Wales, Scotland and Northern Ireland

Proposal of Application Notices in Scotland

7 min readBy PlanScope Editorial Team

A statutory precondition with no English equivalent. The 12 week period, the newspaper advert, the community councils and the report that has to evidence it all.

This article is about Scotland. A proposal of application notice Scotland requires for major and national developments is a statutory step, not a courtesy. Under sections 35B and 35C of the Town and Country Planning (Scotland) Act 1997, the notice must be given to the planning authority at least 12 weeks before the planning application is submitted, and the consultation that follows has to be carried out properly or the authority must decline to determine the application.

There is no English equivalent. English pre-application engagement is encouraged and sometimes required by a local validation list, but it is not a statutory precondition to a valid application in the way this is.

When a proposal of application notice is required

The trigger is the development hierarchy. Developments classified as national or major require pre-application consultation, and those categories are defined by regulations that set thresholds by use and by site area, with housing, retail, business, industry, waste, minerals, energy and fish farming each treated separately.

Check the classification before anything else, because the whole programme hangs off it. A scheme sitting just below a threshold is a local development with no statutory consultation requirement. The same scheme with three more units may be major.

Where you are close to the line, ask the authority for its view in writing. Getting this wrong is expensive in a way few planning mistakes are, because the remedy is to start the 12 weeks again.

The 12 week minimum period before submission

The notice is submitted to the planning authority, and 12 weeks must elapse between the notice and the planning application. That is a minimum rather than a target, and on contested schemes it is common for the process to take longer.

The notice itself must describe the development and the site, and set out how the applicant intends to consult the community. The authority then has a short period, 21 days, to respond, and it may specify additional steps beyond the statutory minimum: more events, consultation with particular bodies, a different venue or a wider notification area.

Take that response seriously. A requirement imposed by the authority at this stage becomes part of what your consultation has to deliver, and failing to meet it undermines the report you will have to submit later.

Programme the 12 weeks as a real period of work rather than a waiting period. Design development continues, but the point of the exercise is that the scheme is still capable of changing in response to what people say.

Public events and what they must offer

The statutory minimum is at least one public event in the area, advertised in a local newspaper circulating in the locality at least seven days before it takes place.

The advertisement has to do specific work. It must state where and when the event will be held, give a description of the development, and explain that comments should be made to the applicant rather than to the planning authority at this stage, while making clear that representations to the authority can be made later when the application is submitted.

Run the event so that it can actually change something. That means drawings people can read, staff who can answer questions about traffic and drainage rather than only about architecture, and a comment mechanism that captures what was said. Timed sessions in a village hall at a time working people can attend will do more for the scheme than a glossy exhibition at 2pm on a Tuesday.

Where the authority has required a second event, hold it after the first has been digested, and show what changed in between.

Notifying community councils and elected members

Community councils in the area of the proposed development must be notified. They are the statutory community voice in Scotland and they will comment on the application whether or not you engage with them.

Elected members are a separate matter and not a statutory requirement at this stage, but briefing local councillors before the public event is normal practice and avoids the situation where a member first hears about a scheme from a constituent.

Keep a record of every notification: who, when, by what means, and what was sent. That record goes into the report.

The pre-application consultation report

The application cannot be validated without a report describing the consultation carried out. It is the evidence that the statutory process was followed, and its quality is what the authority assesses.

A workable report contains:

  1. The proposal of application notice and the authority's response to it.
  2. A list of every body and community council notified, with dates and method.
  3. Copies of the newspaper advertisements with their publication dates.
  4. A description of each event, with attendance and the material displayed.
  5. A fair summary of the comments received, including the critical ones.
  6. A clear statement of what changed in the scheme as a result, and what did not change and why.

Point six is the one that separates a report the authority accepts from one it questions. A report recording 40 objections and no change to the scheme is not necessarily wrong, but it has to explain the reasoning rather than simply record the outcome.

This is a close relative of the English statement of community involvement, and the drafting discipline is similar. The statement of community involvement page sets out that structure, though a Scottish report must be written to the Scottish statutory requirements rather than adapted from an English template.

Consequences of getting the process wrong

The sanction is blunt. Where the authority considers that the pre-application consultation requirements have not been complied with, it must decline to determine the application.

That is not a refusal, which could be appealed. It is a refusal to engage with the application at all, and the remedy is to redo the consultation and submit again. On a major scheme that can mean losing a construction season.

The failures that cause it are procedural rather than substantive: an advertisement placed with fewer than the required days before the event, a community council missed off the notification list, an application submitted before the 12 weeks had run, or a report that does not evidence what was done.

An illustrative example: a developer of 120 dwellings submitted a proposal of application notice, received a response requiring two public events rather than one, held both, and submitted a report setting out how the layout had changed to move the vehicular access away from a primary school and how a request to reduce the unit numbers had been considered and declined with reasons. The application was validated without query. This example is illustrative rather than a real case.

Using the process to shape the scheme

Treat the 12 weeks as design time. The consultation surfaces the objections you will face at committee months early, and dealing with two of them before submission is worth more than answering six of them afterwards.

Three questions are worth asking at every event: what do you use this land for now, what would make this scheme acceptable to you, and what are we missing about this place. The third one produces the most useful answers, because local people know about flooding, informal paths and traffic patterns that no desk study will show.

PlanScope's drafting is grounded in English national policy and English local plans, so a Scottish application needs the relevant national framework checked by the reviewer before submission. You can browse the 66 PlanScope report types by category to see what a supporting document set contains, or enter your postcode on PlanScope to see which reports a site is likely to need.

This is general guidance, not legal advice. Check the position with your planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Which developments need a proposal of application notice?

National and major developments as classified by the Scottish development hierarchy regulations, which set thresholds by use class and site area for housing, retail, business, industry, waste, minerals, energy and fish farming. Local developments are outside the requirement. Where a scheme sits close to a threshold, ask the planning authority for its classification view in writing before programming the application.

How long before the application must the notice be given?

At least 12 weeks. Sections 35B and 35C of the Town and Country Planning (Scotland) Act 1997 set that as a minimum period between the proposal of application notice and submission of the planning application. The authority has 21 days to respond to the notice and may require consultation steps beyond the statutory minimum, which then form part of what you have to deliver.

What must the public event advertisement say?

It must appear in a local newspaper circulating in the area at least seven days before the event, describe the development, state where and when the event will be held, and explain that comments should be made to the applicant at this stage. It should also make clear that representations to the planning authority can be made once the application is submitted.

What happens if the consultation is not done properly?

The planning authority must decline to determine the application. That is not a refusal that can be appealed, it is a refusal to engage with the application at all, and the remedy is to carry out the consultation again and resubmit. The failures that cause it are usually procedural: a short advertisement period, a missed community council or an early submission.

Is this the same as an English statement of community involvement?

They are relatives rather than equivalents. The English document reports engagement that is encouraged and sometimes required by a local validation list. The Scottish process is a statutory precondition to a valid application, with prescribed notice, timing and advertisement requirements. A Scottish report should be written to the Scottish requirements, not adapted from an English template.

Sources and further reading

scotlandproposal of application noticepre-application consultationmajor developmentdevolved planning

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Wales, Scotland and Northern Ireland

View all →
Wales, Scotland and Northern Ireland7 min read

Householder permitted development in Northern Ireland

Extensions, outbuildings and dormers in Northern Ireland are governed by the Planning (General Permitted Development) Order (Northern Ireland) 2015, not the England Order. The differences are substantive.

Read article →
Wales, Scotland and Northern Ireland7 min read

The two tier planning system in Northern Ireland

Eleven councils determine most applications and the Department for Infrastructure takes the regionally significant ones. The category decides the consultation, the decision-maker and the appeal route.

Read article →
Wales, Scotland and Northern Ireland7 min read

Notification of planning applications to Scottish Ministers

Notification bites after a Scottish authority has decided to approve, not before. The categories that trigger it, what happens during the pause, and why withdrawing a statutory objection is the whole game.

Read article →
Wales, Scotland and Northern Ireland7 min read

The hierarchy of developments in Scotland explained

In Scotland the development category decides whether you must consult the community twelve weeks before applying, how long determination takes and where an appeal goes. Here is how to work out which category applies.

Read article →
Wales, Scotland and Northern Ireland7 min read

Listed building consent in Scotland: categories A, B and C

Scotland grades listed buildings A, B and C, protects interiors as standard and still requires a separate conservation area consent for demolition. Here is how the consent works and who must be consulted.

Read article →
Wales, Scotland and Northern Ireland7 min read

Local place plans in Scotland and what they change

The Planning (Scotland) Act 2019 gave communities a statutory route to set out proposals for land in their area. Registration matters, and so does the timetable.

Read article →