Refusals and Appeals

Making the statement of common ground do real work

7 min readBy PlanScope Editorial Team

A statement of common ground fixes the facts so the inquiry can spend its time on the contested judgements. Here is what to agree, how to record disagreement and how to handle a silent council.

A statement of common ground is the document that tells the inspector which facts are not in dispute, so that inquiry or hearing time is spent on the questions that actually decide the appeal. It is required for inquiries and hearings under the appeal procedure rules, and the Planning Inspectorate's procedural guide sets the date yours has to arrive. Treated properly it removes a day of evidence. Treated as a formality it becomes a liability, because an inspector who finds the parties arguing about the site area on day two will draw conclusions about the rest of your evidence.

The discipline is simple. Agree everything capable of agreement, record the disagreements in terms both sides would accept, and do it before proofs of evidence are exchanged rather than after.

What the document is for

The statement is a joint document of the appellant and the local planning authority. It is not advocacy, and it carries no argument about weight or planning balance. Its purpose is to fix the factual and policy baseline so that the proofs can go straight to the contested judgements.

Post-Rosewell inquiry practice pushes this work earlier. Case management directions commonly require a draft statement in advance of the case management conference and a signed version well before proofs, which is a change from the older habit of finalising it the week before. Read the start letter and the directions rather than working from the default in the rules, because the inspector's timetable governs.

A good statement also does something the rules do not require. It gives the inspector a single reliable description of the site, the proposal and the policy framework, which means your proof does not have to spend 800 words setting the scene.

Facts that should always be agreed

Start from the position that anything measurable is agreeable. The list below is the working minimum for a residential appeal, and most of it transfers to commercial cases.

  • The site area, the red line, ownership and the certificate served.
  • The description of development as amended, and the final list of drawings and documents before the authority, with revision numbers.
  • The planning history of the site, including any lawful development certificate, extant permission or previous refusal, with reference numbers and dates.
  • The development plan, the date each document was adopted, and the full text of every policy either party relies on.
  • Which policies the authority accepts are out of date, and whether the tilted balance is engaged.
  • Housing land supply position as at an agreed base date, or an agreed statement that the parties disagree and by how much.
  • Constraints: flood zone, conservation area, listed buildings within a stated radius with their grades, tree preservation orders, Green Belt status.
  • The consultation responses received and which statutory consultees objected.
  • The conditions both sides agree should be imposed if the appeal succeeds, and any section 106 heads of terms.

Agreeing the drawing list sounds trivial. It is the item that most often unravels, because an authority determined the application on revision C and the appellant appealed on revision D. Sort that out in the statement and the inspector knows which scheme is before them.

The policy text matters for the same reason. Reproducing the relevant parts of the adopted plan in an appendix, agreed and paginated, stops the hearing turning into a search through a 400-page document. Where your case rests on how the proposal meets a design or heritage policy, the reasoning belongs in the Planning Statement and the proof, and the agreed policy wording belongs here.

When the council will not engage

This happens, usually because the case officer has left, the authority is under-resourced, or the refusal was contrary to officer recommendation and nobody internally owns the appeal. The answer is to do the work for them.

  1. Send a complete draft with everything agreed from your side, tracked and dated, plus a short covering note listing the five or six matters you expect to be contentious.
  2. Set a reasonable deadline aligned with the inspector's timetable and copy the case officer's line manager.
  3. If there is no response, send a unilateral statement clearly marked as such, recording what was sent, when, and that the authority did not respond.
  4. Raise it at the case management conference. Inspectors are alert to it and will usually direct a date.

A unilateral statement is weaker than an agreed one. It still protects you, because it shows the inspector that the delay is not yours and it gives a factual baseline nobody has contradicted. It can also support an application for costs on the ground of unreasonable behaviour, though that is a separate exercise with its own evidential threshold.

Technical appendices and agreed modelling

The highest-value agreement in most inquiries is technical. Two acoustic consultants disagreeing about a measured background sound level waste more inquiry time than any policy point, and the disagreement is usually about method rather than outcome.

Agree the inputs before the outputs. For transport, that means the trip generation source, the survey dates, the assessment years and the junction models used. For daylight and sunlight, the BRE 209 (2022) targets applied, the window mapping, the model geometry and whether existing rooms have been surveyed internally. For flood risk, the climate change allowance applied, the modelled levels and the source of the topographic survey. For ecology, the survey effort, the dates, the seasons covered and the habitat baseline entered into the statutory metric.

Where the parties agree the inputs, the remaining difference is professional judgement, which is exactly what an inspector is there to weigh. Where the inputs differ, the inspector has to resolve a technical dispute with no independent evidence, and both sides usually lose something.

A short worked illustration, and it is illustrative only. On an appeal about a 40-unit scheme, the parties agreed the TRICS site selection, the survey period and the distribution, and disagreed only on whether a 12 per cent trip reduction for the travel plan was justified. That single agreed appendix reduced two transport proofs to eight pages each and took half a day out of the inquiry.

Recording disagreement precisely

Most statements are too vague about what is in dispute. "The parties disagree about heritage impact" tells the inspector nothing. "The parties agree the appeal building is a non-designated heritage asset and that the proposal would remove the rear wing. They disagree about whether the resulting harm is low or moderate, and about the weight to be given to it" tells the inspector what to listen for.

Write each disagreement as a question the inspector can answer. Keep the wording neutral, so that neither side is quoting the other's case back at them. And resist the temptation to slip an argument into the description of the dispute, because the authority will ask for it to come out and you will have spent a week on drafting rather than on evidence.

Where a matter has been agreed subject to a condition, say so and attach the condition wording. Where agreement depends on a survey that has not been completed, record the date it is expected. Inspectors accept provisional entries when they are labelled as such. They do not accept a statement that quietly goes silent on a live issue. Reading the refusal reasons closely at the outset pays here, and our note on reading reasons for refusal covers how to translate them into a list of agreed and disputed matters.

Signing, late changes and the inquiry itself

The statement should be signed by someone with authority on each side, usually the appellant's agent and the authority's appeals or development management manager. Date it. If facts move after signature, issue a short addendum rather than reissuing the whole document, and flag it in your opening submissions.

Late changes are survivable. Concealed changes are not. If a housing land supply position updates between signature and the inquiry, tell the inspector on day one and hand up an agreed note. The alternative is a cross-examination question you cannot answer.

Inspectors use the statement as the factual spine of the decision letter. Passages describing the site, the history and the policy framework frequently appear in the decision in close to the agreed wording, which is a good reason to draft those sections with care. Your proof of evidence can then open on the first contested issue. Third party evidence sits outside the statement and is handled separately, as our note on interested party representations explains.

This is general guidance on appeal procedure, not legal advice, and the timetable for your appeal is set by the Inspectorate's directions rather than by any general rule. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Browse all 66 PlanScope report types if you are rebuilding the evidence base before a resubmission.

Frequently asked questions

Who prepares the statement of common ground?

It is a joint document of the appellant and the local planning authority. In practice the appellant's agent usually produces the first full draft because they have the drawings, the history and the policy extracts to hand, and the authority then comments. Both sides should sign it, and each needs someone with authority to commit the organisation to the agreed facts.

When does the statement have to be submitted?

The deadline comes from the Inspectorate's start letter and any case management directions, not from a single fixed rule you can assume. Post-Rosewell inquiry practice often requires a draft before the case management conference and a signed version ahead of proofs of evidence. Check the timetable for your appeal and diarise the date as soon as it arrives.

What if the council refuses to agree anything?

Send a complete draft with a deadline, copy the case officer's manager, and if nothing comes back submit a unilateral statement clearly labelled as such. Record what you sent and when. Raise it at the case management conference so the inspector can direct a date, and keep the correspondence in case you later apply for costs.

Should the statement include planning arguments?

No. It records agreed facts, agreed policy text and a neutral description of what is in dispute. Argument about weight, harm and the planning balance belongs in proofs of evidence. Authorities routinely ask for advocacy to be stripped out of drafts, and drafting it in simply costs you a round of comments you did not need.

Can technical modelling be agreed in the statement?

Yes, and it is usually the highest-value agreement available. Agree the inputs rather than the conclusions: survey dates, assessment years, trip rate sources, climate change allowances, BRE targets, habitat baselines. Once the inputs are common, the remaining difference is professional judgement, which is what the inspector is there to weigh.

What happens if facts change after signature?

Issue a short signed addendum rather than reissuing the whole document, and draw the inspector's attention to it in opening submissions or at the start of the hearing. Housing land supply figures and consultation positions move often enough that addenda are routine. Concealing a change is the risk, not the change itself.

Sources and further reading

appealsplanning inquirystatement of common groundplanning consultantevidence

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Refusals and Appeals

View all →
Refusals and Appeals8 min read

Refusal on fire safety information at Gateway One

A Gateway One refusal is usually about what is missing from the drawings rather than anything wrong with the building, which makes it a drafting failure with a determination period attached.

Read article →
Refusals and Appeals8 min read

Lapsed permissions, withdrawn appeals and the route back

There is no extension application and no revival procedure for an expired permission. What you have is a fresh application on a site with a helpful planning history.

Read article →
Refusals and Appeals8 min read

Refusal where the development plan is out of date

The out-of-date plan argument is the most powerful move on appeal and the most frequently mishandled, because appellants assert the trigger rather than proving it.

Read article →
Refusals and Appeals8 min read

Contamination refusals without intrusive investigation

A desk study that identifies a credible pollutant linkage and then stops can get an application refused outright. The gap is between what the report raised and what the application proved.

Read article →
Refusals and Appeals6 min read

HMO refused for over-concentration: testing the count

Concentration refusals turn on data the council never compiled for the purpose. How to test the count address by address and answer the supporting reasons.

Read article →
Refusals and Appeals6 min read

Front garden parking refused: hardstanding and the kerb

Two consents, two decision makers. What the permitted development condition on surfacing actually says, and why the highway authority refuses most crossings on depth.

Read article →