Noise, Air, Odour and Light

Predicting construction noise under BS 5228

7 min readBy PlanScope Editorial Team

Four inputs drive a BS 5228 construction noise prediction, and on-time percentages are the one most often got wrong. How the calculation and the criteria work.

BS 5228 construction noise prediction is an arithmetic exercise with four inputs: the sound power or reference sound pressure level of each item of plant, the proportion of the working period each item is actually running, the distance and screening between the plant and the receptor, and the duration over which the level is averaged. Get those four right and the prediction is defensible. Get the on-time percentages wrong, which is the usual failure, and the result is either an overstated impact that triggers mitigation nobody needs or an understated one that collapses under scrutiny.

The standard is BS 5228-1, the code of practice for noise control on construction and open sites. Part 2 deals with vibration. Councils cite both in conditions, and the environmental health officer reading your assessment will have the tables open.

What the standard provides

Three things, and they are worth separating.

Reference noise data for plant and activities, measured at a stated distance, which saves you measuring a breaker or an excavator yourself. A calculation method for combining plant items, applying distance attenuation and screening, and converting to an equivalent continuous level over the assessment period. And example methods for judging whether a predicted level amounts to an effect that matters.

The standard does not set statutory limits. Limits come from a condition, from a notice under section 60 of the Control of Pollution Act 1974, or from a prior consent under section 61 of the same Act. The distinction matters because an assessment that says "complies with BS 5228" without naming a criterion has not actually said anything.

Building the plant inventory

Start with the programme, not the plant list. For each phase, work out which items are on site at the same time and for how long within a working day.

For each item record the make and type where known, the reference level and the distance it was measured at, the number of units, and the on-time percentage. On-time is the share of the assessment period during which the item is generating noise at that level. An excavator in a 10-hour day might run 70 per cent of the time. A dump truck loading and hauling might be at the receptor-facing part of the site for 20 per cent. A concrete breaker rarely exceeds 30 per cent on-time because the operator repositions, refuels and waits.

Those percentages are the single biggest driver of the answer, and they are also the input a reviewer will question first. Base them on the contractor's method and say where they came from. A table of plant with every item at 100 per cent on-time tells the officer the assessment was not discussed with anyone who will be on site.

Predicting at the nearest receptor

Work out which receptor is nearest in each phase, and remember that the answer changes as the works move across the site.

The calculation for each item combines the reference level with a distance correction, a screening correction where a hoarding or structure intervenes, and the on-time percentage. Distance attenuation for a point source follows 20 times the logarithm of the distance ratio, so doubling the distance from the source takes off about 6 dB. Items are then combined logarithmically and the total expressed as an LAeq over the period.

An illustrative worked example. A breaker with a reference level of 90 dB LAeq at 10 metres, working at 30 per cent on-time, assessed at a facade 40 metres away with no screening, gives roughly 90 minus 12 dB for the distance, then minus about 5 dB for the on-time correction, so in the order of 73 dB LAeq over the period. Add a tracked excavator and a dumper and the combined figure rises by a few decibels rather than doubling, because logarithmic addition of similar levels adds around 3 dB.

Three refinements change results more than people expect. Facade reflection adds in the order of 3 dB where the receptor plane is modelled. Soft ground attenuation applies over grass and bare soil but not over hardstanding. And a solid barrier of adequate height close to either source or receptor is worth several decibels, with the gain depending on the geometry rather than the material.

Significance criteria and the example methods

BS 5228-1 offers example approaches rather than a single test, and the one councils use most is the category method based on existing ambient levels.

Period Category A Category B Category C
Night, 23:00 to 07:00 45 50 55
Evenings and weekends 55 60 65
Daytime, 07:00 to 19:00 65 70 75

Values are threshold levels in dB LAeq over the relevant period, summarised from the standard's example method. Consult the current edition of BS 5228-1 for the full table, the period definitions and the rules for selecting a category, because the category depends on the measured ambient level at the receptor.

The alternative example method treats a change of 5 dB or more above the existing ambient as the trigger. On a quiet rural receptor the two methods can give different answers, and an assessment that reports both is harder to argue with than one that picks whichever is favourable. Where ambient data is thin, strategic noise mapping gives a starting point, as covered in our note on strategic noise mapping for early site appraisal.

Best practicable means and the mitigation hierarchy

Best practicable means is a statutory concept under the Control of Pollution Act 1974, and it bounds what an authority can require. Reasonableness, local circumstances, the current state of technical knowledge and financial implications all come into it.

In practice the hierarchy runs in this order.

  1. Choose a quieter method: augered piling instead of driven, hydraulic crunching instead of a breaker, off-site fabrication instead of cutting on site.
  2. Site the noisy activity and the compound as far from receptors as the layout allows, and orient loading away from facades.
  3. Screen it, with the hoarding line set close to the source and with no gaps at the base.
  4. Restrict the hours for the noisiest operations rather than the whole site.
  5. Manage it, through plant maintenance, broadband reversing alarms, engine shutdown policies and a named contact for residents.

Price the first three before offering the fourth. Hours restrictions extend the programme, which extends the exposure, and an officer who understands that will accept a shorter, louder phase over a long quiet one in some situations.

Feeding the prediction into a management plan

The prediction is evidence for a document, and the document is what gets conditioned. A Construction Management Plan should carry the predicted levels by phase and receptor, the mitigation assumed in those predictions, the monitoring locations and trigger levels, the complaints procedure and the name of the responsible person.

Set trigger levels slightly below the criterion so there is room to respond before a breach. Say what happens when a trigger is reached: who is told, what stops, and within what period the cause is investigated. Dust and air quality monitoring usually share the same plan and the same receptors, so coordinate them with the Air Quality Assessment rather than running two regimes.

Where the contractor wants certainty, a section 61 prior consent application submitted before works start converts the agreed method and levels into a consent, and protects against a subsequent section 60 notice on the same facts.

Vibration from piling as a separate question

Vibration is not a noise question with different units. It has its own standard, its own metrics and its own receptors, and it belongs in a separate section.

Human response is assessed through vibration dose values under BS 6472-1. Cosmetic and structural damage criteria to buildings come from BS 7385-2 and are expressed as peak particle velocity. The two sets of numbers are orders of magnitude apart, so a level that will annoy a resident is far below one that threatens plaster.

Piling method selection is where most of the mitigation sits, and a pre-works condition survey of neighbouring property protects both sides. Noise assessment of this kind is a job for a suitably qualified acoustician, and councils expect a Noise Impact Assessment to carry an author with relevant competence. A PlanScope draft gives that professional a structured starting point, and professional review is strongly advised before submission.

Enter your postcode on PlanScope to see which environmental documents your site is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

Does BS 5228 set noise limits?

No. It gives reference plant data, a prediction method and example approaches to judging significance. Limits come from a planning condition, a notice under section 60 of the Control of Pollution Act 1974 or a prior consent under section 61. An assessment that claims compliance with BS 5228 without naming a criterion has not stated a limit at all.

What are on-time percentages and why do they matter?

The on-time percentage is the share of the assessment period during which an item of plant is actually generating noise at its reference level. It is the input that moves the predicted level most, and the first thing a reviewer questions. Derive the figures from the contractor's method statement and state their source rather than assuming continuous operation.

What is the ABC or category method?

It is an example significance method in BS 5228-1 that compares the predicted level with threshold values in three categories, selected according to the measured ambient level at the receptor. Thresholds differ for daytime, evenings and weekends, and night. Consult the current edition for the full table, the period definitions and the category selection rules.

How much does acoustic hoarding reduce construction noise?

Several decibels, with the benefit depending on geometry rather than material. A solid barrier works best when placed close to the source or close to the receptor and tall enough to break the line of sight, with no gaps at the base. Treat the figure as a calculated screening correction for your specific layout, not a standard allowance.

Is a section 61 prior consent worth applying for?

Often yes on a constrained urban site. A prior consent under section 61 of the Control of Pollution Act 1974, applied for before works start, converts the agreed method, hours and levels into a consent and protects the contractor against a later section 60 notice on the same facts. It needs the prediction work done early.

Is construction vibration assessed under BS 5228 too?

Vibration sits in BS 5228-2, with human response assessed through vibration dose values under BS 6472-1 and building damage criteria under BS 7385-2 as peak particle velocity. The annoyance and damage thresholds differ by orders of magnitude, so keep vibration in its own section with its own receptors and criteria.

Sources and further reading

construction noisebs 5228noise impact assessmentenvironmental healthdevelopers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Noise, Air, Odour and Light

View all →
Noise, Air, Odour and Light7 min read

Statutory nuisance and why permission is no defence

Part III of the Environmental Protection Act 1990 contains no defence of holding planning permission. How abatement notices work, and what best practicable means requires of an operator.

Read article →
Noise, Air, Odour and Light6 min read

When vibration is assessed in a planning application

Human response and building damage thresholds differ by more than an order of magnitude, so the two assessments need separate sections and separate criteria.

Read article →
Noise, Air, Odour and Light7 min read

Delivery and servicing hours conditions on noise grounds

Delivery noise is short, loud events that a BS 4142 rating level dilutes, which is why authorities restrict hours instead. How to assess the events, mitigate them and negotiate the hours.

Read article →
Noise, Air, Odour and Light7 min read

Part O overheating against closed-window noise mitigation

Approved Document O rules out open windows above 40 dB LAeq at night, while acoustic conditions usually cite BS 8233's 30 dB. That 10 dB gap is where most urban infill sits, and it has to be resolved before submission.

Read article →
Noise, Air, Odour and Light7 min read

Lighting design where bats are present

All UK bat species are European protected species, so a lighting layout on a site with bats is an ecological document first. What the plan must show and how the condition should be worded.

Read article →
Noise, Air, Odour and Light7 min read

Vertical illuminance at a window and the curfew

Vertical illuminance at a neighbouring window decides most light trespass objections, and the limit drops after the curfew hour. How the calculation plane is set, which zone applies and what mitigation moves the figure.

Read article →