Indexation of financial contributions in planning obligations

6 min readBy PlanScope Editorial Team

An indexation clause can add a material sum between signing a section 106 agreement and paying the contribution. The base date and the index chosen matter more than the headline figure.

A financial contribution in a section 106 agreement is almost always indexed, which means the figure you negotiate is not the figure you pay. The agreement fixes a sum, names an index, sets a base date, and provides that the sum is adjusted by the movement in that index between the base date and the date of payment. On a scheme where the first payment falls due at occupation three years after the agreement is signed, three years of construction cost inflation is applied to every pound of it.

Negotiating the quantum and ignoring the indexation clause is the standard mistake. The base date is where the money is, and it is often earlier than the agreement.

Why contributions are indexed

Obligations under section 106 of the Town and Country Planning Act 1990 have to meet the tests in regulation 122 of the Community Infrastructure Levy Regulations 2010: necessary to make the development acceptable, directly related to it, and fairly and reasonably related in scale and kind. A contribution calibrated to the cost of a school place or a junction improvement only continues to meet that test if it still buys the thing it was calculated for.

Authorities also have a practical problem. Infrastructure is delivered years after permission, often by a different part of the council, and a fixed cash sum erodes. Indexation is the mechanism that holds the contribution at constant purchasing power rather than constant cash.

Which is reasonable. The argument is rarely about whether to index and almost always about from when, and against what.

Which index is normally used

For contributions calculated from construction costs, the usual choice is a Building Cost Information Service index published by the Royal Institution of Chartered Surveyors, typically the all-in tender price index or the general building cost index. Highway works, education places, play space and open space contributions normally use one of these.

Where the contribution funds something other than construction, a general price index can be appropriate. Monitoring fees, which regulation 122 permits where they are reasonable and reflect the actual cost of monitoring, are often linked to a general consumer or retail price measure instead.

Three drafting points decide whether the clause works years later:

  • name the index precisely, including the series and the publisher, rather than referring to it by initials alone
  • say what happens if the series is discontinued, rebased or renamed, with a successor index provision
  • say whether provisional figures count or whether the last firm figure applies, because construction indices are published provisionally and later revised

A clause that names a series which no longer exists leaves both sides arguing, and the authority usually has the stronger position because the money is not yet paid.

Setting the base date

The base date is the date of the index figure from which the uplift runs. Three candidates appear in practice, and the difference between them can be years.

Base date used Effect on the developer
Date of the agreement Shortest indexation period, best outcome
Date of the committee resolution or decision notice Modest additional period
Date of the supplementary planning document or tariff that set the rate Potentially many years of uplift

The third is the one that catches people. Where an authority's contributions come from an adopted document with a stated base date, the obligation may index from that date rather than from the agreement, so a tariff adopted some years earlier carries all the inflation since. Ask for the base date to be the date of the agreement, and where the authority refuses, price the difference and feed it into the appraisal exactly as you would highway works costs in a development appraisal.

Compounding and the payment trigger

The standard formula is the contribution multiplied by the index figure at the payment date divided by the index figure at the base date. That is a single ratio rather than a year-on-year compounding calculation, so the arithmetic is simple once both figures are identified.

The payment trigger is what fixes the end of the period. Common triggers are commencement, implementation of a specified operation, occupation of a stated number of dwellings, and practical completion, and a phased scheme will have several. Each trigger brings its own index figure, so the same contribution can be indexed differently across phases.

Two traps. First, a clause that uses the date the contribution becomes due rather than the date it is paid removes any benefit from paying late and any penalty for paying early, which is usually what the authority wants. Second, where a payment is made in instalments, check whether each instalment is indexed to its own payment date or whether the whole sum is indexed once at the first trigger.

Disputes about the published figure

Most disputes are mundane. The index figure for the relevant month has not yet been published when payment falls due. The figure published was provisional and has since been revised downwards. The series was rebased, so the numbers before and after are not comparable without a conversion.

Head these off in the drafting. Provide for the last published figure at the date of payment, state whether provisional figures are used, require the paying party to show its calculation, and include a short expert determination route for disagreement rather than leaving the parties to litigate a four-figure difference.

Keep the working. A one-page calculation sheet showing the base figure, the payment-date figure, the source, the publication date and the resulting sum settles most queries by return.

Capping indexation

Caps are negotiable and more common than developers assume. The forms that authorities accept include a ceiling on the total uplift expressed as a percentage, a cap on the period over which indexation runs, a floor preventing the contribution falling below the original sum, and a provision that indexation stops if the authority fails to spend the money within the period provided for repayment.

A longstop is the most useful of these. Where a scheme stalls, an obligation indexed indefinitely becomes a liability that grows while the site produces nothing, and an authority that wants the infrastructure delivered has an interest in the scheme remaining viable.

Modelling the cost at the right date

In an appraisal, index every contribution forward to its expected payment date using the same cost inflation assumption applied to the build cost, and show the indexed figure rather than the agreement figure. Showing the undated sum understates the cost and invites the authority's reviewer to correct it, which is a poor way to open a negotiation.

Then sensitivity test. A twelve-month programme slip moves every payment trigger and every index figure with it, and on a scheme carrying several hundred thousand pounds of obligations the effect on residual value is visible. That is precisely the kind of input an independent review of a viability appraisal will probe.

A Viability Assessment needs the indexed figures, the base dates and the triggers set out transparently, and so does an Affordable Housing Statement where a commuted sum is involved. PlanScope drafts those documents from your scheme inputs and flags the figures it does not have, and you can enter your postcode on the home page to see which reports a site needs. Reports should be reviewed before submission and PlanScope does not guarantee planning approval.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

Which index is used for section 106 contributions?

Construction-related contributions are usually indexed to a Building Cost Information Service index published by RICS, commonly the all-in tender price index or the general building cost index. Contributions that do not fund construction, including monitoring fees, are often linked to a general consumer or retail price measure instead. The agreement should name the series precisely.

Can indexation be backdated before the date of the agreement?

Yes, and it frequently is. Where the contribution comes from an adopted tariff or supplementary planning document with its own base date, the agreement may index from that date rather than from signature, adding every year of inflation since adoption. Ask for the agreement date as the base date and price the difference if refused.

How is an indexed contribution calculated?

Multiply the agreed sum by the index figure at the payment date and divide by the index figure at the base date. It is a single ratio rather than a compounding calculation. Where payment is in instalments, check whether each instalment uses its own payment-date figure or whether the whole sum is indexed once at the first trigger.

Can an indexation clause be capped?

It can be negotiated. Authorities accept ceilings on the total uplift, caps on the period over which indexation runs, floors preventing the sum falling below the original figure, and provisions ending indexation where the money is not spent within the repayment period. A longstop matters most on schemes that may stall.

What happens if the index is discontinued or rebased?

A well-drafted clause provides for a successor index or for a method of conversion, so include one. Without it, the parties have to agree a substitute at the point of payment, and the authority holds the stronger position because the contribution has not yet been paid. Also state whether provisional or firm figures apply.

Sources and further reading

section 106indexationplanning obligationsviabilitycontributionsbcis

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial7 min read

Waste contributions and bin provision in new schemes

Collection authorities start with where the refuse vehicle can stand and how far the crew moves containers. Store sizing, access standards and testing a waste contribution against regulation 122.

Read article →
Viability, Obligations and Commercial7 min read

Spend deadlines and repayment clauses in obligations

A spend deadline gives the authority a fixed period to apply a contribution to the named project, and a repayment clause gets the unspent balance back. The drafting that makes it work.

Read article →
Viability, Obligations and Commercial7 min read

Pre-application fee bands and what each band buys

Pre-application charges are set under section 93 of the Local Government Act 2003 and banded by scale. What each service level includes, and how to make the fee pay for itself.

Read article →
Viability, Obligations and Commercial7 min read

Section 278 agreements and the cost nobody budgeted

The works cost is the part everyone budgets. Design check fees, supervision, bonds, commuted sums, traffic orders and undertaker diversions are the part that hurts.

Read article →
Viability, Obligations and Commercial7 min read

Monitoring fees and the statutory tests for obligations

A monitoring fee has to be fairly and reasonably related in scale and kind to the development and reflect the authority's estimated monitoring cost. Most draft fees have never been tested against that.

Read article →
Viability, Obligations and Commercial7 min read

First Homes and the discount mechanics

A First Home is sold at least 30 per cent below market value with the discount held in perpetuity on title, and the price after discount must not exceed £250,000, or £420,000 in London.

Read article →