6 min readBy PlanScope Editorial Team

A modular classroom is either permitted development under Part 7 or a temporary permission. Siting decides which, and the playing field consultation decides the programme.

A modular classroom on a school site is usually either permitted development under Part 7 of Schedule 2 to the General Permitted Development Order 2015, or a temporary planning permission granted for a fixed number of years. Which of the two applies turns on floor area, height, how close the building sits to the site boundary, and whether it lands on a playing field. Temporary classroom planning is mostly a question of siting.

The deadline is the academic year, and the thing that breaks the programme is almost never the planning merits. It is the playing field consultation.

The school permitted development rights

Part 7 of the Order includes a class covering the extension or alteration of school, college, university and hospital buildings. The right is subject to limits on the additional floor space, on height, and on proximity to the boundary of the site, and it applies only where the building remains in use for the purposes of the institution.

Read the class text itself before relying on it. The limits are expressed as the lesser of a percentage of the original building's gross floor space and a fixed area, and the class carries conditions about the type of development and its position. An authority that disagrees with a reliance on the class will say so when a neighbour complains, which is late.

Two points recur. The right relates to the extension or alteration of a building, so a free-standing modular unit in the playground is a new building rather than an extension and sits outside it. And "original building" means the building as it stood at a defined date, so a school that has already used the allowance has nothing left.

Where the units are needed to support building works on the site, the temporary buildings right in Part 4 may be available instead, and that right is tied to the duration of the works.

Where temporary permission is needed

For a free-standing classroom block, assume a planning application. The application is a minor one rather than a householder one, and the usual choice is to apply for a temporary permission for a defined period, commonly three to five years.

A temporary permission is not a weaker permission. It is a different one, and it is granted because the authority accepts a building it would not accept permanently. Expect a condition requiring the building to be removed and the land restored at the end of the period.

Route When it fits Main risk
Part 7 permitted development Extension or alteration within the limits Allowance already used, or boundary distance breached
Part 4 temporary buildings Units supporting construction works on site Right ends with the works
Temporary planning permission Free-standing units for a bulge cohort Playing field consultation and duration conditions
Full planning permission Permanent accommodation Longer programme, more evidence

The temporary route also appears in other contexts where a use has to prove itself before a permanent consent is justified, as in our note on a rural workers dwelling and temporary permission.

Siting, and the playing field problem

Space on a school site is already allocated. A new classroom goes onto hard play, a grass pitch, a car park or a landscaped margin, and each has a consequence.

Development affecting land used as a playing field brings Sport England in as a statutory consultee, and it will assess the proposal against its own policy on playing field land. A proposal that takes pitch area without replacing it is likely to attract an objection, and an objection from a statutory consultee is what turns an eight week determination into a committee item.

There is a second consent to consider. Disposal or change of use of school playing field land can require consent from the Secretary of State for Education under section 77 of the School Standards and Framework Act 1998, which is separate from planning permission and runs on its own timetable.

Practical siting moves that avoid the worst of this: use hard play or a redundant car park rather than pitch area, keep the unit off the boundary so the permitted development distance limit is not the issue, replace lost pitch area elsewhere on the site where there is room, and show the retained pitch dimensions on the drawing against the governing body's sport standards.

Access, drainage and the things that get conditioned

The application is small, so the technical content should be proportionate. Five items cover most of it.

  1. Level access to the new building, with a ramp or level threshold detailed on the drawings and compliance with Approved Document M addressed.
  2. Fire escape routes from the new unit and the effect on existing escape routes across the playground.
  3. Surface water from the new footprint and any new hardstanding, with a drainage position even if the area is small.
  4. Services: the route of the electrical supply and any drainage connection, and whether a trench crosses a root protection area.
  5. Trees. A modular unit sited under a canopy needs a survey to BS 5837:2012, and the root protection area usually decides the final position.

Where the number of pupils on site increases rather than simply being rehoused, the highway authority will ask about the effect on the school run. A short Transport Statement setting out the pupil numbers before and after, staff numbers and any change to drop-off arrangements answers that without commissioning a full assessment.

Duration conditions and what happens at the end

Read the duration condition carefully. Three things matter: the date the period runs from, whether it runs from the permission or from first occupation, and what the condition requires at the end.

Extending the period is an application under section 73 of the Town and Country Planning Act 1990 to vary the condition, and it is a fresh planning judgement rather than a renewal. The authority can refuse. Schools that have had temporary units for a decade sometimes find the second or third extension refused, with the authority asking for a permanent solution instead.

Apply for the extension well before the period expires. A building standing without permission is a breach, and in an authority with an active enforcement team that becomes a letter to the governing body.

Working back from September

An illustrative programme for units needed for the following September:

  • Pre-application discussion with the authority and Sport England, including the siting options: six to eight weeks, ideally in the autumn term.
  • Tree survey and topographical survey: two to three weeks.
  • Drawings, a Planning Statement and a Design and Access Statement where the site is in a conservation area: three weeks.
  • Submission and validation: one to two weeks.
  • Consultation and determination: eight weeks for a minor application, longer if Sport England objects or the item goes to committee.
  • Section 77 consent where playing field land is involved: run in parallel and allow longer.
  • Groundworks, delivery and connection: four to eight weeks depending on the supplier.

That totals six to eight months on a straightforward site. Starting in the spring term for a September delivery is tight, and starting in the summer term usually means portable units arriving under a temporary arrangement that then has to be regularised.

Settle the siting first, with Sport England in the room. Everything after that is paperwork.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can a school add a classroom under permitted development?

Part 7 of Schedule 2 to the GPDO 2015 includes a class for the extension or alteration of school buildings, subject to limits on additional floor space, height and distance from the site boundary. A free-standing modular unit in the playground is a new building rather than an extension, so it normally falls outside the class.

When is Sport England consulted?

Where development affects land used as a playing field, Sport England is a statutory consultee and assesses the proposal against its own policy on playing field land. Taking pitch area without replacing it is likely to attract an objection, which turns a straightforward minor application into a committee item.

Is planning permission the only consent needed?

No. Disposal or change of use of school playing field land can require consent from the Secretary of State for Education under section 77 of the School Standards and Framework Act 1998. That runs on its own timetable alongside the planning application, so start it in parallel rather than afterwards.

How long does a temporary permission last?

Commonly three to five years, set by condition. Read the condition carefully for the date the period runs from and what it requires at the end, which is usually removal of the building and restoration of the land. Extending it is a section 73 application and a fresh planning judgement that can be refused.

How far ahead should a school start?

Allow six to eight months on a straightforward site: pre-application discussion and siting options, tree and topographical surveys, drawings and statements, validation, an eight week determination, any section 77 consent in parallel, then groundworks and delivery. Starting in the summer term for September rarely works.

Sources and further reading

schoolstemporary permissionpermitted developmentplaying fieldsmodular buildingsplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Project Type Guides

View all →
Project Type Guides7 min read

Re-cladding an existing residential block: planning rules

Replacing an external wall system materially affects the appearance of a block, so it needs permission. Here is what the application must cover and where planning ends and building safety begins.

Read article →
Project Type Guides7 min read

Setting up supported living in a house

Up to six residents living as a single household with care provided falls within Class C3(b), so no permission is needed. The single household test is what decides it.

Read article →
Project Type Guides7 min read

Converting a farm building into a holiday let

Class R allows an agricultural building to change to Class C1 hotel use, but a self-contained self-catering cottage usually needs a full application, and the works always do.

Read article →
Project Type Guides7 min read

Developing a corner plot with two frontages

Corner plots fail on three things: a blank side elevation, a boundary that blocks the junction, and overlooking in two directions. Here is how to resolve each before you apply.

Read article →
Project Type Guides7 min read

Filling a gap site in a conservation area street

Whether a gap is an opportunity for improvement or part of the character is answered in the council's own appraisal. What to measure before drawing anything.

Read article →
Project Type Guides7 min read

Building on a serviced plot from the self-build register

A self-build register plot usually arrives with outline permission and a design code. What is left for you is the application, the condition discharges and the exemptions.

Read article →