Planning appeal or statutory challenge in the High Court

7 min readBy PlanScope Editorial Team

An appeal to the Planning Inspectorate reconsiders the merits of a proposal. A statutory challenge under section 288 tests whether the decision was lawful, within six weeks. The two routes solve different problems.

An appeal and a statutory challenge answer different questions. An appeal to the Planning Inspectorate re-decides the planning merits: a different decision maker looks at the same proposal and reaches their own view. A statutory challenge under section 288 of the Town and Country Planning Act 1990 asks the High Court a much narrower question, which is whether the decision was made lawfully. The court cannot substitute its own planning judgement, and the application has to be filed within six weeks.

That six weeks is the point most people miss. By the time a neighbour has read the decision letter, taken advice and thought about it, a third of the period has usually gone.

What an appeal reconsiders

A section 78 appeal is available where a council refuses permission, grants it with conditions the applicant objects to, or fails to determine the application within the statutory period. The inspector redetermines the application from scratch, applying the development plan and any other material considerations as they stand on the day of the decision. New evidence can be submitted, though late material risks being refused or attracting a costs award.

Only the applicant can appeal. This surprises objectors more than anything else in the system. If a council grants permission and a neighbour thinks it was wrong to do so, there is no appeal route at all, and the only way to challenge it is judicial review in the Planning Court.

Three procedures exist. Written representations handle most appeals and run on paper with a site visit. A hearing is a round-table discussion led by the inspector. An inquiry involves advocates and cross-examination, and is reserved for large or legally complicated schemes. The Inspectorate decides the procedure, taking the parties' preferences into account.

Deadlines depend on what was appealed:

Appeal type Time limit from the decision notice
Householder application 12 weeks
Minor commercial application 12 weeks
Most other refusals and conditions 6 months
Non-determination 6 months from the end of the determination period
Enforcement notice Before the notice takes effect
Listed building consent 6 months

Check the current figures on the Inspectorate's own guidance before relying on them, because procedural time limits have been changed more than once.

What a statutory challenge can and cannot address

Section 288 applies to decisions of the Secretary of State and, in practice, to inspectors' decisions on appeals. The ground is that the decision was not within the powers of the Act, or that a procedural requirement was not complied with and the applicant has been substantially prejudiced. In plain language, an error of law.

The errors that succeed tend to fall into a short list. Misinterpreting a development plan policy, because the meaning of a policy is a question of law even though its application is a matter of judgement. Failing to have regard to an obviously material consideration. Giving reasons so inadequate that the loser cannot tell why they lost. Breaching a statutory duty, such as the duty in section 66 of the Planning (Listed Buildings and Conservation Areas) Act 1990 to have special regard to the desirability of preserving a listed building and its setting, or the duty in section 38(6) of the Planning and Compulsory Purchase Act 2004 to determine in accordance with the plan unless material considerations indicate otherwise.

What a challenge cannot do is reopen the planning balance. Disagreeing with the weight an inspector gave to harm, or to housing need, is not an error of law. Courts say this repeatedly and claimants keep trying it.

Section 289 covers challenges to enforcement appeal decisions and works slightly differently, with permission required and a shorter practical window. Judicial review under Part 54 of the Civil Procedure Rules is the route for challenging a council's own grant of permission, its screening opinion, or its decision on a prior approval.

Who can use each route

Appeal rights belong to the applicant or the appellant on an enforcement notice. Nobody else, including a parish council that objected throughout, can appeal.

A section 288 application can be made by a person aggrieved. The courts read that fairly generously, and an objector who took part in the appeal by making written representations or appearing at an inquiry will normally qualify. Someone who never engaged at all may struggle. Judicial review uses a different test, sufficient interest in the matter, which a local resident or a constituted local group can usually satisfy.

Permission, deadlines and costs risk

Since the Criminal Justice and Courts Act 2015, a section 288 application needs the permission of the High Court before it proceeds. A judge reads the papers and decides whether the grounds are arguable. Refusal at that stage can be renewed at an oral hearing, and many claims stop here.

The time limits are unforgiving:

  1. Section 288: six weeks beginning with the date the decision is taken.
  2. Judicial review in planning: six weeks under CPR 54.5(5), which is shorter than the general three-month rule.
  3. Section 289: six weeks, with permission required.

Courts have very limited power to extend these. Being on holiday, waiting for legal aid or struggling to instruct counsel will not rescue a late claim.

Costs are the other deterrent. In an ordinary claim the loser pays the winner's costs, which on a planning challenge involving a developer as an interested party can be serious money. Claims that qualify as Aarhus Convention claims, meaning environmental claims within the scope of the Convention, attract a capped costs liability set out in the Civil Procedure Rules. The caps are reviewed periodically, so check the current figures rather than a number quoted in an older article.

What each route can actually deliver

An appeal can grant permission. The inspector can allow the appeal, impose their own conditions, vary the ones the council imposed, or dismiss it. The outcome is a decision on the development.

A successful statutory challenge produces something less satisfying. The court quashes the decision and sends it back to be redetermined, usually by a different inspector. The scheme is not approved and it is not refused: it simply goes round again, correctly this time. The same result can follow even where everyone suspects the second decision will land in the same place, because the court is policing the process rather than the outcome.

That difference shapes strategy. If the complaint is that the decision was wrong on the merits, the challenge route will not help. If the complaint is that the decision maker never grappled with a point that mattered, it might.

Working out which route fits

Start with who you are. If you are the applicant facing a refusal, the appeal is almost always the first move, and it is worth considering whether a revised application or a section 73 application to vary a condition would be quicker than an appeal. The comparison of discharging conditions and amending a permission sets out when the section 73 route is available.

If you are an objector facing a grant, there is no appeal. Judicial review is the only route, the clock is six weeks, and the first task is to obtain the officer report and the decision notice and identify a legal flaw in them.

If you are the applicant who has lost an appeal, read the decision letter for what the inspector did with your main evidence. A letter that recites your argument and then explains why it carried little weight is a merits decision and is hard to touch. A letter that never mentions the argument at all is a different matter.

Where lawfulness of existing use is the underlying question rather than the merits of a new proposal, a certificate application may sidestep the argument entirely, and the comparison of a lawful development certificate and planning permission explains when that works.

Whichever route applies, the evidence base is what carries it. Enter your postcode on PlanScope to see which reports a site is likely to need, or browse the full list of report types to work out what an appeal statement should be supported by.

This is general guidance, not legal advice. Anyone considering a challenge in the High Court should take advice from a solicitor or counsel experienced in planning before the deadline runs. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can a neighbour appeal against a planning permission?

No. Appeal rights under section 78 belong to the applicant alone. A neighbour or parish council that objects to a permission has no appeal route and must bring judicial review in the Planning Court instead, within six weeks of the decision. That claim has to identify an error of law rather than argue the council reached the wrong planning judgement.

How long do I have to challenge an inspector's appeal decision?

Six weeks beginning with the date the decision is taken, under section 288 of the Town and Country Planning Act 1990. Permission from the High Court is needed before the claim proceeds. The courts have very little scope to extend the period, so instruct a solicitor as soon as the decision letter arrives rather than after taking soundings.

What counts as an error of law in a planning decision?

Misinterpreting the wording of a development plan policy, failing to take account of an obviously material consideration, giving reasons that leave the loser unable to tell why they lost, acting irrationally, or breaching a statutory duty such as section 66 of the Listed Buildings Act. Disagreeing with the weight given to a factor is not an error of law.

If a challenge succeeds, does the scheme get refused?

No. The court quashes the decision and remits it for redetermination, normally by a different inspector. The application is then decided again with the legal error corrected. The second decision can reach the same conclusion, because the court is checking the lawfulness of the process rather than choosing the planning outcome.

What is a householder appeal deadline compared with a full application?

Householder and minor commercial appeals must be lodged within 12 weeks of the decision notice, using the fast-track written representations procedure. Most other refusals and condition appeals carry a six month limit. Enforcement notice appeals must be made before the notice takes effect. Check the Planning Inspectorate's current guidance, as these periods have changed.

Sources and further reading

appealsjudicial reviewsection 288planning inspectorateplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →
Comparisons7 min read

Building notice or full plans application to building control

Two routes to building control approval under the Building Regulations 2010. What each involves, where a building notice is unavailable, and how completion certificates and regularisation work.

Read article →
Comparisons8 min read

Dropped kerb approval or permission for a front hardstanding

The crossover is licensed under the Highways Act 1980. The driveway behind it is permitted development only if it is porous or drains inside your boundary. Most people need both approvals.

Read article →
Comparisons7 min read

Strategic Environmental Assessment or Sustainability Appraisal

A local plan appraisal discharges two duties at once: strategic environmental assessment under the 2004 Regulations and sustainability appraisal under section 19(5). Only one has sharp legal teeth.

Read article →
Comparisons7 min read

Environmental permit or planning permission for a waste use

The Environment Agency permits the operation. The waste planning authority decides whether the use belongs there. Both are needed, and a registered exemption is not a planning permission.

Read article →