Comparisons

Heat pump permitted development or a planning application

7 min readBy PlanScope Editorial Team

Most air source heat pumps go in without an application. The ones that need permission usually fail on the noise calculation or on where the unit has to sit.

An air source heat pump permitted development installation stands or falls on two questions: does the calculated noise level at the neighbour's window come in at or below 42 dB(A), and is there a position for the unit that the right actually covers. Almost every case that needs a planning application fails one of those, and the size of the unit is rarely the problem.

The right is in Schedule 2 Part 14 of the General Permitted Development Order 2015, and it is conditional. Conditional rights are not the same as unconditional ones: fail a condition and the installation is unauthorised development, even though nobody applied for anything and nobody told you.

The limits in the permitted development right

The right covers installation of an air source heat pump on a dwellinghouse or a block of flats, or within the curtilage, subject to a set of limitations and conditions.

Four conditions matter in practice. The pump must be used solely for heating purposes. It must comply with the microgeneration planning standards. It must be sited so as to minimise its effect on the external appearance of the building and on the amenity of the area. And it must be removed as soon as reasonably practicable when no longer needed.

The dimensional and siting limits, including the size of the outdoor unit and its position relative to boundaries, have been amended since the right was introduced. So read the current consolidated text of Class G rather than a summary written before the last change, and check whether an Article 4 direction applies locally.

One more limitation catches people. Where a wind turbine already stands on the building or within its curtilage, the heat pump right is not available.

Noise conditions and how they are met

This is the condition that does the work, and it is a calculation rather than a measurement.

The microgeneration planning standards set out a procedure: take the sound power level of the specific unit from the manufacturer's data, apply the distance to the assessment position, apply factors for reflective surfaces and any barrier, and compare the result against 42 dB(A). The assessment position is one metre from a habitable room window or door of neighbouring premises.

Four things move the answer.

  • The unit selected, because sound power levels differ substantially between models of similar output.
  • The distance to the nearest neighbouring habitable room opening.
  • The number of hard surfaces close to the unit, since a pump in a corner between two walls is reflecting sound in two directions.
  • Whether a barrier is present, and whether it is solid, high enough and close enough to count.

Get the calculation done at design stage on the specific model, in writing, and keep it. An installer who says it will be fine has not done a calculation, and a courtyard or a narrow side passage between two terraced houses is exactly where the arithmetic fails.

Where the calculation cannot be met, a planning application is the route, and the council will want a proper acoustic assessment rather than the microgeneration sheet. That is where a Noise Impact Assessment prepared to a recognised methodology becomes the supporting document.

Conservation areas and listed buildings

Designation narrows the right and adds a separate consent regime, in the same way it does for other external fixings.

In a conservation area or World Heritage Site the right does not cover installation on a wall or roof fronting a highway, nor installation on a building within the curtilage. So the workable positions are rear and side elevations out of public view, and a corner plot with two highway frontages can be very awkward.

Listing is a separate question. Permitted development rights are about planning permission, and listed building consent is required for works affecting the character of a listed building as one of special architectural or historic interest. Bolting a condenser to a historic elevation, cutting a 60 mm pipe penetration through ashlar and routing a condensate drain are all such works. Treat consent as necessary and design the route accordingly.

Situation Planning permission Other consent
Rear garden position, unlisted house, no designation Covered by the right if conditions met None
Conservation area, rear elevation out of public view Usually covered None
Conservation area, elevation fronting a highway Application needed None
Listed building, any position Right may apply Listed building consent needed
Calculated level above 42 dB(A) Application needed None
Flat, no freeholder consent Right may apply Lease consent needed

Flats and shared walls

The right extends to blocks of flats, which surprises people, and it is not the end of the analysis.

A leaseholder almost always needs the freeholder's consent for an external alteration, and many leases prohibit fixings to the structure outright. That is a private law question the planning system does not touch, and it is the more common obstacle.

Then there is the party wall. A unit fixed to a wall shared with a neighbour transmits vibration through the structure, which the airborne noise calculation does not capture. Anti-vibration mounts and a freestanding base rather than a wall bracket are the practical answers, and on a shared wall the freestanding option is worth the extra space it takes.

Where a block is converting several flats, one shared arrangement designed properly beats six individual units bolted to whichever elevation was convenient.

Where an application is unavoidable

Six situations, and none of them is a reason to abandon the project.

The calculated level exceeds 42 dB(A) and no reasonable relocation or barrier brings it down. The only viable position fronts a highway in a conservation area. An Article 4 direction has removed the right. More than one unit is needed. The building is not a dwellinghouse or block of flats, so Part 14 does not apply. Or the unit will serve something other than heating.

A householder application for a heat pump is a modest submission: a location plan, a site plan showing the unit position with dimensions, an elevation, the manufacturer's data sheet, and the acoustic assessment. A short Planning Statement addressing amenity and the relevant development plan policies is usually enough on top of that.

As an illustrative example, a mid-terrace house with a 4 m rear yard, neighbouring kitchen windows 2.5 m away on both sides and brick walls on three sides is a case where the calculation is likely to fail on any unit and where a planning application with an acoustic enclosure is the realistic path. A detached house with 8 m to the nearest neighbouring window is a case where nobody needs to apply for anything.

If an application is refused, the fast-track route applies to householder refusals, and knowing which procedure you are in matters, so the householder appeal route is worth checking before you decide whether to appeal or revise.

Evidence to keep on file

Five documents, in one folder, kept for as long as you own the house.

The microgeneration certificate for the installation. The sound calculation sheet showing the model, the distances and the result. The manufacturer's technical data including the sound power level. The commissioning record. And dated photographs of the installed position with a tape measure in shot showing the distance to the boundary and to the nearest neighbouring opening.

That folder answers a conveyancing enquiry, an environmental health enquiry and a planning enforcement enquiry. Without it, an owner three years later has no way of demonstrating that a condition of the right was satisfied on the day.

Where the pump forms part of a wider retrofit or a new build, the figures should be consistent with the Energy Statement, particularly the seasonal efficiency assumed and the electrical load, because a planning submission that quotes two different performance figures invites a question.

Confirming lawfulness

Where certainty matters, apply for a lawful development certificate for proposed use or development. It is the only formal route to confirmation, it puts the council's view on the record, and it produces a document with legal standing.

Do it before installation rather than after. A certificate for proposed development is decided on the design; a certificate for existing development has to be argued on what was built. And permitted development status does not displace environmental protection law, so a unit that becomes a statutory nuisance can still be dealt with by the council's environmental health team.

Enter your postcode on PlanScope to see which documents an application for external plant at your property would need.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. A lawful development certificate is the only formal way to confirm that works are lawful. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What noise limit applies to a domestic air source heat pump?

The permitted development right requires compliance with the microgeneration planning standards, which set a calculated sound level limit of 42 dB(A) at an assessment position one metre from a habitable room window or door of neighbouring premises. The figure is calculated using the manufacturer's sound power level, the distance and the reflective surfaces around the unit, not measured after installation.

Can I put a heat pump on the front of my house in a conservation area?

Generally not under permitted development. The right restricts installation on a wall or roof fronting a highway, and on a building within the curtilage, where the dwellinghouse is in a conservation area or World Heritage Site. A rear or side position away from public view is the usual answer, and an application is needed where no such position works.

Do I need listed building consent for a heat pump?

Assume yes if the building is listed. Fixing a unit to an elevation, cutting pipework through a wall and adding a condenser to a curtilage building are all alterations capable of affecting the character of the building. Plan the route and the position with the conservation officer before ordering equipment, because relocating a unit afterwards is expensive.

Does permitted development protect me from a noise complaint?

No. Permitted development deals with planning permission only. A unit that causes a statutory nuisance can still be the subject of an abatement notice under environmental protection legislation, whatever its planning status. That is a further reason to keep the calculation sheet and the commissioning record on file.

How can I be certain the installation is lawful?

Apply for a lawful development certificate for proposed use or development. It is the only formal way to confirm that works do not require planning permission, and it produces a document you can hand to a buyer's solicitor. An installer's assurance is not evidence, and the liability for unauthorised works sits with the owner.

Sources and further reading

heat pumpspermitted developmentnoisehouseholderconservation areas

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →
Comparisons7 min read

Building notice or full plans application to building control

Two routes to building control approval under the Building Regulations 2010. What each involves, where a building notice is unavailable, and how completion certificates and regularisation work.

Read article →
Comparisons8 min read

Dropped kerb approval or permission for a front hardstanding

The crossover is licensed under the Highways Act 1980. The driveway behind it is permitted development only if it is porous or drains inside your boundary. Most people need both approvals.

Read article →
Comparisons7 min read

Strategic Environmental Assessment or Sustainability Appraisal

A local plan appraisal discharges two duties at once: strategic environmental assessment under the 2004 Regulations and sustainability appraisal under section 19(5). Only one has sharp legal teeth.

Read article →
Comparisons7 min read

Environmental permit or planning permission for a waste use

The Environment Agency permits the operation. The waste planning authority decides whether the use belongs there. Both are needed, and a registered exemption is not a planning permission.

Read article →