Prior notification or prior approval: the difference

7 min readBy PlanScope Editorial Team

A Part 6 agricultural notification runs on 28 days and asks whether the council wants a say. Prior approval applications run on 56 days and carry a deemed grant.

Prior notification vs prior approval is a real distinction with real deadlines attached. A prior notification under Part 6 of the GPDO 2015 asks the council one narrow question: does it want to approve the siting, design and external appearance of the building? A prior approval application asks the council to approve specified matters that the Order has already listed, and it runs on a longer clock. Use the wrong form and you lose weeks, or you start work without a permission you thought you had.

The two procedures sit inside the same Order

Both routes live in the Town and Country Planning (General Permitted Development) (England) Order 2015. Both are permitted development, which means the right to build comes from the Order rather than from a grant of planning permission. Neither is a planning application in the ordinary sense, and in neither case is the council weighing up the whole proposal against the development plan.

What differs is the question put to the authority. Under Part 6 you notify, and the council decides whether it wants a say. Under the prior approval classes you apply, and the council must decide whether to approve the matters the Order specifies.

The practical consequence is in the timetable, the fee and the enforcement risk if you move too early.

What a Part 6 agricultural notification asks for

Part 6 covers agricultural and forestry development. Class A applies to agricultural units of 5 hectares or more, Class B to units between 0.4 and 5 hectares, with different limits on each. Larger buildings, new private ways and certain excavations trigger the notification duty.

The application is for a determination as to whether the prior approval of the authority will be required for the siting, design and external appearance of a building, or for the siting and means of construction of a private way. That wording matters. The council cannot use Part 6 to reopen whether the building is reasonably necessary for agriculture, although it can and will test that the development falls within the class at all.

Submit a written description of the proposed development, the materials to be used and a plan showing the site. Then wait. If the council tells you prior approval is not required, you can build in accordance with the details submitted. If it tells you approval is required, you cannot start until you have it.

What a prior approval application asks for

The prior approval classes work the other way round. The Order states which matters the council may consider, and you must apply for approval of those matters before you begin.

Part 6 notification Prior approval classes
What you ask Whether approval is required For approval of listed matters
Who sets the matters The Order, limited to siting, design, external appearance The Order, class by class
Period 28 days 56 days under paragraph W of Part 3, 42 days for the larger home extension scheme, 8 weeks for Part 20 upward extensions
If the council says nothing You may proceed in accordance with the submitted details Deemed grant under paragraph W(11) for Part 3 classes
Neighbour consultation Not part of the procedure Required for several classes

Class MA in Part 3 is the one most readers meet: commercial, business and service use to dwellinghouses. Class Q covers agricultural buildings to dwellings. Part 20 covers new dwellings on top of existing buildings. Each lists its own matters, from transport and highways impacts to flooding, contamination, noise and the external appearance of the building.

Paragraph W of Part 3 is the procedural engine behind those classes. It sets the information to be supplied, the consultation the authority must carry out, the 56 day period and the deemed grant. Read it alongside the class itself rather than on its own, because the class can add requirements.

Determination periods and what silence means

This is where money is won and lost.

Under Part 6, development must not begin before the expiry of 28 days from the date the council received the notification, unless the council has told you in writing that prior approval is not required. Silence for 28 days is permission to proceed in accordance with the details you submitted. Submit vague details and you have a vague right.

Under paragraph W, if the authority does not give you notice of its decision within 56 days beginning with the day the valid application was received, the development is taken to be approved. The deemed grant is genuine, and it is used in practice. It is also fragile, because it depends on the application having been valid on the day it was received. An application missing a required document or the correct fee was never valid, so the 56 days never started.

Keep the proof. Date stamped submission receipt, the fee payment reference, a copy of everything sent. If you are relying on a deemed grant two years later when a buyer's solicitor asks, that file is the whole of your case. The safest confirmation is a lawful development certificate under section 192 of the Town and Country Planning Act 1990, which is the only formal way to establish that works are lawful.

Fees, forms and the drawings people skimp on

Both routes use Planning Portal forms, and both carry a fee set by the national fee regulations. Those fees have been indexed annually since April 2025, so check the current schedule rather than a figure quoted in an old article.

What is submitted differs sharply:

  1. For a Part 6 notification, a description of the development, the materials, and a plan showing the site. Short, but the description binds you.
  2. For a prior approval application, the specific reports the class names. Class MA expects information on transport and highways, contamination, flooding, noise from commercial premises and natural light to all habitable rooms.
  3. For Part 20, structural information and external appearance material that goes well beyond a site plan.

The common error on prior approval is treating the Order's list of matters as a menu. It is the scope of the council's consideration, so every matter listed needs something in the pack addressing it. A planning statement that walks through each matter in the order the class sets them out avoids most invalidity letters.

Starting work before the clock runs out

Begin development early and you are not building under permitted development. You are building without permission.

The right in the Order is conditional on the procedure being followed. Break the condition and the whole of the development is unauthorised, which opens the council to enforcement action and leaves you applying retrospectively with none of the protection the Order gave you. For an agricultural building that is an expensive mistake, because the fallback is a full application where the council can consider landscape impact, access and whether the building is needed at all.

If the deadline is close and the council has not responded, the discipline is to wait out the day and keep the evidence, rather than to take a view in the yard.

Choosing the route for a farm building

Start by asking whether the unit meets the area threshold for Class A or Class B, then whether the building sits inside the dimensional limits of the class, then whether the site is within an excluded area such as a National Landscape or the curtilage of a listed building. Only then does the notification question arise. Many proposals fail at the first or second step and need a full application, and finding that out before the fee is paid saves a cycle.

Where the proposal is a conversion rather than a new building, Class Q and its prior approval route applies instead, with a very different information requirement. The two are often confused because both involve agricultural buildings. They are different classes with different tests, much as an ancillary use and a material change of use are different questions about the same barn.

Checking which supporting documents a given class expects is the part people underestimate. The full list of report types shows what a transport, contamination or noise matter usually needs behind it, and the planning law timeline is where to follow changes to the Order itself.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Enter your postcode on PlanScope to see which reports a Part 6 or prior approval submission on your land is likely to need.

Frequently asked questions

What is the difference between prior notification and prior approval?

A prior notification asks the council to determine whether its prior approval is required for the siting, design and external appearance of a building. A prior approval application asks the council to approve the specific matters the relevant class of the Order lists. The first can end with the council declining to get involved, the second cannot.

How long does the council have to respond to a Part 6 notification?

Development must not begin before 28 days have passed from the date the authority received the notification, unless it tells you in writing sooner that prior approval is not required. If the 28 days expire without a response, you may build in accordance with the details you submitted, so those details need to be precise.

Does a prior approval application get deemed consent if the council misses the deadline?

For Part 3 classes, paragraph W provides that development is taken to be approved if the authority has not notified its decision within 56 days of receiving a valid application. Validity is the weak point, because a missing document or an incorrect fee means the application was never valid and the period never began.

What fee applies to an agricultural prior notification?

A fixed fee set by the national planning fee regulations applies, and prior approval applications have their own charges. Those figures have been indexed annually since April 2025, so take them from the current fee schedule on GOV.UK or the Planning Portal rather than from an older summary.

What happens if I start building before the period expires?

The permitted development right is conditional on the procedure being followed, so starting early means the development is unauthorised in full rather than partly. The council can take enforcement action and your fallback is a full planning application, where it can consider matters the Order would have kept out of scope.

Can a lawful development certificate confirm the position?

Yes, and it is the only formal route. An application under section 192 of the Town and Country Planning Act 1990 for proposed works, or section 191 for existing works, produces a certificate the council has to stand behind. Buyers' solicitors ask for one far more often than people expect.

Sources and further reading

permitted developmentgpdoprior approvalagriculturalpart 6class marural

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons7 min read

Resubmit or appeal after a planning refusal

A fresh application lets you change the scheme and may be fee exempt. An appeal defends the scheme as refused. The refusal reasons tell you which route fits.

Read article →
Comparisons7 min read

Unilateral undertaking against a bilateral section 106 deed

Both instruments are made under section 106 and both bind the land. The difference is that a unilateral undertaking cannot contain any obligation on the authority.

Read article →
Comparisons7 min read

Householder application against a full application

The householder category is defined by what you are proposing, not chosen. It carries a different fee, lighter validation and the 12 week expedited appeal route.

Read article →
Comparisons7 min read

Prior approval against permitted development without it

Schedule 2 to the GPDO 2015 splits permitted development into rights you can simply exercise and rights suspended until prior approval. The difference governs certainty, fees and conditions.

Read article →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →