Raised platforms and floodplain compensatory storage

8 min readBy PlanScope Editorial Team

Raising a site in Flood Zone 3a displaces flood water that has to be replaced band by band. The level for level calculation, the land search, the connectivity tests and how the storage is secured.

Raising a site above flood level does not remove flood risk. It moves water somewhere else. Every cubic metre of floodplain filled by a raised platform is a cubic metre that has to go into the river, onto the road or into a neighbour's garden, which is why floodplain compensatory storage is a condition of almost every consent for development on raised ground in Flood Zone 3a. The test an authority and the Environment Agency will apply is that the scheme causes no net loss of floodplain storage and no increase in flood level or extent off site, and the way you demonstrate it is level for level compensation backed by hydraulic modelling.

Start with where you are. In the functional floodplain, Flood Zone 3b, where water has to flow or be stored in times of flood, most built development is simply the wrong proposal and compensation will not rescue it. Compensatory storage is a Zone 3a conversation. If your site is 3b, the answer is the sequential test and a different site, not a cleverer platform.

Level for level, not merely volume for volume

The distinction is where most schemes come unstuck. Volume for volume means replacing the total volume lost. Level for level means replacing the volume lost within each elevation band, so that storage is available at the same height and therefore at the same moment in the flood event.

Imagine a platform that fills 400 cubic metres of floodplain, of which 300 sits between 12.0 and 12.5 metres above ordnance datum and 100 between 12.5 and 13.0. Dig a hollow that holds 400 cubic metres entirely between 12.5 and 13.0 and you have satisfied volume for volume while making the one in twenty year flood worse, because none of the new storage is available at the levels that fill first. The Environment Agency will object to exactly that arrangement.

Elevation band (m AOD) Storage lost to platform (m³) Compensation required (m³)
12.0 to 12.5 300 300 within the same band
12.5 to 13.0 100 100 within the same band
Total 400 400, band by band

The figures above are illustrative. What they show is the shape of the calculation you need in the Flood Risk Assessment: a table of lost and replaced volume in bands, usually at 100mm or 250mm intervals, referenced to modelled flood levels rather than to ground levels.

Finding land that can hold the water

Compensation land has to be dry now and wet later. That rules out most of the obvious candidates. Land already within the floodplain is already providing storage, so lowering it gains nothing unless you can show it currently sits above the design flood level. Land behind a flood defence is usually excluded, because lowering it creates a void the river cannot reach.

In practice the search narrows to a strip immediately outside the modelled flood extent, at a level just above it, on the same bank and in the same reach. The constraints that then bite:

  • Ownership or control. Compensation outside the application red line needs to be inside the blue line with the appropriate ownership certificate, or secured by agreement, and the authority will want to see the legal mechanism before it grants permission.
  • Contamination and made ground. Excavating into former fill brings a different set of problems, and a land contamination assessment prepared by a suitably qualified person may be needed before you can price the earthworks.
  • Trees, hedgerows and habitats. Lowering ground kills root plates, and the compensation area is often the greenest part of the site.
  • Archaeology. Floodplain terraces are good places to find things, and a desk based assessment may be needed before you commit to a cut volume.
  • Agricultural land quality. Stripping topsoil from best and most versatile land is a planning objection in its own right.

The earthworks balance is worth running early. A 400 cubic metre cut and a 400 cubic metre platform fill rarely balance once you account for unsuitable material, and a scheme that needs 3,000 tonnes imported is a different scheme commercially.

Hydraulic connectivity decides whether any of it works

A compensation area only works if flood water can get in and out freely. The design tests are plain and the Environment Agency applies them consistently:

  1. The area must be hydraulically connected to the watercourse at the levels at which it is intended to fill, with no bund, wall, kerb or high spot between it and the river.
  2. It must drain back to the watercourse by gravity as levels fall, without a pump and without a non return valve that could leave it full.
  3. It must not simply be a hole that fills with groundwater and sits full before the flood arrives, which means checking the groundwater regime rather than assuming it.
  4. Side slopes have to be shallow enough to be stable and maintainable, typically 1 in 3 or flatter, and the resulting plan area is usually larger than clients expect.

Point three catches more schemes than any other. A hollow dug into a high water table holds nothing when it matters. Where groundwater is close to the surface, the honest answer is often that compensation cannot be provided on that site at all, which the article on evidencing groundwater flooding in a flood risk assessment goes into further.

Modelling the compensated case

A statement that the volumes balance is not evidence. What a lead local flood authority and the Environment Agency want is a hydraulic model, baseline and post development, run for the design events and showing the effect on flood levels and extents on third party land.

The model normally has to cover the 1 per cent annual exceedance probability event with the relevant climate change allowance applied, and the 0.1 per cent event as a residual risk check. Climate change allowances are revised, so take the percentage uplift from the current published allowance for your river basin district and management catchment, and state in the report which version you used and when you downloaded it.

Two outputs do the persuading. A difference plot showing change in peak water level between baseline and post development, with a contour at zero and anything positive on third party land explained. And a table of peak levels at named model nodes, before and after, so the reader can see the numbers rather than infer them from a colour ramp.

Where the model shows a small increase on the applicant's own land, that is usually acceptable. Where it shows any increase on land you do not control, expect an objection and plan for a redesign rather than an argument. Hydraulic modelling is specialist work, and councils expect a suitably qualified author, so treat an AI-assisted draft as the framing around the modeller's output rather than a replacement for it.

Keeping the storage available for 100 years

A hollow that someone fills in ten years later has achieved nothing. Expect the authority to secure the compensation through a condition requiring it to be formed before any part of the platform is raised, plus a mechanism that keeps it available for the lifetime of the development.

The usual tools are a planning obligation under section 106 of the Town and Country Planning Act 1990, a restrictive covenant, a management and maintenance plan naming who cuts the grass and clears the outfall, and a plan annexed to the obligation with levels on it. For a residential scheme that will be sold off in plots, the obligation needs to bind successors in title and the management company needs a funded maintenance stream from the start. Ask the question at heads of terms stage, because retrofitting it into a signed agreement is painful.

When compensation cannot be provided

Sometimes the land is not there. On a tight urban brownfield site in Zone 3a, with buildings to three boundaries and a groundwater table a metre down, level for level compensation is not available at any price.

The alternatives, in the order an authority will expect you to have considered them:

  • Avoid the loss. Keep the development footprint at existing ground level and raise only the floor, with a void beneath that remains open to flood water and is excluded from the storage calculation as lost volume only where it is actually obstructed.
  • Build on an undercroft or on piers so the floodplain continues to function beneath the building, with no walls below the design flood level and no enclosed parking that would silt up.
  • Reduce the footprint until the lost volume is small enough to compensate within the site.
  • Rely on the exception test with flood resilient construction and a flood warning and evacuation plan, which needs the Exception Test to be argued properly rather than asserted.

And if none of those work, the scheme is in the wrong place. That is an uncomfortable conclusion to reach at the end of a feasibility study, which is the argument for running a desk based storage check in the first week rather than the twelfth.

Climate change allowances, flood zone mapping and national flood policy all change, so verify each against the current published source before relying on it in a submission. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required. To see which flood and drainage documents a site is likely to need, enter your postcode on PlanScope.

Frequently asked questions

What is the difference between level for level and volume for volume compensation?

Volume for volume replaces the total storage lost. Level for level replaces the volume lost within each elevation band, so new storage is available at the same height and fills at the same point in the flood event. A scheme that balances overall but places all its compensation high up makes smaller, more frequent floods worse, and will be objected to.

Can compensatory storage be provided outside the application site?

Yes, but it has to be in the same reach and on the same bank, hydraulically connected at the right levels, and secured legally. Land outside the red line needs to be shown within the blue line with the correct ownership certificate, or tied in by agreement. Authorities want to see the mechanism before granting permission, not afterwards.

Does compensation work in the functional floodplain?

Generally no. Flood Zone 3b is land where water has to flow or be stored in times of flood, and most built development there is inappropriate regardless of compensation. The right response is the sequential test and a different site. Compensatory storage is a Flood Zone 3a technique for sites that have already passed the sequential and exception tests.

How is the compensation area kept available long term?

Usually through a planning condition requiring it to be formed before the platform is raised, plus a planning obligation under section 106 of the Town and Country Planning Act 1990 that binds successors in title. A management and maintenance plan should name who maintains the area and the outfall, with a plan showing finished levels annexed to the agreement.

What modelling does the Environment Agency expect?

A hydraulic model run for baseline and post development conditions, covering the 1 per cent annual exceedance probability event with the current climate change allowance and the 0.1 per cent event as a residual check. The persuasive outputs are a difference plot of peak water level change and a table of peak levels at named nodes before and after.

What are the options if compensation cannot be provided?

Keep the development footprint at existing ground level and raise only the floor, build over an open undercroft or on piers so the floodplain still functions beneath, shrink the footprint until the lost volume can be replaced on site, or argue the exception test with flood resilient construction and an evacuation plan. If none works, the site is the wrong one.

Sources and further reading

flood riskcompensatory storageflood zone 3ahydraulic modellingenvironment agencyearthworks

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Local resilience forums and flood emergency planning

Flood emergency planning sits with local resilience forums under the Civil Contingencies Act, not with the planning system. Here is how the two meet.

Read article →
Flood, Drainage and SuDS8 min read

Sewerage design standards and sewer adoption approval

Adoptable sewers are designed to the sewerage undertaker's standards, not the council's. Here is what governs the layout, how the application runs and where the programme slips.

Read article →
Flood, Drainage and SuDS6 min read

Flood Re and what buyers will ask about

Homes built on or after 1 January 2009 cannot use Flood Re, so new build insurance rests on the open market. What to hand over at completion and what not to promise.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens and the liability they create

Screens protect a culvert and introduce a new flood risk upstream. How blockage is modelled, which designs degrade gracefully, and who maintains the structure afterwards.

Read article →
Flood, Drainage and SuDS7 min read

Car park change of use and surface water retrofit

An existing impermeable site protects you from a greenfield requirement but not from a betterment expectation. How to evidence the baseline discharge and what the strategy must show.

Read article →
Flood, Drainage and SuDS7 min read

Attenuation under an adopted highway: what is allowed

Highway authorities rarely accept attenuation storage under an adopted carriageway. The reasons, the technical bar where it is considered, and the alternatives that keep storage inside the site.

Read article →