Residential Scale Thresholds

Phasing a scheme without triggering a higher threshold

7 min readBy PlanScope Editorial Team

Splitting a scheme into phases rarely avoids an obligation, because connected phases are assessed cumulatively. Where phasing does help is CIL timing and section 106 triggers.

Splitting a scheme into phases to stay under a threshold works for programme and cash flow and almost never works as a way of avoiding an obligation. Phased application thresholds are assessed on the development as a whole where the phases are functionally connected, so a 14-unit site submitted as two applications of seven is usually still a major application, still crosses the affordable housing threshold, and still gets screened for environmental impact as one project.

That does not make phasing pointless. It means the reason for phasing has to be real, and the description of development has to be written so that each phase stands up on its own terms.

Why phasing looks attractive and often fails

The thresholds are close together and the step changes are expensive. Ten dwellings turns a minor application into a major one, with a 13-week determination period, a higher fee, statutory publicity and, in most authorities, an affordable housing requirement. Fifty units brings a Statement of Community Involvement and a Transport Assessment into scope in many local validation lists.

So the temptation is obvious. Submit nine now, nine more next year.

Authorities see this pattern constantly and the response is procedural rather than adversarial. The case officer looks at the red line, the ownership, the access arrangement and the timing, and asks whether the second application is a separate project or the second half of one. If it is the second half, the assessment follows the whole.

How authorities assess cumulative effect

There is no statutory bar on selling or developing land in parcels. What the system does instead is treat the effects cumulatively.

Three questions decide it in practice. Do the parcels share an access, a drainage strategy or an open space provision that only works if both are built? Is the land in the same ownership or subject to an option held by the same party? Was the second parcel identified in the first application's supporting documents, for example on an illustrative masterplan or in a phasing note?

Answer yes to two of those and the authority will assess the parcels together. The consequence is not usually refusal. It is that the affordable housing, the play space, the education contribution and the transport work are calculated on the total.

An honest phasing plan submitted up front tends to get a better reception than a second application that arrives six months later with a straight face.

Screening under the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 is where splitting carries the sharpest risk. Schedule 2, paragraph 10(b) covers urban development projects, with screening thresholds including development of more than 150 dwellings and an overall development area of more than 5 hectares.

Schedule 3 of the same Regulations requires the screening authority to consider the cumulation of the proposal with other existing or approved development. The courts have held that where two proposals are functionally interdependent, they must be screened as a single project rather than separately.

A negative screening opinion obtained on a deliberately narrow description is fragile. If the second phase comes forward and the true scale becomes clear, the earlier opinion can be revisited, and a permission granted without a required environmental statement is vulnerable to challenge. An Environmental Impact Assessment environmental statement must be prepared by competent experts under the 2017 Regulations, so a draft is a starting point for that team rather than a substitute for it.

Request a screening opinion on the whole landholding if you intend to bring forward more than one parcel. A negative opinion on the full extent is worth more than two narrow ones.

Infrastructure obligations across phases

Section 106 obligations and the Community Infrastructure Levy behave differently across phases, and this is where phasing does real work.

CIL is charged on chargeable development when it starts. A permission that is expressly phased is treated as a series of separate chargeable developments, so the levy falls due phase by phase rather than in one payment on the first spade in the ground. Outline permissions are phased by definition where phases are set out. Full permissions need the phasing to be written into the permission itself, which means drawing it into the description and the approved plans rather than bolting it on later.

Section 106 obligations can be drafted with phase triggers in the same way: affordable housing delivered pro rata per phase, contributions paid on occupation of a stated number of units within each phase, highway works tied to the phase they serve.

Mechanism Phasing effect What to do at application
CIL Payable per phase where the permission is expressly phased Define phases in the description and on a phasing plan
Section 106 Triggers can be set per phase Draft heads of terms with phase-based triggers
Affordable housing Calculated on the scheme as a whole where phases are connected Set out the total and the per-phase delivery
Conditions Conditions to be discharged before works start can be phase-specific Ask for "phase" wording at the draft condition stage

Get the phase boundaries onto a plan and referenced in the description of development. Retrofitting phasing onto an unphased full permission normally needs a section 73 application.

Where phasing is legitimate and accepted

Phasing is accepted, and often welcomed, where it reflects something real about the site or the delivery.

Ground conditions or remediation that only allow part of the site to be worked at once. A land assembly where one parcel has an unresolved title issue. A drainage outfall that cannot be built until an adjoining scheme completes. Flood risk sequencing that puts the lower-risk parcel first. A self-build or custom-build element delivered on a different timescale. An employment parcel whose occupier is not yet identified.

In each case the phasing has a cause outside the threshold. Say so, in the Planning Statement, in one paragraph, with the evidence behind it.

Evidence that a phase stands alone

Where you want a parcel treated as its own project, the file has to show independence rather than assert it.

  1. A red line that includes its own access from the public highway, not a spur off the other parcel's estate road.
  2. A drainage strategy with its own outfall and attenuation, not shared storage.
  3. Open space, parking and refuse provision sized for that parcel alone and deliverable on it.
  4. Different ownership, or a genuine arms-length disposal with dates.
  5. No reference to the adjoining land in the masterplan, the illustrative layout or the supporting statements.
  6. A Transport Assessment or statement whose trip generation is calculated for that parcel, while still assessing committed development on the adjoining land as part of the baseline.

Point five catches people out. An illustrative masterplan showing the wider site is helpful for placemaking and fatal to an argument that the parcels are unrelated.

Drafting the description of development

The description is the boundary of the permission and it is where phasing is won or lost. Write it to say what is being permitted, in how many phases, and what is reserved.

"Erection of 24 dwellings in two phases (Phase 1: 12 dwellings; Phase 2: 12 dwellings) with associated access, parking and landscaping, in accordance with the phasing plan" tells the authority, the CIL officer and the section 106 solicitor the same thing. A description that says only "erection of 24 dwellings" does not.

Where the total crosses the affordable housing threshold, an Affordable Housing Statement that sets out delivery per phase is better received than one that argues the threshold is not engaged. Our note on planning fees and thresholds on a growing scheme covers the fee consequences, and splitting a site below a planning threshold deals with the separate question of selling parcels to different parties.

This is general guidance, not legal advice, so check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can I submit two applications of nine units instead of one of eighteen?

You can submit them, but if the parcels share an access, drainage or ownership the authority will assess them cumulatively. That means major application procedure, the affordable housing threshold engaged on the total, and a screening opinion taken on both together. The split usually costs time without avoiding anything.

What is salami slicing in planning?

It is the practice of breaking a larger project into smaller applications so that each falls below a threshold, most often an environmental impact assessment threshold. Screening under the 2017 Regulations requires cumulation with other existing or approved development to be considered, and the courts have required functionally interdependent projects to be screened as one.

Does phasing help with the Community Infrastructure Levy?

Yes. Where a permission is expressly phased, each phase is a separate chargeable development, so the levy falls due as each phase starts rather than all at once. Outline permissions are phased by definition where phases are identified. A full permission needs the phasing written into the description and the approved plans.

Can I add phasing to a permission after it is granted?

Normally only through a section 73 application to vary the relevant condition, or a fresh application. Section 96A non-material amendments are rarely suitable because changing the phasing changes how CIL and section 106 triggers operate. Defining the phases in the original description costs almost nothing by comparison.

Will an illustrative masterplan of the wider site harm my case?

It can. If the supporting documents show adjoining land as part of a wider vision, that is strong evidence the parcels are one project. Where you want a parcel assessed on its own, keep the submission to that parcel and assess the adjoining land only as committed development in the baseline.

Sources and further reading

thresholdsphasingeiacilsection 106major development

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Residential Scale Thresholds

View all →
Residential Scale Thresholds6 min read

When a scheme needs environmental impact screening

More than 150 dwellings or more than five hectares puts a scheme into Schedule 2 of the EIA Regulations 2017. Crossing a threshold does not mean an environmental statement is needed, but it does make screening unavoidable.

Read article →
Residential Scale Thresholds7 min read

What changes for a scheme of one new dwelling

One new house is not a householder application. Net gain exemptions, the levy start notice and foul drainage evidence are where single plot schemes go wrong.

Read article →
Residential Scale Thresholds7 min read

What changes when a scheme includes affordable housing

Crossing the major development threshold brings a percentage requirement, a tenure mix to agree with a registered provider, and a section 106 agreement that has to be enforceable years later.

Read article →
Residential Scale Thresholds7 min read

What changes when a site crosses into a flood zone

A site that straddles a flood zone boundary is judged on where you build, not on a single classification. Here is how the sequential approach, levels and access work.

Read article →
Residential Scale Thresholds7 min read

What changes at eighteen metres in height

Eighteen metres or seven storeys pulls in Planning Gateway One, the higher-risk building regime and three Building Regulations changes. Here is how the tests are measured and what each one costs the plan.

Read article →
Residential Scale Thresholds7 min read

What changes at two thousand five hundred square metres

Two thousand five hundred square metres is the national default threshold for retail impact assessment outside a town centre, and the figure most highway authorities use for a Transport Assessment. The sequential test has no threshold at all.

Read article →