Glossary

Permission in principle: the two stage consent route

6 min readBy PlanScope Editorial Team

Permission in principle settles use, location and amount in five weeks, then technical details consent fixes the scheme. When it beats outline, and when it does not.

Permission in principle splits a housing consent into two decisions. The first stage establishes that the site is acceptable for housing in principle, fixing only the use, the location and the amount of development. The second stage, technical details consent, deals with everything else. It is a statutory route under section 58A of the Town and Country Planning Act 1990, and for a small self-build or infill scheme it can be faster and less costly than outline permission.

It is also narrower than most people expect, and it fails for a small set of predictable reasons.

What each stage decides

The first stage settles three things and nothing more: that the use is housing, where on the land development will go, and how much of it there will be, expressed as a minimum and maximum number of dwellings.

Design, access, drainage, ecology, parking, materials and layout are all left to the second stage. So is any question about the effect on neighbours, because those are matters for technical details consent rather than for the principle.

Technical details consent then fixes the scheme. It is a full application in substance, assessed against the development plan and material considerations, but the principle of housing on that land is already settled and cannot be revisited.

That division is the attraction. A landowner can establish that a paddock behind the village hall is acceptable for four houses without paying for a full design package, then either build out or sell with a consent that has real value.

Scale limits and the housing-led requirement

The application route is limited. Permission in principle by application is available for housing-led development that is not major development, which in practice means fewer than 10 dwellings on a site of less than one hectare.

Housing-led means housing must be the predominant use. A scheme with some commercial floorspace on the ground floor can qualify, provided the residential element dominates. A scheme that is mostly commercial cannot.

Several categories are excluded. Development requiring environmental impact assessment is out. So is development requiring an appropriate assessment under the Habitats Regulations. Where a site carries either of those, the route closes and an outline or full application is the alternative.

There is a second route that does not involve an application at all. Local authorities enter suitable brownfield sites on Part 2 of their brownfield land register, and entry grants permission in principle automatically. Ask whether your site could be entered rather than applying, because it costs nothing.

Timescales, fees and what expires

Stage Decision period Fee basis
Permission in principle 5 weeks Charged per 0.1 hectare of site area
Technical details consent, minor 8 weeks Equivalent to a full application
Technical details consent, major 13 weeks Equivalent to a full application

The five week period for the first stage is the shortest determination period in the English system, and it is one of the route's genuine advantages. Publicity requirements still apply, so the authority must consult before deciding.

Permission in principle has a life of three years from the date it is granted, unless the authority directs a longer or shorter period. A technical details consent application must be made within that window. Miss it and the principle lapses.

Fees are indexed annually, so check the current national fee schedule before budgeting. The per-hectare basis means a large site with few dwellings can cost more at stage one than a tight infill plot.

When it beats outline permission

Outline permission with reserved matters covers the same ground in a different order. The comparison comes down to three questions.

How much information does the authority need to decide the principle. Outline requires enough to assess the proposal properly, and authorities routinely request access details, ecology surveys and drainage information with an outline application. Permission in principle limits the authority to use, location and amount, which reduces the up-front spend.

How certain is the buyer. A technical details consent gives more certainty than reserved matters approval because the principle cannot be reopened. What outline permission leaves open is a genuine risk for a purchaser, and one that a two-stage route handles differently.

How constrained is the site. On a constrained site, the constraints have to be resolved eventually, and deferring them can mean a technical details refusal after the principle is established. Nobody benefits from a consent in principle for four houses that cannot physically be drained.

For an unconstrained infill plot in a settlement with a supportive policy, the route is efficient. For a site with flood risk, protected species or a difficult access, outline is usually the better instrument.

Why applications fail

The recurring reasons are consistent.

The most common is a site that is not acceptable for housing in principle at all, whether because it lies outside a settlement boundary, in the Green Belt, or on a protected employment allocation. Permission in principle does not lower any policy bar. It changes the sequence, not the test.

The second is insufficient information about the three matters the authority can consider. An application that gives a red line and no indication of the amount of development leaves the officer unable to grant anything, because the amount has to be stated as a range.

The third is a screening problem. Where the authority concludes that the scheme is environmental impact assessment development or requires appropriate assessment, the application cannot proceed on this route, and the fee is spent.

The fourth is more practical. Where the determination period expires without a decision, the applicant's remedy is an appeal against non-determination, and on a five week clock that arrives quickly. Authorities unfamiliar with the route sometimes treat it as an outline application and ask for documents they cannot require. Point to the statutory scope politely and in writing.

Preparing the technical details application

Once the principle is granted, the second stage is where the evidence base arrives. For a four-dwelling scheme that usually means a design and access statement, drainage details, an ecology report where habitat is present, and a Planning Statement tying the scheme to the development plan and to the terms of the permission in principle.

Keep the technical details scheme inside the parameters granted. A consent for a minimum of three and a maximum of five dwellings does not support an application for seven, and a location plan showing development on the northern half does not support a southern layout.

Consultation at the second stage is a full consultation, so neighbours who did not engage with the principle will engage with the detail. Expect comments on overlooking, parking and construction access, and answer them in the design rather than in correspondence.

And read the permission in principle notice carefully. Any direction shortening its life, and any restriction on the amount, is on that document.

To scope the documents your technical details application will need, browse the report types by category and work from your site details.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What can a permission in principle actually decide?

Three matters only: that the use is housing, the location of development on the land, and the amount of development expressed as a minimum and maximum number of dwellings. Design, access, drainage, ecology and layout are all reserved to the technical details consent stage and cannot be assessed at stage one.

What size of scheme qualifies?

Housing-led development that is not major development, meaning fewer than 10 dwellings on a site of less than one hectare. Some non-residential floorspace is allowed provided housing predominates. Development requiring environmental impact assessment or appropriate assessment under the Habitats Regulations is excluded from the route.

How long does a permission in principle last?

Three years from the date of grant unless the authority directs otherwise, and the direction appears on the decision notice. A technical details consent application must be made within that period. If it is not, the principle lapses and the site returns to where it started.

Does it cost less than outline permission?

Usually at the first stage, because the authority can only consider three matters and cannot require the survey work an outline application often attracts. The fee is charged per 0.1 hectare, so a large site with few dwellings can cost more than expected. Technical details consent is charged like a full application.

Can I get permission in principle without applying?

Yes, where the local authority enters the site on Part 2 of its brownfield land register, which grants permission in principle automatically. Ask the council whether your site could be entered before paying an application fee, because entry costs the landowner nothing.

Sources and further reading

permission in principletechnical details consentself buildbrownfield registerplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary6 min read

Prior approval: the application that is not quite one

The permission already exists. A prior approval application only determines the matters the class lists, which is both the attraction of the route and its main trap.

Read article →
Glossary6 min read

Planning obligation: when a contribution may be required

Regulation 122 sets three statutory tests for any planning obligation. The most useful question in a contributions negotiation is which limb a given ask satisfies.

Read article →
Glossary7 min read

Section 73 application: varying a condition in practice

Section 73 lets you vary conditions on a permission you already hold, but it cannot touch the description of development and it will not buy you more time.

Read article →
Glossary7 min read

Certificate of lawfulness for a proposed use or operation

Section 192 asks whether a proposed use or operation would be lawful, not whether it would be acceptable. The authority has no discretion to refuse on the merits, and the onus of proof is on the applicant.

Read article →
Glossary7 min read

Stop notice and the compensation risk it carries

Section 183 allows a stop notice only where an enforcement notice has been issued. Section 186 then pays compensation if that notice is quashed on any ground other than the planning merits.

Read article →
Glossary7 min read

Enforcement notice: what it must specify to be effective

Section 173 of the Town and Country Planning Act 1990 fixes what an enforcement notice must say. Where the drafting fails, the notice may be a nullity rather than merely invalid, and that changes what you do next.

Read article →