Main modifications at a local plan examination
Main modifications are the changes an examining inspector recommends to make a submitted local plan sound or legally compliant. They can only be recommended if the council asks, and the council must adopt them or not adopt the plan.
A main modification is a change to a submitted local plan that the examining inspector considers necessary to make the plan sound or legally compliant, and the inspector can only recommend one if the council has asked for it. That request, made under section 20(7C) of the Planning and Compulsory Purchase Act 2004, is what puts main modifications local plan changes into the inspector's hands. Once the report arrives the council either adopts the plan with those changes or does not adopt it at all. There is no third route where the authority keeps the modifications it likes and drops the rest.
Consultants who pick up an examination after the hearings often misread this. The schedule of main modifications is not a negotiating position. It is the price of a sound plan, and the council set that price itself when it made the request.
Main and additional modifications do different jobs
Two sets of changes come out of an examination, and they travel by different routes.
Main modifications go to soundness or legal compliance. They change what a policy requires, add or delete a site allocation, alter a housing requirement figure, or repair wording that would leave a policy ineffective in practice. The inspector recommends them and lists them in a schedule appended to the report.
Additional modifications, which most councils call minor modifications, are the authority's own tidying. Typographical corrections, paragraph renumbering, updated evidence references, a clearer sentence that leaves the policy's effect untouched. Section 23(3) of the 2004 Act allows the council to make those on adoption without any recommendation, so long as they do not materially affect the policies.
The boundary between the two is where most arguments sit. A change presented as minor that moves a settlement boundary by 40 metres, or turns "should" into "will", is doing policy work and belongs in the main schedule. If a council tries to shift something across that line, object in writing during the modifications consultation and explain the practical consequence for decision-taking rather than complaining about procedure alone.
Only the council can ask for them
The inspector recommends main modifications only if the local planning authority requests it. Most councils make that request in the submission letter as routine, and the request is normally open-ended rather than limited to particular policies.
Without the request, an inspector who finds the plan unsound has one option: recommend non-adoption. That outcome wastes years of plan-making, which is why the request is almost always made. It also means the inspector's hands are tied in the other direction. Where the authority has asked for modifications, the inspector cannot simply approve a plan that falls short and leave the gaps for a future review.
A related point catches out promoters. The inspector can recommend modifications that no party proposed. Hearing discussion that exposes a problem in a policy the authority thought settled can produce a modification nobody asked for, so attending sessions on policies you did not make representations about is often worthwhile. Testing your plan against the soundness tests before the hearings, covered in our note on soundness at a local plan examination, is the surest way to predict where those modifications will land.
Consultation and sustainability appraisal
Main modifications have to be published for representations before adoption. Six weeks is the normal period, and the council publishes the schedule alongside any updated sustainability appraisal and habitats regulations assessment work.
That appraisal step is the one councils underestimate. Where a modification introduces a new allocation, increases the yield on an existing one, or removes a policy that carried mitigation, the strategic environmental assessment has to be revisited under the Environmental Assessment of Plans and Programmes Regulations 2004. Publishing an addendum late, or not at all, is a legal compliance problem rather than a presentational one, and it has grounded successful challenges to adopted plans.
Representations at this stage are considered by the inspector, not by the council's planning committee. They must address the modifications themselves. A representation that reopens an objection to a policy left unchanged will be set aside, however well argued.
What the inspector's report does and does not settle
The report says whether the plan, with the recommended main modifications, satisfies the legal requirements and is sound. Both the report and the schedule are binding in the sense that adoption under section 23(3) has to include the main modifications as recommended.
What the report does not do is fix the meaning of a policy for all time. An inspector's reasoning on a modification is a strong indication of intent, and decision-makers read it, but the adopted policy wording governs. Where a modification leaves genuine ambiguity, expect that ambiguity to be argued at appeal within a year.
The report also carries no weight against a different plan. Reasoning about a green gap policy in one district tells you how one inspector approached one evidence base, so use it as an argument rather than as authority.
Effect on sites, policies and the weight they carry
For a landowner or promoter, the practical question is what happens to your site during the modifications window.
| Position at examination | Typical route | Effect on weight |
|---|---|---|
| Allocation added by main modification | Consulted on for six weeks, then adopted | Full development plan weight on adoption |
| Allocation deleted by main modification | Consulted on, then removed | Falls away entirely on adoption |
| Policy wording relaxed or tightened | Main modification schedule | Applies as adopted, including to undetermined applications |
| Typographical fix | Additional modification on adoption | No change to policy effect |
Applications already in the system are decided against the development plan as it stands at the time of the decision, so a plan that is adopted mid-determination changes the policy basis of a live application. Where the modification is adverse, a case officer will normally invite an amended Planning Statement addressing the new wording rather than refusing outright. Where the modification introduces an affordable housing requirement that did not previously apply, an Affordable Housing Statement will be added to the validation list for later applications.
How they delay adoption, and by how much
Main modifications add time. The schedule has to be drafted, the appraisal addendum prepared, the consultation run for six weeks, the responses passed to the inspector, and the final report written. Councils commonly allow several months between the close of hearings and adoption for exactly this, and complex plans with many modifications take longer.
Two things extend that further. Where the inspector suspends the examination for further evidence, such as a revised housing land supply position or new highway modelling, the modifications consultation happens after the suspension lifts. And where the consultation responses raise a point the inspector accepts, a second round of consultation on revised modifications follows.
Anyone relying on plan adoption for a development timetable should treat the council's published timetable as an intention rather than a commitment, and watch the examination library for the inspector's post-hearing letters instead. Those letters usually signal the shape of the modifications months before the schedule appears.
Making representations that actually get read
The representations that change modifications share a pattern. They identify the specific words in the specific modification, explain why those words fail one of the soundness tests, and offer alternative wording the inspector could adopt.
- Quote the modification number and the text you object to, without summarising it in your own words.
- Name the soundness test engaged, and say why the modification fails it on the evidence in the examination library.
- Point to the document and page in that library that supports your position.
- Offer replacement wording that is capable of being recommended as it stands.
- Say what the modification would mean for a real decision, such as an application that could not be determined consistently under the new wording.
Short submissions do better. An inspector working through several hundred representations on twenty modifications will find a two-page letter with precise wording more useful than a forty-page critique of the plan. Leave the plan's strategy alone at this stage. That argument is over.
Where a modification reshapes the evidence you need for a forthcoming application, checking which documents the new policies will require is quicker than waiting for the validation list to catch up, and the full list of planning report types is a reasonable starting point for that exercise.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.
Frequently asked questions
What is the difference between a main modification and a minor modification?
A main modification goes to soundness or legal compliance and has to be recommended by the inspector, then consulted on before adoption. A minor or additional modification is the council's own tidying, such as typographical corrections or renumbering, made under section 23(3) of the 2004 Act without a recommendation, provided it does not materially affect any policy.
Can a council refuse to accept a main modification?
Not selectively. Where the council has asked the inspector to recommend main modifications, adoption must include them as recommended. The only alternative is to decline to adopt the plan, which restarts plan-making and loses the evidence base's currency. That is why authorities almost never reject a schedule outright.
How long is the consultation on main modifications?
Six weeks is the normal period, published alongside the schedule and any addendum to the sustainability appraisal and habitats regulations assessment. Representations go to the inspector rather than to the planning committee, and they must address the modifications rather than reopening objections to unchanged policies.
Do main modifications affect an application already submitted?
Yes. An application is determined against the development plan in force at the time of the decision, so a plan adopted during determination changes the policy basis. Case officers usually ask for an amended planning statement addressing the new wording rather than refusing, but any new policy requirement applies from adoption.
Can an inspector recommend a modification nobody asked for?
Yes. If hearing discussion exposes a soundness problem in a policy that no party challenged in writing, the inspector can recommend a modification to fix it. That is one reason promoters attend sessions on policies they did not make representations about, because the first sight of a change can otherwise be the published schedule.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.