Templates, Checklists and Examples

Checklist: pre-application pack for a minor residential scheme

7 min readBy PlanScope Editorial Team

A pre-application pack for a small residential scheme should be thin. The value sits in a numbered list of questions, not in drawings you will have to redo.

A pre application pack checklist for a minor residential scheme should be thin, and most of the value is in the questions rather than the drawings. Send a location plan, a short written case, indicative layouts and a numbered list of questions the officer can answer in a letter. Send a full set of technical reports and you have spent consultant money to be told which consultant reports you need.

Pre-application advice is a discretionary charged service. It is not binding on the authority, and the officer will say so in the response. It is still the least costly way to find out which of your assumptions about the site are wrong.

Site location plan and red line

An Ordnance Survey based location plan at 1:1250 or 1:2500, with a north arrow, a scale bar and the application site edged in red. Any other land in the same ownership or control, including access strips, garden land and a field behind, edged in blue.

Get the red line right at pre-application stage even though nothing is being validated. The red line defines what the officer is advising on, and a red line that omits the access or the visibility splays produces advice that does not cover the scheme you intend to build. Where ownership is split, say so in the covering note and identify who owns what, because that affects both the certificates on a later application and any highway works.

Description and quantum

One paragraph, then a short table of numbers. The officer needs the site area in hectares, the number of dwellings, the mix by number of bedrooms, gross internal floorspace, the parking count, the access arrangement and the density in dwellings per hectare.

Give the existing use as well, with its use class and how long it has been in that use. On a plot that was part of a garden, or a former yard, or a building that has stood empty, the lawful use is the first thing the officer will want settled, and the answer changes both policy and any levy calculation.

Indicative drawings at the right level

Keep the drawings at sketch quality and say on the sheet that they are indicative.

  • A block plan showing the footprints, parking, bin and cycle storage and the access at 1:200 or 1:500.
  • One indicative street elevation or a sketch section through the site showing the relationship to neighbours.
  • A simple floor area schedule.
  • Two or three annotated photographs of the site and the street, with the viewpoints marked on a plan.

Resist producing detailed elevations, materials palettes and landscape drawings. Advice changes designs, and everything you draw before the advice arrives is at risk. A Design and Access Statement belongs to the application stage rather than the enquiry.

Statement of the planning case

Two to four pages is enough, and a short Planning Statement does the job. Cover the site and its surroundings, the planning history with application references and dates, the designations and constraints affecting the site, the development plan policies you consider relevant by number, and how the scheme responds to them.

If the site has been refused before, say so, give the reference, list the reasons for refusal and explain what has changed. Officers find previous refusals anyway, and an enquiry that conceals one loses credibility from the first paragraph. Where a neighbouring site has been approved on comparable grounds, give that reference too.

The list of questions to ask

This is the part that earns the fee. Number the questions so the officer can answer them in order, and keep each one answerable.

  1. Is the principle of residential development on this site acceptable, and under which policies?
  2. Which local plan, neighbourhood plan and supplementary planning document policies will the determination turn on?
  3. Are the quantum, density, mix and layout acceptable in principle, and what would you change?
  4. Which documents will be required for validation beyond the national list?
  5. Is an ecology survey required, at what level, and in which survey season?
  6. What does the authority expect on biodiversity net gain for a site of this size, and who signs the gain plan?
  7. Is a transport statement needed, and which parking standard applies?
  8. Will the lead local flood authority be consulted, and what surface water information is expected?
  9. Is the community infrastructure levy chargeable here, at what rate, and which exemptions might apply?
  10. Will planning obligations be sought, under which heads of terms, and at what indicative figures from the adopted schedule?
  11. Would this be determined under delegated powers or by committee?
  12. Are there Article 4 directions, tree preservation orders or other designations affecting the site?
  13. Are there any recent appeal decisions in the area you consider relevant?

Three or four of those answers usually change the scheme. Questions 5 and 6 change the programme, because a survey season missed in September costs until the following May.

Constraint evidence to include

Do the free desk checks yourself and attach the outputs. It saves the officer time and it demonstrates that the enquiry is serious.

Check Source
Flood zone The Environment Agency flood map for planning, with the date
Designations and habitats The Defra magic map and the planning data service
Listed buildings and conservation areas The National Heritage List for England and the council's map
Planning history The council's own application search, by address and by reference
Local plan policies The adopted plan and its policies map

Where trees are present, a measured tree position plan is worth having early, because tree constraints move buildings and a root protection area drawn late redesigns the scheme. Where parking is likely to be contested, note whether on-street stress evidence may be needed, following the discipline set out in the guide to writing a parking survey method statement.

Fee band and how to check it

Pre-application charges are set by each authority, published as a schedule on its website, and normally banded by scheme size, so a scheme of one to four dwellings usually sits in a different band from five to nine. The schedules differ in what the fee buys: a written response only, a written response plus a meeting, or a site visit. Some authorities charge separately for a follow-up. Value added tax is often added, and the fee is usually payable in advance.

Check the schedule on the day you submit, because these charges are reviewed annually. The planning application fee is separate and set nationally by regulations, with annual indexation, so confirm the current figure before budgeting either.

For schemes at the larger end of minor, ask whether the authority offers a planning performance agreement. On a nine-dwelling site with a heritage constraint, a written timetable is often worth more than the advice.

What to leave out at this stage

Do not send a biodiversity metric, a viability appraisal, a full arboricultural report or a bat survey unless the site plainly needs one and you already have it. Do not send a drainage design. Do not argue the case aggressively, because the response you want is candid rather than defensive.

And do not ask questions the published documents already answer. An officer who spends the first page of a response telling you to read the validation checklist has less space for the judgement you actually paid for. Browse the 66 report types first, so that question 4 asks about the documents your scheme might realistically need rather than all of them.

Enter your postcode on PlanScope to see which reports your site is likely to need before you book the pre-application meeting.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is pre-application advice binding on the council?

No. It is a discretionary charged service and the response will say that the advice does not bind the authority or prejudice the determination of any later application. It is still worth having, because it identifies which of your assumptions about policy, validation requirements and survey seasons are wrong before you spend money on consultants.

What drawings should a pre-application enquiry include?

A location plan at 1:1250 or 1:2500 with the site edged red, a block plan at 1:200 or 1:500 showing footprints, parking and storage, one indicative street elevation or sketch section, a floor area schedule and a few annotated site photographs with viewpoints marked. Label everything indicative and keep it at sketch quality.

How much does a pre-application enquiry cost?

Each authority sets and publishes its own schedule, normally banded by scheme size, so one to four dwellings usually sits in a different band from five to nine. What the fee buys varies between a written response, a response plus a meeting, and a site visit. Charges are reviewed annually and VAT is often added, so check on the day.

Should I mention a previous refusal?

Yes, with the application reference, the reasons for refusal and an explanation of what has changed. Officers find previous refusals in their own system, and an enquiry that conceals one loses credibility immediately. Where a neighbouring site has been approved on comparable grounds, give that reference too.

What should I leave out of a pre-application pack?

A biodiversity metric, a viability appraisal, a drainage design, a full arboricultural report and a bat survey, unless the site plainly needs one and you already hold it. Also leave out detailed elevations and materials, because advice changes designs. And do not ask questions the published validation checklist already answers.

Sources and further reading

pre-applicationchecklistminor developmentself buildvalidationplanning fees

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →