Industrial plant, machinery and hardstanding under Part 7
Part 7 allows plant, machinery and hard surfaces within the curtilage of an industrial building within limits on height and position. Conditions on the existing permission, designated land and open storage are where operators come unstuck.
Industrial plant permitted development rights live in Part 7 of Schedule 2 to the General Permitted Development Order 2015, which covers non-domestic extensions and alterations including industrial buildings and warehouses. Between them the classes in that Part allow plant and machinery to be installed on industrial land, hard surfaces to be laid within the curtilage, and industrial or warehouse buildings to be extended, all within limits on height, floorspace and position and all subject to the land not being designated.
One caution before any of it is relied on. Part 7 has been amended repeatedly, class letters have moved, and the limits differ between the classes, so read the consolidated text of the Part on legislation.gov.uk for the date you are working to rather than a summary.
What the Part covers, class by class in substance
The useful way to hold Part 7 in your head is by subject matter rather than by letter.
- Extension or alteration of an industrial building or warehouse, subject to caps on additional floorspace and on height, a restriction on proximity to the curtilage boundary, and a requirement that the use remains an industrial or warehouse use.
- Provision, rearrangement or replacement of plant or machinery on land used for an industrial process, subject to a height limit.
- Laying of a hard surface within the curtilage of an industrial building or warehouse for a purpose incidental to the undertaking.
- Equivalent, and different, rights for shops, offices, schools and hospitals, which have their own classes and their own limits.
Three qualifications apply across the industrial classes. The land must already be in the relevant use, since none of these rights create a use. The rights do not apply, or apply in reduced form, on article 2(3) land, which covers conservation areas, National Parks, National Landscapes, the Broads and World Heritage Sites. And a condition on an existing planning permission can remove them, which on a modern industrial estate is common.
That last point deserves checking first. Estate-wide permissions frequently carry conditions requiring approval of external plant, restricting external storage, or removing Part 7 rights entirely, and the condition overrides the Order.
Height limits on external plant
The plant and machinery class permits installation up to a stated height, measured from ground level, with a lower limit where the land is within a specified distance of the curtilage boundary. Those figures are in the current text of the class and they are the first thing to check, because process plant frequently exceeds them.
Where the plant is on a roof, the measurement basis changes, and rooftop chillers and air handling units are the most common cause of an unintentional breach. Measure from the same datum the class specifies rather than from the roof surface.
Two practical habits:
- Get the supplier's dimensioned drawing before ordering, including acoustic enclosures and any support steelwork, because the enclosure often adds the height that breaks the limit.
- Record the ground level datum used, with a survey point, so that the position can be evidenced years later.
Where plant exceeds the limit, a planning application for the plant alone is usually straightforward, and the issues will be appearance, noise and any air quality or odour effect rather than the principle.
Development within the curtilage, and where the curtilage ends
Part 7 rights attach to the curtilage of the industrial building or warehouse, which is not the same as the site boundary or the leasehold demise. Yard areas used with the building are normally within it. A separate field behind the yard, fenced off and unused, probably is not.
Hard surfacing rights are limited to purposes incidental to the undertaking, which covers circulation, parking and loading. It does not cover laying a surface as the first step towards an external storage operation, because that operation may itself be a material change of use.
Surface water is the other half of the hard surfacing question. Laying a large impermeable area changes run-off, and while the Order does not impose a drainage condition on the industrial hard surface class, the discharge itself may need consent from the water company or the Environment Agency, and an existing permission's drainage condition may bite.
Noise from plant is a separate control
Permitted development status says nothing about whether the plant can be operated without complaint. Three separate controls apply.
| Control | What it addresses |
|---|---|
| Statutory nuisance under the Environmental Protection Act 1990 | Noise amounting to a nuisance, with an abatement notice as the remedy |
| Conditions on the existing planning permission | Plant noise limits, hours of operation, approval of external plant |
| Environmental permit conditions where the process is permitted | Emissions including noise where the permit covers it |
Designing to a noise limit before installation is far less painful than responding to an abatement notice afterwards. Where residential receptors are within earshot, a short assessment to BS 4142 establishes the rating level against the background and shows what attenuation is needed, and a Noise Impact Assessment prepared at that stage also gives you the evidence if a complaint follows.
Acoustic enclosures, anti-vibration mounts, attenuators on intake and discharge, and siting away from the boundary are the usual answers. All of them cost less at specification stage.
Storage in the open air
This is where operators most often stray outside permitted development. Using an open yard for the storage of materials or finished goods can be a material change of use, depending on the scale, duration and whether it is ancillary to the building's use.
A pallet of finished goods awaiting collection is ancillary. A yard racked out and used as the primary storage operation, with vehicle movements to match, is a different use of the land and needs permission. Between those two poles the question is one of fact and degree, and the factors that matter are the proportion of the site used, the permanence of the arrangement, visibility from outside, and whether the activity has its own vehicle movements.
Where open storage is intended, apply for it. A permission with conditions on stacking height, position and hours is a manageable outcome, while an enforcement notice halting the operation is not. Our note on Part 6 Class B and small agricultural units covers the analogous problem of rights that permit a building but not the use it is put to.
Where an environmental permit is engaged
Certain industrial processes require a permit under the Environmental Permitting (England and Wales) Regulations 2016, issued by the Environment Agency or by the local authority depending on the process.
Planning and permitting are separate. A permit does not authorise development, and permission does not authorise emissions. What matters practically is that the two should be applied for in a coordinated way, because the permit application will describe the plant and the abatement in detail, and inconsistency between that description and the planning drawings is the kind of thing an objector finds.
Where the process is permitted, the planning authority should not duplicate the pollution control regime, and national policy expects it to assume the permitting regime will operate effectively. That is a helpful argument, and it is not a complete answer, because amenity effects such as noise, dust and visual impact remain planning matters.
Recording the installation date
Permitted development leaves no paper trail, which becomes a problem the day somebody asks whether the plant is lawful.
Keep, for each installation:
- Dated photographs from a fixed position, showing the plant in place.
- The supplier's invoice and dimensioned drawing.
- A site plan marking the position, with the height and the datum used.
- A short note recording which class of Part 7 was relied on and the text of that class as it stood on the date.
Time limits for immunity from enforcement apply to operational development and have historically been four years, with the Levelling-up and Regeneration Act 2023 providing for a move to ten, so check the current position for the date of the works. Where the position is arguable, a certificate of lawfulness under section 191 of the Town and Country Planning Act 1990 settles it, and a Planning Statement setting out the history is the core of that application.
To see which supporting documents an industrial application is likely to need, browse the planning report types by category.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. A Lawful Development Certificate is the only formal way to confirm that works are lawful.
Frequently asked questions
Does Part 7 allow any size of external plant?
No. The plant and machinery class permits installation up to a stated height measured from a specified datum, with a lower limit near the curtilage boundary. Rooftop units are the common breach because the measurement basis is not the roof surface. Check the current text of the class and the supplier's dimensioned drawing before ordering.
Can a planning condition remove Part 7 rights?
Yes, and on modern industrial estates it frequently has. Estate-wide permissions often carry conditions requiring approval of external plant, restricting outdoor storage or removing permitted development rights outright. The condition overrides the Order, so read the original permission and any subsequent variations before relying on Part 7.
Is laying hardstanding in an industrial yard permitted development?
Within the curtilage of an industrial building or warehouse, and for purposes incidental to the undertaking, generally yes within the limits of the relevant class. That covers circulation, parking and loading. It does not cover surfacing as a first step towards an open storage operation, which may itself be a material change of use.
When does open storage become a change of use?
It is a question of fact and degree. A pallet awaiting collection is ancillary to the building's use. A yard racked out as the primary storage operation with its own vehicle movements is a different use of land. The proportion of the site used, permanence, visibility and traffic generated are the factors that decide it.
Does an environmental permit deal with planning noise concerns?
Not entirely. Permitting and planning are separate regimes, and national policy expects the planning authority to assume the pollution control regime will operate effectively rather than duplicating it. Amenity effects including noise, dust and visual impact remain planning matters, so design to a noise limit rather than relying on the permit.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.