 min read

Urban greening factor: calculating a score that passes

The urban greening factor is a weighted average across the whole red line area, not just the landscaped parts. Here is how the weightings work, where the score is won, and how to present a calculation an officer can check.

Read article →
Energy, Sustainability and Carbon7 min read

Whole life carbon thresholds: which schemes are caught

The trigger for a whole life carbon assessment is not floor area. In London it is referability to the Mayor; outside London it is the adopted local plan, or nothing at all.

Read article →
Energy, Sustainability and Carbon8 min read

Solar panels on a listed building: what is possible

Solar on a listed building turns on visibility, fixing detail and reversibility rather than on the panels. The slopes least likely to be refused, and the documents consent needs.

Read article →
Energy, Sustainability and Carbon7 min read

Embodied carbon in a retrofit against a new build

A retrofit against new build carbon comparison turns on four module groups, the structural appraisal behind the reuse case, and the grid decarbonisation assumption nobody states.

Read article →
Energy, Sustainability and Carbon8 min read

Fabric first against renewables: where the money goes

Fabric first is right for the first few thousand pounds and wrong for the last few. Work out the crossover for your own plot with SAP sensitivity runs rather than borrowing someone else's league table.

Read article →
Energy, Sustainability and Carbon8 min read

Part O overheating: simplified method or modelling

Approved Document O offers tabulated glazing limits or a dynamic thermal simulation. Single aspect flats, high risk locations and noisy roads push schemes into the modelling route whether the team planned for it or not.

Read article →