Relocating or adding a bus stop for a development

7 min readBy PlanScope Editorial Team

A new bus stop is rarely a drawing exercise. It is a negotiation with the transport authority and the operator, plus a traffic order that can take longer than the planning application.

If your transport case relies on bus access, the highway authority will want the stop built, accessible and served before the first occupation. That means three separate consents rather than one: the planning permission, a section 278 agreement for the works in the highway, and usually a traffic regulation order for the clearway markings. The order is the item that decides your programme, and it is the one developers discover last.

Start by accepting that you do not choose the location. You propose, fund and build. The transport authority and the operator decide.

When a scheme triggers bus infrastructure

Three situations produce a bus requirement.

The first is distance. Where the walking route from the site to the nearest existing stop exceeds the authority's accessibility standard, usually expressed as a walking distance rather than a straight line, the transport assessment cannot claim the site is served by public transport. Moving or adding a stop closes that gap.

The second is capacity and quality at an existing stop. A development of a few hundred dwellings pushing more passengers onto a flag on a narrow footway will attract a request for a shelter, a raised kerb and real time information.

The third is severance. Where the development changes the road layout, adds a signalised junction or takes footway width, an existing stop may have to move for engineering reasons that have nothing to do with your passenger numbers.

The threshold at which any of this gets asked for follows from trip generation rather than from unit numbers alone, which is the argument set out in transport assessment thresholds and trip generation.

Who owns the stop and who has to agree

Bus stop infrastructure has a fragmented ownership pattern, and working out who holds what saves weeks.

  • The carriageway, footway and kerb belong to the local highway authority
  • The pole and flag usually belong to the local transport authority, which in a two-tier area is the county council
  • The shelter may belong to the district or borough council, a parish council or an advertising contractor under a concession
  • Real time information equipment usually belongs to the transport authority
  • The clearway markings exist because of a traffic order made by the traffic authority
  • The service itself belongs to a commercial operator, or is tendered by the authority

In London, Transport for London holds the stop and the service, with the borough as highway authority for most roads. On a trunk road, National Highways is in the mix as well.

Get a written note of the ownership pattern at pre-application stage. On a site where the shelter is on an advertising concession, the contractor's consent and a revised concession payment can hold the works up long after the engineering is agreed.

Consulting the operator and the transport authority

The operator's view decides whether the stop is worth building. Two questions matter to them: can the vehicle serve the stop without adding running time it cannot recover, and does the stop fit the existing registered route.

Route and timetable changes have to be registered, and the notice periods for varying a local bus service registration mean a routing change is not something an operator can do in a fortnight. A stop on an existing alignment is straightforward. A diversion into a new estate road is a commercial decision that may come with a request for a subsidy.

Ask the operator for three things in writing: confirmation that the proposed stop can be served, any running time implication, and any requirement about turning, gradient or stop spacing. That correspondence goes into the transport assessment as an appendix, and it is the material that persuades a highway officer the bus strategy is real. A Transport Assessment that asserts bus accessibility without it tends to attract a holding objection.

Kerb height, shelter and boarding provision

The stop has to work for a wheelchair user, a pushchair and a passenger with a shopping trolley, and the authority will hold you to its own stop design standard.

The elements that recur in those standards are:

  • a raised kerb to reduce the step into the vehicle, with a profile that lets the driver pull in close
  • a hard-surfaced boarding area clear of street furniture
  • a shelter with a cantilever or perch seat, sited to keep the remaining footway width usable
  • tactile and visual contrast at the boarding point
  • lighting to the authority's standard
  • a pole and flag position that suits where the doors stop, rather than where the drawing looks tidy

Department for Transport guidance in Inclusive Mobility sets the accessibility framework, and the authority's standard sits inside it. Two practical points that get missed: the footway behind a shelter needs enough clear width to remain a usable route, and a stop opposite a side road or a private drive will attract an objection on visibility if the clearway is drawn without checking sight lines.

Where the scheme also reworks the frontage, the accessible parking and cycle provision are judged against the same accessibility standards, and the interaction is covered in accessible and motorcycle parking in a new scheme.

Real time information and its running costs

Hardware is the small part. A display needs a power connection, a data feed, a maintenance regime and a replacement cycle, and the transport authority carries all four for the life of the asset.

So authorities ask for a commuted sum rather than just the equipment, usually covering installation plus a defined number of years of operation and maintenance. Expect that figure to be set from the authority's published contribution schedule where it has one, and to be negotiated where it does not.

Open data has changed one part of this conversation. Operators publish timetable, fare and vehicle location data through the national bus open data arrangements, which means a stop can be usefully served by an app and a printed timetable case rather than a physical display. On a smaller scheme it is worth asking whether a display is proportionate, because a sum for a display on a low-frequency route is hard to justify against the regulation 122 tests.

Securing the works

The usual package has three parts. A section 278 agreement under the Highways Act 1980 covering the design, the works, the inspection fees and the commuted maintenance sum. A planning obligation covering any contribution towards service enhancement, real time information or the traffic order costs. And a negative condition preventing occupation until the stop is available for use.

Each financial element has to satisfy regulation 122 of the Community Infrastructure Levy Regulations 2010: necessary to make the development acceptable, directly related to the development, and fairly and reasonably related in scale and kind. A contribution towards a bus service that would run anyway, or towards a stop a kilometre from the site, fails that test and is worth resisting.

Where the development also commits to bus vouchers, a travel coordinator or monitoring, those measures belong in a Travel Plan with targets and a review mechanism rather than in the section 106 heads of terms as loose promises.

Programme risk from the traffic order

A bus stop clearway needs a traffic regulation order, and the order follows a statutory procedure: consultation with prescribed bodies, public advertisement, a period for objections, consideration of any objections, then making and sealing the order. Where objections are substantial the authority may hold a hearing.

Several months is normal. The order is usually promoted by the authority rather than by the developer, funded by the developer, and sequenced behind the authority's own programme. Two consequences follow. Raise it at pre-application stage, and make sure the occupation condition does not require you to deliver something only the authority can make.

Construction access and temporary stop suspensions are a separate strand again, handled through the street works regime and covered in temporary road closures and street works during construction.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can a planning condition require a bus stop on the public highway?

A condition cannot compel works on land outside the applicant's control, so authorities use a negative condition preventing occupation until the works are complete, alongside a section 278 agreement with the highway authority. Where the works depend on a traffic order that the authority itself must make, the condition needs to be drafted so the applicant is not in breach of something it cannot deliver.

Who decides where a bus stop goes?

The local transport authority, in consultation with the operator and the highway authority where they are different bodies. In London that is Transport for London working with the borough. The developer can propose a location and fund it, but the decision on siting rests with the authority, and an operator that will not serve a stop makes the location academic.

What kerb height allows level boarding?

Department for Transport guidance in Inclusive Mobility recommends a raised kerb at bus stops to reduce the step into the vehicle, and transport authorities publish their own standard within that range. The kerb profile matters as much as the height, because a vehicle needs to pull in close without scuffing. Ask for the authority's stop design standard before drawing anything.

Do I have to pay for the bus service as well as the stop?

Sometimes. Authorities do seek contributions towards service enhancement or a new route where a development would otherwise be poorly served, secured by planning obligation. The obligation has to meet the tests in regulation 122 of the Community Infrastructure Levy Regulations 2010, so it must be necessary, directly related to the development and reasonable in scale and kind.

How long does a traffic regulation order take?

Plan for several months rather than weeks. The procedure requires consultation with prescribed bodies, advertisement, a period for objections and consideration of those objections, with the possibility of a hearing where objections are substantial. Start the conversation with the authority at pre-application stage, because the order is often the longest item on the highway programme.

Sources and further reading

bus stoptransportsection 278traffic regulation ordersection 106

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking6 min read

Temporary traffic orders for construction works

A construction programme usually needs four separate highway permissions, each under a different power. What each one covers, how long it lasts and what happens when works overrun.

Read article →
Transport, Highways and Parking8 min read

Highway drainage for a new rural access

Highway authorities treat run-off and material transfer onto a rural lane as a safety matter. The design comes down to the levels in the first few metres and the consent position for the roadside ditch.

Read article →
Transport, Highways and Parking7 min read

Car club and travel voucher contributions

The money is simple. The on-street bay needs a traffic regulation order the developer cannot deliver, and the operator may never come forward.

Read article →
Transport, Highways and Parking7 min read

Gated accesses and emergency service override

Three bodies have a view on a gated access: the highway authority, the fire service and the waste service. Design for all three before the driveway is drawn.

Read article →
Transport, Highways and Parking7 min read

Blocking back and queue length at a junction

A capacity ratio tells you how hard an arm is working. Only the queue in metres, compared against measured storage, tells you whether the junction behind will block.

Read article →
Transport, Highways and Parking7 min read

Which design vehicles to test in a swept path analysis

A tracking drawing is only as good as the vehicle chosen. The routine and occasional movements to test, and the parked car case most submissions omit.

Read article →