Permitted Development

Prior approval applications and EIA screening

6 min readBy PlanScope Editorial Team

A prior approval granted for unscreened Schedule 2 development may be worth nothing. The restriction in article 3, sensitive areas, and how to sequence the two.

Permitted development does not apply to development that requires environmental impact assessment. Article 3 of the GPDO 2015 says so directly, and the consequence is blunt: a prior approval granted for Schedule 1 or Schedule 2 development that was never screened may be worth nothing.

The fix is procedural and costs almost nothing. Request a screening opinion from the local planning authority before submitting the prior approval application, and keep the response on file with the decision notice.

Why the two regimes meet

The General Permitted Development Order grants planning permission by statutory instrument rather than by decision. The EIA Regulations require certain development to be assessed before consent is given. Those two things cannot both happen, so the Order excludes the overlap.

The exclusion applies to the development, not to the application. A prior approval under Part 3 or Part 6 is still a grant of permission for the purposes of the EIA Regulations, and a proposal can be Schedule 2 development even where the prior approval process examines only a short list of matters such as transport, contamination, flooding and noise.

That mismatch is the whole problem. The prior approval officer is looking at five headings. The EIA question is about the effects of the project as a whole.

The restriction the Order places on Schedule 1 and Schedule 2 development

Article 3 of the Order provides that Schedule 2 does not grant permission for development that is Schedule 1 or Schedule 2 development within the meaning of the EIA Regulations, unless one of three things has happened.

  1. The local planning authority has adopted a screening opinion that the development is not EIA development.
  2. The Secretary of State has made a screening direction to the same effect.
  3. The Secretary of State has directed that the development is exempt from the Regulations.

Note what is absent from that list. There is no de minimis, no exception for small sites and no saving for a developer who reasonably believed the proposal fell outside Schedule 2.

Schedule 1 development always requires assessment. Schedule 2 development requires screening where it meets a description in column 1 and exceeds the applicable threshold in column 2, or falls in a sensitive area. The categories that come up most often alongside permitted development are urban development projects, intensive livestock installations, and projects for the use of uncultivated land or semi-natural areas for intensive agriculture.

Part 6 agricultural notifications reach those thresholds more often than people expect, and the practical position is set out in agricultural prior notification on holdings of five hectares.

Obtaining a screening opinion first

The request goes to the local planning authority under the EIA Regulations, with a plan identifying the land, a description of the development, and a description of its likely effects on the environment.

The authority is required to respond within three weeks, extendable by agreement in writing. A screening opinion that the development is not EIA development restores the Order as a route. One that concludes the opposite ends the permitted development route entirely, and the proposal becomes a full application supported by an Environmental Statement.

Write the request properly. A description that understates the project invites a challenge to the opinion later, and an opinion obtained on an incomplete description gives less protection than no opinion at all. Include the whole project, including anything on adjoining land in the same ownership, because cumulation with existing and approved development is one of the selection criteria the authority must consider.

Where the answer is that assessment is required, the Environmental Impact Assessment must be prepared by competent experts under the 2017 Regulations, so an AI-assisted draft is a starting point for that team rather than a substitute for it.

What happens if development starts without screening

The development is unauthorised from the outset. There is no permission to breach, because the Order never granted one.

Practical consequences, in the order they usually bite:

  • An enforcement notice, or a stop notice where the works are under way.
  • A refusal to issue a certificate of lawfulness, closing the route to regularising the position quickly.
  • A funder or purchaser's solicitor finding the gap on due diligence, which on a completed scheme can be worse than enforcement.
  • A judicial review by a third party where the prior approval was granted recently.

Retrospective screening is possible in some circumstances and is not a comfortable position to be in. It also does not repair the period during which the works were unlawful.

Sensitive areas and the removal of thresholds

The definition of a sensitive area in the EIA Regulations covers sites of special scientific interest, National Parks, National Landscapes, the Broads, World Heritage Sites, scheduled monuments and European sites.

Inside a sensitive area, the column 2 thresholds fall away for the purposes of deciding whether a proposal is Schedule 2 development. A scheme far below the ordinary size trigger can require screening simply because of where it sits.

Location Effect on Schedule 2
Ordinary land Description in column 1 plus applicable threshold in column 2
Sensitive area Description in column 1, thresholds disapplied

That matters most for Part 6 agricultural development and for barn conversions in upland and coastal authorities, where a large share of holdings sit within or adjoining a designation. Check the designation before checking the threshold, not afterwards. Conversions in those areas raise their own structural questions, covered in the structural works test in a Class Q barn conversion.

Recording the screening outcome

The screening opinion belongs on the planning register, and the authority will normally place it there. Do not rely on that.

Keep, in the project file and in the sale pack: the screening request as submitted with its plans and description, the authority's opinion with its date and reference, the prior approval application referencing the opinion, and the prior approval decision notice.

Where the description of development changes between the screening request and the prior approval application, request a fresh opinion. A material change to the scheme means the opinion no longer covers what is being built, and that gap is exactly what a purchaser's solicitor will find.

A short Planning Statement accompanying the prior approval, setting out the screening history and confirming that the development matches what was screened, costs little and closes the point on the face of the application.

Programming the two applications together

The sequence that works on a straightforward scheme:

  1. Establish whether the proposal falls within any Schedule 1 or Schedule 2 description, and whether it sits in a sensitive area.
  2. Where either applies, submit the screening request with a full description of the project.
  3. Wait for the opinion, allowing three weeks plus any agreed extension.
  4. Submit the prior approval application, referencing the screening opinion by date and reference.
  5. Keep the whole chain together in the file.

Resist the temptation to run the two in parallel to save a fortnight. A prior approval determined before the screening opinion is adopted sits on an uncertain footing, and the determination period for prior approval is short enough that the authority may decide it before the screening question is resolved.

Where the proposal is clearly outside both schedules, record the reasoning in a file note rather than leaving nothing. A note written now is easier than reconstructing the analysis in three years for a buyer's solicitor.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Enter your postcode on PlanScope to see which documents a prior approval or full application is likely to need.

Frequently asked questions

Can permitted development rights be used for EIA development?

No. Article 3 of the GPDO 2015 provides that Schedule 2 does not grant permission for Schedule 1 or Schedule 2 development within the meaning of the EIA Regulations, unless the authority has adopted a screening opinion that it is not EIA development, the Secretary of State has made a screening direction to that effect, or an exemption direction has been given.

How long does a screening opinion take?

The local planning authority must respond within three weeks of receiving a valid request, extendable by agreement in writing. Submit a plan identifying the land, a description of the development and a description of its likely environmental effects. An incomplete description weakens the opinion and can leave it open to challenge.

What happens if a prior approval was granted without screening?

The development may be unauthorised from the outset, because the Order never granted permission for it. Exposure runs to enforcement action, refusal of a certificate of lawfulness, problems on funding or sale, and judicial review by a third party where the approval is recent. Retrospective screening does not repair the earlier period.

Does a sensitive area change the thresholds?

Yes. In a sensitive area, which includes SSSIs, National Parks, National Landscapes, the Broads, World Heritage Sites, scheduled monuments and European sites, the column 2 thresholds fall away for deciding whether a proposal is Schedule 2 development. A scheme well below the usual size trigger can still need screening.

Which Schedule 2 categories catch permitted development most often?

Urban development projects, intensive livestock installations, and projects for the use of uncultivated land or semi-natural areas for intensive agricultural purposes. Part 6 agricultural notifications and larger Part 3 conversions are the routes where these descriptions are most commonly engaged without anyone checking.

Should I run screening and prior approval at the same time?

No. The prior approval determination period is short, and an approval issued before the screening opinion is adopted sits on an uncertain footing. Obtain the opinion first, then reference it by date and reference in the prior approval application, and keep the whole chain in the project file.

Sources and further reading

prior approvaleia screeninggpdopermitted developmentsensitive areasschedule 2

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Permitted Development

View all →
Permitted Development6 min read

The three year deadline on a prior approval

A planning permission must be begun within three years. A Part 3 prior approval must be completed within three years of the prior approval date, and the condition sits in the Order where nobody can vary it.

Read article →
Permitted Development7 min read

Class M: betting shops and takeaways to homes

Class M turns a small shop, betting office or hot food takeaway into a dwellinghouse through prior approval. The 150 m2 floorspace cap and the 20 March 2013 qualifying use date decide most cases before design begins.

Read article →
Permitted Development8 min read

Class L and moving between C3 and C4 use

Class L permits a dwellinghouse to become a small house in multiple occupation and back again, with no application. The limits are the household test, the six-resident ceiling and the Article 4 directions that withdraw the right.

Read article →
Permitted Development8 min read

Industrial and warehouse extensions under Part 7

Part 7 Class H lets an occupier extend an industrial building or warehouse without an application, within limits that are tighter than they look. This covers the allowance, the boundary condition and the new process restriction.

Read article →
Permitted Development7 min read

Bat roosts and roof works under permitted development

A re-roof or loft conversion needs no planning application, so nothing prompts an ecology check. This sets out when to commission a roost assessment, the survey seasons that control the programme, and who is liable.

Read article →
Permitted Development7 min read

Protected trees and permitted development on the same site

Permitted development grants planning permission for the building work, not consent to touch a protected tree. This covers the consent routes, the root protection trap in foundation design, and how to sequence the two.

Read article →