Data Tools How-To

Obtaining modelled flood levels from the Environment Agency

6 min readBy PlanScope Editorial Team

The flood map gives a zone, not a level. Here is how to request the Environment Agency's detailed modelled data, which events to ask for, and how to use it against surveyed site levels.

The flood map for planning tells you which zone a site sits in. It does not tell you the level the water reaches, and for anything that needs a finished floor level, a freeboard or a safe access route, the level is the number you need. That comes from a separate request to the Environment Agency for its detailed modelled flood data, and it takes weeks rather than minutes.

Request it at the start of the project. Applicants who leave it until the flood risk assessment is being written lose a month they did not plan for.

What a detailed flood data request returns

Where a hydraulic model exists for the watercourse, the Environment Agency can supply the modelled outputs behind the published map.

A typical response includes flood levels at model node points, given in metres above Ordnance Datum, for a range of return periods and for defined climate change scenarios. It usually also includes flood extents, the location of the nodes relative to the site, and information about the model itself: when it was built, what it covers, and any known limitations.

The last part matters more than people expect. A model built for a strategic study fifteen years ago, upstream of a scheme that has since changed the channel, is data with a caveat attached, and the caveat belongs in your report.

Some information is published free under the Open Government Licence and some involves a charge for staff time. Check the current position and the published turnaround before you build a programme around it.

Choosing the right event and return period

Ask for what the assessment needs rather than everything available, and say what the site is.

For fluvial sites the design event for most development is the one per cent annual exceedance probability flood, commonly called the one in a hundred year event, with the climate change allowance applied. For tidal and coastal sites the equivalent is the half per cent event. The extreme one tenth of one per cent event is used to test residual risk and the consequences of defence failure or overtopping.

Ask for the undefended as well as the defended case where defences exist, because the assessment has to consider what happens if they fail. And be specific about where you want node data, giving a grid reference and the red line boundary, because a level at a node 800 metres downstream of your site is not the level at your site.

Climate change allowances applied to the output

Allowances are published by the Environment Agency for peak river flow and for peak rainfall intensity, varying by management catchment, by the period being considered and by the allowance category.

Two things follow. The allowance to use depends on the vulnerability of the development and the lifetime you are assessing, which for residential is conventionally taken as a long horizon. And the allowances are revised periodically, so a level taken from a report written three years ago may be based on a superseded figure.

State in the assessment which allowance category you applied, for which period, and from which published version. A reviewer checks that before anything else.

Turnaround, fees and programme

Treat the request as a long lead item.

The published service standard varies and requests involving bespoke work take longer than those answered from existing outputs. There is no realistic way to accelerate it, and a request made a fortnight before a target submission date will not be answered in time.

Two practical habits help. Send the request as soon as the site is under offer rather than after planning fees are committed. And ask the lead local flood authority at the same time for anything it holds, because surface water and ordinary watercourse flooding sit with that authority rather than with the Environment Agency, as does the strategic flood risk assessment that may already contain the level you need.

Reading the output against site survey levels

This is where the arithmetic gets done, and where errors are expensive.

Modelled levels are given to Ordnance Datum. Your site levels have to be on the same datum, from a measured topographical survey tied to a benchmark, not from remotely sensed national data. Comparing a modelled level against an approximate ground level produces a finished floor level you cannot defend.

Where the nearest node is some distance away, interpolating between nodes along the channel is normal practice, but the method has to be stated and it has to account for the gradient of the water surface. Do not average two nodes either side of a structure.

Then add freeboard. A margin above the design level is standard practice, commonly a few hundred millimetres, with the precise figure set by the local planning authority or the Environment Agency in its consultation response. Our note on setting finished floor levels and freeboard on a flood site works through the calculation in full.

When no model exists

Plenty of watercourses have never been modelled, particularly ordinary watercourses and small catchments, and a request will come back saying so.

Three routes remain. Commission hydraulic modelling, which is proportionate for a scheme of any size but heavy for a single dwelling. Use a simplified hydrological estimate of flows and a conservative approach to levels, agreed in advance with the authority. Or design out the problem by raising levels well clear of any plausible flood level and demonstrating safe access, which is often the practical answer on a small site.

Whichever route, agree the approach with the Environment Agency or the lead local flood authority before doing the work. An unagreed methodology is the most common reason a flood risk assessment comes back.

One habit worth adopting on any site with defences. Ask what standard the defences provide, who maintains them, and whether they are formal Environment Agency assets or privately held. A scheme relying on a privately maintained embankment with no maintenance agreement is relying on something that may not be there in thirty years, and a consultee will say so.

Using the data in a flood risk assessment

The levels feed almost every part of the document.

They set the finished floor levels and the freeboard. They determine whether safe access and egress can be achieved above the design level. They inform the resistance and resilience measures for the residual risk case. They underpin the Sequential Test where one is required, and they establish the baseline against which any compensatory storage is designed.

Put the data request, its reference and its date in an appendix to the Flood Risk Assessment, along with the model information and the caveats supplied with it. An assessment that quotes a level without saying where it came from will be queried, and the query costs more time than the appendix would have.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

Enter your postcode on PlanScope to see which reports a site in a flood zone is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the difference between the flood map and modelled flood data?

The flood map for planning shows flood zones, which are broad categories of probability. Detailed modelled data gives actual water levels at model node points in metres above Ordnance Datum for defined return periods and climate change scenarios, together with information about the model. You need levels rather than zones for finished floor levels, freeboard and safe access.

How long does a flood data request take?

Weeks rather than days, and longer where bespoke work is involved. The published service standard varies, and there is no realistic way to accelerate it. Send the request as soon as the site is under offer rather than when the flood risk assessment is being written, and ask the lead local flood authority for its records at the same time.

Which return periods should I ask for?

For fluvial sites, the one per cent annual exceedance probability event with climate change applied, which is the design event for most development. For tidal sites the half per cent event. Also ask for the extreme one tenth of one per cent event to assess residual risk, and for the undefended case where flood defences are present.

Can I use LiDAR levels to compare against modelled flood levels?

Only for an initial view. Anything that will be built to, including finished floor levels and thresholds, needs a measured topographical survey tied to a benchmark and on the same datum as the modelled levels. Comparing a modelled level against a remotely sensed approximate ground level produces a floor level that cannot be defended at consultation.

What if the Environment Agency has no model for my watercourse?

That is common for ordinary watercourses and small catchments. The options are to commission hydraulic modelling, to use a simplified hydrological estimate with a conservative approach to levels, or to raise levels well clear of any plausible flood level and demonstrate safe access. Agree the chosen method with the authority before doing the work.

Sources and further reading

flood levelsenvironment agencyflood risk assessmentdata requestclimate change allowancesself build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Data Tools How-To

View all →
Data Tools How-To7 min read

Checking coal mining and former mineral workings

A free online check tells you whether your site falls in a coal mining development high risk area. What follows is a risk assessment, often intrusive drilling, and a permit before anyone touches the coal.

Read article →
Data Tools How-To6 min read

Using the trip rate database for a small scheme

Trip rate data decides whether a small scheme needs junction modelling or a one-page statement. Here is how to select comparable survey sites, size the sample and present the rates so a highway officer can verify them.

Read article →
Data Tools How-To6 min read

Finding borehole and ground data before you buy a plot

Published borehole records and geological mapping cost nothing and answer most of the ground questions a desk study has to raise. Here is how to search them.

Read article →
Data Tools How-To7 min read

Checking Article 4 directions on planning.data.gov.uk

The national Article 4 dataset is the fastest first check on a site, and the least reliable last word. Here is how to use it properly.

Read article →
Data Tools How-To8 min read

Finding trip rate data and using it defensibly

The output is only as good as the site selection. Record the land use category, the filters, the included sites and the reason for every exclusion, then offer a sensitivity test.

Read article →
Data Tools How-To7 min read

Using aerodrome safeguarding maps

Safeguarding maps sit with the local planning authority, and the triggers cover far more than tall buildings. Check the map before the layout is fixed, not after.

Read article →