Householder application: building the document list

7 min readBy PlanScope Editorial Team

Article 7 of the Development Management Procedure Order sets a short national list for every planning application. Here is what it contains, what a local list adds, and why most householder submissions are returned.

A householder application has a short national list and a longer local one, and almost every invalidation comes from the short list. Article 7 of the Development Management Procedure Order 2015 sets out what every application must contain: the completed standard form, a plan identifying the land, the correct ownership certificate, the fee, and a design and access statement where one is required. Get those five right and the council cannot refuse to validate on national grounds.

The rest of the pack is drawings, and the drawings are where the time goes.

The nationally required documents

Five items, and they are not negotiable.

The application form comes from the standard set, completed in full. Blank fields cause returns even where the answer is obviously nil, so write "none" or "not applicable" rather than leaving a box empty.

The plan identifying the land is the location plan. It must be at a recognised scale, normally 1:1250 for a town plot or 1:2500 for a larger or rural one, with the application site edged in a red line and any other adjoining land in the same ownership edged in blue. It needs a north point and a scale bar, and the red line must include everything affected, including the access and any land where scaffolding will stand.

The ownership certificate is a statutory declaration under section 65 of the Town and Country Planning Act 1990, and it must be signed and dated. The fee must be the correct amount for the application type.

The fifth item, the design and access statement, is conditional rather than universal. For a householder application it applies in a designated area such as a conservation area or a World Heritage Site, and then where the development comprises one or more dwellings or 100m² or more of floor space. Outside those situations a short Design and Access Statement is optional, though a well-written one still helps a marginal case.

Plans, scales and north points

The drawings are where returns actually happen. A workable set for a typical extension looks like this.

Drawing Usual scale What it must show
Location plan 1:1250 or 1:2500 Red line, blue line, north point, scale bar
Block or site plan 1:200 or 1:500 Site boundaries, the building, parking, trees, drainage
Existing floor plans 1:50 or 1:100 Every affected floor, room labels
Proposed floor plans 1:50 or 1:100 Same floors, with new work identified
Existing elevations 1:50 or 1:100 All four elevations, including the unaffected ones
Proposed elevations 1:50 or 1:100 All four, with materials annotated
Section 1:50 or 1:100 Where ground levels change or a roof is complex
Roof plan 1:100 Where the roof form changes

Every drawing needs a unique number, a revision letter, a title, the scale and the paper size it was drawn at. Councils receive drawings as PDFs and print them, so a scale bar is worth more than a stated scale.

The single most common return is a set of proposed elevations without the matching existing ones. The officer cannot assess the change without both, and no amount of annotation substitutes.

Where a local list adds items

Local lists are published by each authority and should be reviewed regularly, so download yours rather than relying on what another council asked for last year.

For householder work the usual additions are site photographs, a tree survey where a protected or nearby tree is affected, a Heritage Statement in a conservation area or next to a listed building, a flood risk assessment in Flood Zone 2 or 3, a drainage or soakaway note for large areas of new hardstanding, and a parking or highways note where an access changes.

A local list requirement has to be reasonable and relevant to the application. Where a council asks for something clearly disproportionate to a single-storey rear extension, say so politely in writing with your reasoning, and ask which published local list item is being relied on. That conversation resolves more disputes than it starts.

Some authorities also ask for a biodiversity checklist or a statement on the small sites biodiversity net gain exemption. Householder development is exempt from the net gain requirement, but the council may still want the exemption stated on the form.

Ownership certificates and notices

Certificate A applies where you own the whole application site and nobody else has an interest. That covers most extensions and it is the one people tick automatically.

Certificate B applies where somebody else owns part of the site or has been an owner or agricultural tenant in the preceding 21 days, and you know who they are. You must serve notice on each of them and record the date. Leasehold flats, shared driveways, ransom strips and land where a neighbour owns the boundary wall all trigger this.

Certificate C covers the case where some owners are unknown despite reasonable enquiries, and Certificate D where none can be traced, both requiring a newspaper advertisement. The agricultural holdings certificate sits alongside them.

Getting this wrong is not a technicality. A certificate signed incorrectly can make a grant of permission vulnerable, and a neighbour who was never served has a real grievance.

Photographs and existing condition records

Photographs are not nationally required and are worth including anyway.

Take them from the positions an officer would use on a site visit: the front elevation from the opposite pavement, the rear from the far end of the garden, the flank from the boundary, and a shot of the neighbouring property in the same frame as yours. Date them and number them against a key plan.

For anything involving alteration to an older building, photograph what is there now in detail. Existing brickwork bonds, window profiles, rainwater goods and boundary treatments are the facts a conservation officer will want, and they are easier to record now than to reconstruct from memory after the scaffolding goes up.

An illustrative example

A single-storey rear extension to a 1930s semi in a conservation area. The validated pack was the form, a 1:1250 location plan with a red line taking in the side access, Certificate A signed and dated, the fee, a four-page design and access statement covering the conservation area character, existing and proposed floor plans and all four elevations at 1:100, a section through the new roof, twelve numbered photographs, and a short heritage note on the affected brickwork. Twelve documents, and the application validated on the day of submission. This example is illustrative rather than drawn from a specific case.

Fee and how it is calculated

Householder application fees are set nationally by regulations and indexed, so check the current figure on the fee calculator before you submit rather than relying on a figure quoted in an article or by a builder.

A few points catch people. There is no fee for an application for listed building consent. Where an application is made for works to a listed building and for planning permission at the same time, two applications are submitted and only one fee is payable. And where the first application is refused or withdrawn, a free go may apply to one resubmission within twelve months on the same site, subject to conditions.

Paying the wrong fee is treated as an invalid application, and the clock does not start until the correct amount is received. On a marginal case that is four weeks lost for the sake of a phone call.

Common reasons a submission is made invalid

Work through this list before you press submit.

  1. Missing existing elevations, or elevations that do not show all sides of the building.
  2. A red line that excludes the access, the parking area or land needed during construction.
  3. No north point or no scale bar on the location plan.
  4. An unsigned or undated ownership certificate.
  5. The wrong certificate where a neighbour owns part of the boundary or the property is leasehold.
  6. Drawings without unique numbers, so a revision cannot be tracked.
  7. The wrong fee, or the fee paid against the wrong application reference.
  8. A local list item omitted with no explanation of why it does not apply.

If the council does declare the application invalid, ask for the reasons in writing and the specific published requirement each one relies on. Most invalidity notices are resolved in a day or two once you know precisely what is being asked for.

And keep the whole pack in one folder with a contents sheet. A Planning Statement is rarely required for a householder application, but a one-page covering note listing every document, its reference and its purpose costs nothing and makes the validation officer's job easy.

Browse the report types by category if your local list has thrown up something unfamiliar. This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What must every householder application include?

The completed standard application form, a plan identifying the land, the correct ownership certificate signed and dated, the correct fee, and a design and access statement where one is required. Those are the national requirements under article 7 of the Development Management Procedure Order 2015. Everything else comes from the council's published local list or from the drawings needed to describe the proposal.

Do I need a design and access statement for an extension?

In a designated area such as a conservation area or a World Heritage Site, and then where the development comprises one or more dwellings or 100 square metres or more of floor space. Outside those situations it is optional for householder work. A short statement is still worth writing where the design decisions need explaining to a case officer who has not visited yet.

What scale should my location plan be?

Normally 1:1250 for an urban plot or 1:2500 for a larger or rural site. It needs the application site edged in red, any other adjoining land in the same ownership edged in blue, a north point and a scale bar. The red line must take in everything affected, including the access and any land where scaffolding or plant will stand.

Which ownership certificate do I sign?

Certificate A where you own the whole site and nobody else has an interest. Certificate B where someone else owns part of it or has been an owner or agricultural tenant in the past 21 days and you know who they are, in which case you serve notice on each. Certificates C and D cover unknown owners and both require a newspaper advertisement.

What happens if the council says my application is invalid?

The determination period does not start until the application is valid. Ask for the reasons in writing and for the specific published requirement each one relies on. Most invalidity notices are cleared within a day or two once the missing item is identified. Local list requirements have to be reasonable and relevant to the application being made.

Sources and further reading

householdervalidationplanning applicationdrawingschecklist

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →