Viability, Obligations and Commercial

Mortgagee exclusion clauses in a planning obligation

7 min readBy PlanScope Editorial Team

Lenders will not fund land burdened with obligations they cannot perform. How the exclusion works, why possession rather than ownership is the trigger, and the controlled process authorities accept.

No lender will fund a scheme where enforcement of its security could leave it holding land burdened with obligations it cannot perform. A mortgagee exclusion clause answers that: the planning obligations do not bind the mortgagee, any receiver it appoints, or a purchaser from them, except to the extent the clause says they do. It is standard in section 106 agreements and the negotiation is usually about scope rather than principle.

The authority's interest is the mirror image. Section 106 of the Town and Country Planning Act 1990 makes obligations enforceable against the person who entered into them and against successors in title, which is what gives the authority comfort that affordable units will still exist in twenty years. A broad exclusion weakens that, and on affordable housing it can mean the units are lost.

Why lenders insist on the clause

A development loan is secured on the land. If the borrower defaults, the lender wants to realise the security by appointing a receiver or by selling, and it wants the sale to be of land it can value.

Obligations that run with the land are a valuation problem. A requirement to transfer twelve units to a registered provider at a discounted price, to pay a contribution on occupation, or to construct a highway improvement all reduce what a purchaser will pay and may be impossible for a lender to perform at all, since a lender is not a housebuilder. Without the exclusion, credit committees either decline or price the uncertainty into the facility.

So the clause is not a negotiating flourish. It is a condition of the funding, and on most schemes the funding is a condition of the development happening.

What the standard exclusion covers

The usual formulation excludes from the obligations any mortgagee or chargee of the whole or part of the site, any receiver appointed by them, and any person deriving title through them, with the important qualification that such a person becomes bound if and for so long as it takes possession of the land.

Three features deserve a careful read in any draft.

The exclusion is normally personal rather than permanent. It protects the lender while it is enforcing, and a purchaser who buys and then develops becomes bound. A clause that releases the land itself rather than protecting the person is far wider, and authorities should resist it.

The trigger for being bound is usually possession, not ownership. A lender with a charge is not bound. A lender in possession, or a receiver running the site, generally is. That distinction is the whole architecture of the clause.

And the exclusion rarely covers everything. Obligations that are restrictive in nature, such as a covenant not to occupy more than a stated number of units before a trigger is met, often remain enforceable against anyone, because they restrict use rather than requiring performance.

Party Bound by the obligations Typical qualification
Developer entering the deed Yes Fully bound
Successor in title buying the site Yes Bound as successor under section 106
Mortgagee holding a charge No Not bound while it has no possession
Mortgagee in possession or receiver Yes, in most drafts Bound while in possession, often with carve-outs
Purchaser from a mortgagee in possession Varies The point most heavily negotiated
Statutory undertaker taking an easement No Standard exclusion in most agreements

Effect on the authority's ability to enforce

For financial contributions the practical effect is modest. The authority's remedy is usually against the person who was bound when the trigger occurred, and a scheme that stalls before the trigger was never going to pay in any event.

For affordable housing the effect is substantial, because the obligation is the thing the authority bargained for and a release means the units become market housing. That is why most authorities accept a mortgagee exclusion for the general obligations and insist on a controlled process for the affordable housing element.

The controlled process is the sensible compromise, and it looks the same in most agreements: before the lender can dispose free of the affordable housing restrictions, it must give the authority written notice, allow a period in which the units can be marketed to another registered provider, and only then sell on the open market, often with a provision that part of the proceeds goes to the authority. The negotiation is about the length of the periods and who bears the marketing cost.

Registered provider funding requirements

Where affordable units are transferred to a registered provider, the provider's own lender needs protection too, and that produces a second mortgagee clause with a different shape.

Registered providers borrow against their stock, and their funders require the ability to realise that security if the provider fails. The usual mechanism gives the provider's lender a right, on enforcement, to dispose of the units free of the affordable housing restrictions after a defined process: notice to the authority, a period during which the units must be offered to other registered providers at a price reflecting their value as affordable housing, and a fallback allowing open market disposal if no provider takes them.

Three practical points. The periods required by different providers and their funders are not identical, so agree the clause with the named provider rather than drafting generically. Grant funding adds its own conditions, and a scheme relying on grant should check the funder's requirements before the deed is engrossed. And the authority will usually want a recycling provision directing any surplus to affordable housing elsewhere in the area.

Where the affordable offer itself is contingent on viability, these clauses interact with any review mechanism, and the interaction is easy to get wrong, as our note on affordable housing review mechanisms describes.

Negotiating the wording

Four points carry most of the value, and all four are easier to settle before the deed goes to the authority's solicitor than after.

  1. Define possession precisely, and say whether a receiver appointed under the charge is treated as in possession for the purpose of the clause.
  2. Separate the general exclusion from the affordable housing provisions, in different clauses, so that a later variation of one does not disturb the other.
  3. State which obligations survive the exclusion, by clause number rather than by description, because a description invites argument about whether a given covenant is restrictive or positive.
  4. Deal with partial disposals. A lender enforcing over one phase of a multi-phase site creates questions about apportionment of contributions and affordable units that generic wording does not answer.

Where an authority resists

Resistance usually comes from a legal team that has seen affordable housing lost under a loosely drafted clause, and the way through is to narrow the clause rather than to argue the principle.

Offer the authority three things. A short notice period before any disposal free of the restrictions, so that it finds out in time to act. A marketing obligation to other registered providers with the price basis stated. And a recycling provision for any surplus. Authorities that have refused a bare exclusion will often agree one with those protections attached, and the lender usually accepts them because they do not prevent realisation of the security.

Where an authority refuses outright, the options are to escalate to the head of planning with the funding timetable attached, or to accept a narrower clause and go back to the lender. The second is often faster. A deal that completes with an imperfect clause beats a perfect clause on a scheme that never funds.

Timing against the funding agreement

The sequence that works runs backwards from financial close. Obtain the lender's required wording early, before the heads of terms for the obligation are agreed, because retro-fitting it into an agreed draft restarts the authority's legal review. Share it with the registered provider at the same time, since their funder's requirements may conflict with the development lender's.

Then build the review time into the programme honestly. A mortgagee clause negotiated between three sets of solicitors and a local authority legal team takes weeks, and it sits on the critical path to the decision notice. Schemes that discover this late end up either delaying the committee or signing an agreement the lender then refuses to accept, which means a deed of variation before a single brick is laid.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope drafts the planning statements and the Affordable Housing Statement narrative that accompany an application, alongside the Viability Assessment structure, rather than the deed itself. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is a mortgagee exclusion clause?

A provision in a section 106 agreement stating that the planning obligations do not bind a mortgagee or chargee of the site, a receiver it appoints, or a person deriving title through them, usually with the qualification that such a person becomes bound if and for so long as it takes possession of the land.

Why do lenders require one?

Because a development loan is secured on the land, and obligations running with the land reduce what a purchaser will pay and may be impossible for a lender to perform. A lender is not a housebuilder and cannot transfer affordable units. Without the clause, credit committees either decline or price the uncertainty into the facility.

Does the clause mean affordable housing can be lost?

It can, which is why most authorities accept an exclusion for general obligations and insist on a controlled process for affordable housing: written notice to the authority, a period in which the units must be marketed to another registered provider, and open market disposal only after that, often with a share of proceeds recycled.

Is a lender bound if it holds a charge but has not taken possession?

Under the standard drafting, no. The trigger for being bound is possession rather than ownership of a charge, so a lender holding security is outside the obligations while a lender in possession or a receiver running the site is generally within them. Check how the draft defines possession and treats receivers.

When should the clause be agreed?

Before the heads of terms for the obligation are settled. Obtain the lender's required wording early and share it with the registered provider at the same time, because their funder's requirements may conflict. Retro-fitting the clause into an agreed draft restarts the authority's legal review and sits on the critical path.

Sources and further reading

section 106mortgagee exclusionaffordable housingfundingplanning obligationsdevelopment

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial8 min read

Marriage value and site assembly in a viability appraisal

Assembly costs are real, but most of them do not reduce what a scheme can contribute. Where acquisition costs, ransom premiums and created marriage value each belong in the appraisal.

Read article →
Viability, Obligations and Commercial7 min read

Varying a planning obligation after five years

After the five year relevant period, a statutory application under section 106A replaces negotiation, and a refusal can be appealed under section 106B. What the authority can decide and what it cannot.

Read article →
Viability, Obligations and Commercial7 min read

Social infrastructure contributions and how they are justified

Contribution requests are built from a yield factor, a capacity claim and a published cost. The arithmetic is usually right, so the argument belongs on the capacity evidence and the statutory tests.

Read article →
Viability, Obligations and Commercial7 min read

Pooling restrictions and clawback in planning obligations

Regulation 123 and the five obligation pooling cap went in September 2019. What remains is the statutory test in regulation 122, the infrastructure funding statement, and careful drafting against duplication.

Read article →
Viability, Obligations and Commercial8 min read

Indexation of section 106 contributions and which index applies

The index family and the base date decide how far an indexed contribution moves. Name the series exactly, set the base date to the prices the figure is expressed in, and recalculate every demand.

Read article →
Viability, Obligations and Commercial8 min read

Phasing a scheme to manage section 106 triggers

Phasing moves when obligations fall due rather than how much they total. Define phases by land parcel, build in a revised phasing plan mechanism, and tie affordable delivery to occupation within each phase.

Read article →