Public rights of way affected by development

8 min readBy PlanScope Editorial Team

Planning permission does not authorise obstructing a footpath. The definitive map, section 257 orders, objection risk and how long the process really takes.

A public right of way diversion is a separate legal process from the planning permission, and it runs on its own timetable. Planning permission does not authorise you to obstruct a footpath. Building across a recorded route without an order in place is an obstruction of the highway, and the fact that a council granted permission for the building is no defence.

That catches developers regularly, because the order process is often left until the contractor is mobilising. Start it early and it is a manageable piece of work. Start it late and it becomes the critical path item nobody costed.

Finding the routes that affect the site

Three checks, all of which should happen at acquisition rather than at planning.

First, the definitive map and statement held by the surveying authority, which is the county council or the unitary authority. This records public footpaths, bridleways, restricted byways and byways open to all traffic, each with a numbered reference tied to a parish.

Second, the authority's register of pending applications to modify the map. A route not yet recorded but subject to a live application is a real risk, and it will not show on a standard search.

Third, evidence on the ground. Worn paths, stiles, gates, waymarkers and gaps in hedgerows suggest use, and use over a long period can create rights whether or not anything is recorded.

Order the definitive map extract formally rather than relying on an online viewer. Authorities charge a modest fee and the formal extract is the document you will need later.

The definitive map and what it proves

The map is conclusive evidence that the rights it shows exist. It is not conclusive that no other rights exist.

That asymmetry is the whole problem. A site can be clear on the definitive map and still be crossed by a public right of way established through long use and never recorded. The Highways Act 1980 provides for a way to be deemed dedicated where it has been used by the public as of right and without interruption for 20 years, and the question of what interrupts that period is heavily litigated.

Modification of the map is dealt with through applications to the surveying authority, which can add, delete or reclassify a route on the evidence. Those applications take years and can be made by anyone, including a neighbour who objects to your scheme.

There is also a long running question about a cut off date for recording historic rights of way, which has been legislated for, deferred and revisited more than once. Check the current position rather than relying on a figure you remember, because it has moved.

Where a route is unrecorded but claimed, the practical options are to design around it, to negotiate a recorded route in an agreed position, or to resist the claim on the evidence. The third is slow and uncertain.

Diversion under planning legislation

Where a footpath, bridleway or restricted byway crosses a site and has to move to allow development, the usual route is an order under section 257 of the Town and Country Planning Act 1990. The local planning authority may authorise the stopping up or diversion of such a route to enable development authorised by a planning permission.

Two features of that power matter.

It is tied to the permission. The order enables the development that has been permitted, so the permission generally has to be in place or the application under consideration, depending on the authority's practice. Making the order first is not available.

And it is discretionary. The authority has to be satisfied it is necessary to enable the development, and it will consider the effect on users. A diversion that adds a long detour, loses a view, substitutes a surfaced path beside a road for a field route, or funnels walkers between garden fences will attract objections and may not be confirmed.

Highways legislation offers a parallel route through sections 118 and 119 of the Highways Act 1980, used where the reason is not development. The tests are different and a highway authority will usually direct you to the planning route where development is the driver.

For vehicular highways rather than paths, section 247 of the 1990 Act is the equivalent power and is made by the Secretary of State, which adds time.

Stopping up and the order process

The mechanics are similar for diversion and stopping up.

  1. Pre order discussion with the rights of way officer, agreeing the proposed line, width, surface and any structures.
  2. The authority drafts and makes the order, with a plan defining the existing and proposed routes.
  3. Publication: notice in a local newspaper, notices on site at each end of the affected route, and service on prescribed bodies including the parish council and the national user organisations.
  4. An objection period of at least 28 days.
  5. If unopposed, the authority may confirm the order itself.
  6. If opposed and the objections are not withdrawn, the order is referred to the Secretary of State and determined by an inspector through written representations, a hearing or an inquiry.
  7. Certification that the works are complete and the new route is available, before the old route is extinguished.

Step seven is the one people forget. Most orders are drafted so the old route stays open until the new one is built to the specified standard, which means the construction sequence has to allow for it.

The specification in the order binds you. Width, surface, gradients, drainage, gates rather than stiles, and any structures such as bridges or steps all appear in the order schedule, and building something narrower or steeper than the order says leaves the order uncertified.

Timescales and what causes delay

An unopposed order commonly takes several months from first discussion to confirmation, and an opposed one referred to an inspector takes considerably longer, often more than a year including the inquiry or hearing programme.

What drives objections, in rough order of frequency:

  • Increased journey length, particularly where a field path becomes a route alongside a road.
  • Loss of amenity and outlook, where a path is moved between fences or buildings.
  • Poorer surface or a route that becomes muddy or unlit.
  • Severance of a wider network, where the diversion breaks a circular walk.
  • Consultation carried out badly, with local users hearing about it from the site notice.

The last one is the most avoidable. Talking to the parish council, the local access forum and the user organisations before the order is drafted turns several of the others into design comments rather than objections. It costs a couple of meetings.

Budget for the possibility of an inquiry even where you expect none. And do not programme the first occupation on the assumption of an unopposed order.

Temporary closures during construction

Where the route can stay in its position but has to close while works happen nearby, a temporary closure is the tool, made by the highway authority under road traffic regulation powers. It has a maximum duration with provision for extension, and it normally requires a signed alternative route.

Apply early, because these orders have their own notice periods, and expect the authority to ask for evidence that the closure is necessary rather than convenient. The same coordination issues arise as with any street works, as covered in our note on temporary road closures and street works during construction.

Keep the closure honest. A path fenced off for eighteen months under a series of short orders attracts complaints, enforcement interest and objections to your next application in the same area.

The closure arrangements, the signed alternative route and the reinstatement standard should appear in the Construction Management Plan so that the authority can condition them together.

Designing the route in rather than moving it

The cheapest order is the one you do not need.

Where a path crosses the site in a position that can be accommodated, keeping it in place removes the legal process, removes the objections and usually improves the scheme. A route retained through a green corridor, with the housing addressing it rather than backing onto it, is better placed in policy terms and easier to defend.

Where a diversion is unavoidable, design the new route as a piece of the scheme rather than as a residual strip: a sensible width, natural surveillance from the surrounding development, lighting where appropriate, a surface suited to the user group, and a connection to the wider network at both ends. Set it out in the Green Infrastructure Plan alongside the other open space and movement provision, and reference it in the Transport Assessment where the route forms part of the walking and cycling strategy.

Where the route runs through a street rather than across open land, the treatment questions are the ones covered in our note on shared surface streets.

And check the order requirements against the layout before the planning submission, because an order line that conflicts with the approved plots means going back for both.

Browse all 66 PlanScope report types to see which documents your scheme is likely to need.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can I build over a public footpath once I have planning permission?

No. Planning permission does not authorise obstruction of a highway, and a public footpath is a highway. You need a separate order stopping up or diverting the route, and most orders keep the existing route open until the replacement has been built to the specified standard and certified.

What power is used to divert a footpath for development?

Section 257 of the Town and Country Planning Act 1990 allows the local planning authority to authorise stopping up or diversion of a footpath, bridleway or restricted byway to enable development authorised by planning permission. Sections 118 and 119 of the Highways Act 1980 are the parallel powers where development is not the reason.

How long does a diversion order take?

An unopposed order commonly takes several months from first discussion to confirmation. An opposed order is referred to the Secretary of State and determined by an inspector through written representations, a hearing or an inquiry, which often takes more than a year. Do not programme first occupation on the assumption of no objections.

Is the definitive map conclusive?

It is conclusive evidence that the rights shown on it exist, but not that no other rights exist. A site clear on the map can still be crossed by an unrecorded route established through long public use, and applications to modify the map can be made by anyone, including an objector to your scheme.

What makes objectors challenge a diversion?

Increased journey length, particularly where a field path becomes a route alongside a road. Loss of outlook where the path is moved between fences. A poorer or unlit surface. Severance of a circular walk. And consultation done late, so local users first learn of it from the site notice.

Sources and further reading

rights of waydefinitive mapsection 257footpath diversionstopping upconstruction

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking6 min read

Temporary traffic orders for construction works

A construction programme usually needs four separate highway permissions, each under a different power. What each one covers, how long it lasts and what happens when works overrun.

Read article →
Transport, Highways and Parking8 min read

Highway drainage for a new rural access

Highway authorities treat run-off and material transfer onto a rural lane as a safety matter. The design comes down to the levels in the first few metres and the consent position for the roadside ditch.

Read article →
Transport, Highways and Parking7 min read

Car club and travel voucher contributions

The money is simple. The on-street bay needs a traffic regulation order the developer cannot deliver, and the operator may never come forward.

Read article →
Transport, Highways and Parking7 min read

Gated accesses and emergency service override

Three bodies have a view on a gated access: the highway authority, the fire service and the waste service. Design for all three before the driveway is drawn.

Read article →
Transport, Highways and Parking7 min read

Blocking back and queue length at a junction

A capacity ratio tells you how hard an arm is working. Only the queue in metres, compared against measured storage, tells you whether the junction behind will block.

Read article →
Transport, Highways and Parking7 min read

Which design vehicles to test in a swept path analysis

A tracking drawing is only as good as the vehicle chosen. The routine and occasional movements to test, and the parked car case most submissions omit.

Read article →