Solar on farm buildings: permitted development limits

7 min readBy PlanScope Editorial Team

Roof and ground mounted renewables on an agricultural unit fall under Part 14, while Part 6 covers agricultural buildings. How the purpose test decides which applies.

Solar on farm buildings permitted development rights sit in Part 14 of Schedule 2 to the General Permitted Development Order 2015, not in Part 6. That distinction catches people out every season. Part 6 is the agricultural rights, and it covers buildings and operations reasonably necessary for agriculture on the holding. Part 14 is the microgeneration rights, and it is Part 14 that lets you put panels on a grain store roof or a turbine in a yard. Confuse the two and you either submit a prior notification that the council cannot determine, or you build something with no lawful cover at all.

The purpose test is where the two parts meet, and it is the test that decides most rural renewables questions.

Which rights cover which installation

Part 14 divides microgeneration by whether the premises are domestic or not, and by whether the equipment sits on a building or stands alone.

Installation Class Broad position
Panels on the roof or wall of a farm building Part 14 Class J Permitted subject to projection, siting and designated land limits
A standalone array in a yard or paddock Part 14 Class K Permitted within tight area and height limits, one installation only
Panels on the farmhouse roof Part 14 Class A Domestic rights, with their own projection limits
A standalone turbine serving the holding Part 14 Class H Domestic standalone wind, with separation and sound limits
A commercial solar farm on agricultural land None Full planning application

Class J has been amended more than once, and the capacity ceiling for rooftop installations on non-domestic buildings has been relaxed since the Order was made. Read the current consolidated text of Part 14 on legislation.gov.uk before you rely on any figure, because secondary guidance and trade summaries lag behind the amendments.

Class K is the one that disappoints people. A standalone non-domestic array is held to a small panel area and a low overall height, and only one standalone installation is permitted within the curtilage. It is a right for a single array powering a building, not a route to a field of panels.

The purpose test and the agricultural use requirement

Part 6 Class A permits agricultural development on a unit of five hectares or more, provided the development is reasonably necessary for the purposes of agriculture within that unit. Part 6 Class B covers smaller units of between 0.4 and five hectares, with tighter limits.

Energy generation is not agriculture. A building erected under Part 6 to house generating plant, or a hardstanding laid under Part 6 for an array, is outside the purpose test and the right does not apply. The same reasoning bites where the output is mostly exported. If the installation primarily serves the grid rather than the holding, the argument that it is reasonably necessary for agriculture becomes very hard to run.

Part 14 does not carry an agricultural purpose test in those terms, which is why it is the right place to look. What Part 14 does carry is a requirement that the equipment is used for microgeneration, together with a condition that it be removed as soon as reasonably practicable when no longer needed for that purpose. That condition travels with the installation and the council can enforce it.

Where you do want a Part 6 building, the familiar limits apply. The ground area covered must not exceed 465 square metres, the height is capped at 12 metres and at 3 metres within three kilometres of an aerodrome, and nothing may sit within 25 metres of the metalled part of a trunk or classified road. Significant Part 6 development needs a prior notification to the council for a determination as to whether its prior approval of siting, design and external appearance is required.

Where a full application starts

The honest line for most farm renewables schemes of any scale is that permitted development will not reach them.

A ground-mounted array beyond the Class K limits, a turbine above the Class H envelope, a battery storage compound, a biomass boiler house or an anaerobic digestion plant all need planning permission. So does a building whose main purpose is to house generating or storage equipment, however agricultural the setting looks.

The threshold questions for a larger scheme are the ones a planning officer will ask in the first meeting. What is the land classified as, because the loss of best and most versatile land weighs against development and an Agricultural Land Classification survey is the way that is answered. What is the landscape designation. Where is the grid connection. And what happens at the end of the operational life.

Panels without a connection are an expensive roof covering. The grid connection is a separate exercise from planning, handled through a connection application to the distribution network operator, and its cost and timescale are frequently the thing that kills a rural scheme.

Two planning points follow. First, the connection infrastructure may need its own consent. Underground cables and substations are often covered by the electricity undertaker rights in the Order, but a new overhead line can require consent under section 37 of the Electricity Act 1989, and a substation compound on a designated site can need permission in its own right. Second, export capacity is not a planning matter, so a permission tells you nothing about whether you can sell the power. Get an indicative connection offer before you commission any planning documents.

Where a scheme is designed around heat rather than power, our note on safeguarding a future heat network connection sets out how to keep the option open at design stage. For combustion plant the air quality position matters more than the planning class, and our piece on biomass boilers in a smoke control area covers the overlap with environmental protection law.

Designated land, listed buildings and Article 4

Part 14 rights are restricted on designated land, meaning conservation areas, National Parks, the Broads, National Landscapes and World Heritage Sites. Restrictions typically bite on the wall or roof slope facing a highway, and on standalone installations visible from a highway. Read the specific class conditions rather than assuming a blanket ban.

Panels on a listed building are a separate matter entirely. Permitted development rights do not remove the need for listed building consent, and fixing an array to the roof of a listed barn will usually require it. Expect the conservation officer to ask about fixings, reversibility, the visibility of cable runs and whether a less visible roof slope would work.

Article 4 directions can remove Part 14 rights in a defined area. Check the council's Article 4 register before you order equipment, because the direction will not be on the deeds.

Glint, glare and the highway

Two technical objections recur on farm arrays, and both are answerable.

Glint and glare matters where an array sits near an aerodrome, a railway or a road on an alignment that puts reflected light into a pilot's or driver's eye. Aerodrome safeguarding consultation is triggered by proximity to a safeguarded airfield, and a glint and glare study using the panel geometry and the sun path is the standard answer. The Civil Aviation Authority publishes the safeguarding framework.

Highway objections are usually about the access rather than the array. A field access that was adequate for a tractor twice a season may not be adequate for construction deliveries, and the highway authority will say so. Deal with the construction phase explicitly, including the swept paths at the junction and any temporary passing bays.

Conditions, aftercare and tying the installation to the holding

Permitted development under Part 14 comes with the removal condition described above. A planning permission for a larger scheme will come with more.

Expect a decommissioning condition requiring removal and restoration within a defined period after generation ceases, a landscape and biodiversity scheme, a construction management plan, a condition fixing the panel height and the layout as approved, and on some sites a requirement to retain agricultural use between and beneath the rows. Where the land is let, make sure the tenancy and the planning obligation do not contradict each other on who removes what.

Councils increasingly ask for an Energy Statement that sets out the generation case against local plan policy rather than a generic benefits list, and for an honest account of how much of the output serves the holding.

PlanScope can draft the planning statement, energy statement and supporting documents for a farm renewables scheme, structured to UK planning policy, with flags where your own yield figures, connection offer and land classification need to go in. Enter your postcode on PlanScope to see which reports a rural site is likely to need. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

This is general guidance, not legal advice. A lawful development certificate is the only formal way to confirm that works are lawful, so check the position with your local planning authority or a qualified professional before relying on permitted development rights.

Frequently asked questions

Can I use Part 6 agricultural rights to build a solar array?

No. Part 6 Class A only permits development reasonably necessary for the purposes of agriculture within the unit, and energy generation is not agriculture. A building to house generating plant, or a hardstanding for an array, falls outside the purpose test. Renewable installations are dealt with under Part 14 of Schedule 2 to the General Permitted Development Order 2015 instead.

How large can a standalone solar array be under permitted development?

Standalone non-domestic arrays under Part 14 Class K are held to a small panel area and a low overall height, and only one standalone installation is permitted within the curtilage. It is a right for a single array serving a building rather than a route to a field of panels. Read the current consolidated text of Part 14 before relying on figures.

Do I need listed building consent for panels on a barn roof?

If the barn is listed, or is a curtilage structure within the listing, then usually yes. Permitted development rights do not remove the need for listed building consent. The conservation officer will ask about fixings, reversibility, cable routes and whether a less visible roof slope could take the array. Raise it before you order equipment.

Does planning permission guarantee I can export the power?

No. Grid connection is handled separately through a connection application to the distribution network operator, and export capacity is not a planning matter. The cost and timescale of a connection offer frequently decide whether a rural scheme proceeds. Get an indicative offer before you commission planning documents rather than afterwards.

What happens to the installation at the end of its life?

Part 14 attaches a condition requiring removal as soon as reasonably practicable once the equipment is no longer needed for microgeneration, and that condition is enforceable. A permission for a larger scheme will carry a decommissioning condition with a defined period for removal and land restoration. Check that the tenancy and the planning obligation agree on who does the work.

Sources and further reading

permitted developmentsolaragriculturalgpdopart 14renewables

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Energy, Sustainability and Carbon

View all →
Energy, Sustainability and Carbon7 min read

Securing fabric performance through planning conditions

Design stage calculations secure a drawing, not a result. How air tightness testing and certification are conditioned, and the wording that is enforceable.

Read article →
Energy, Sustainability and Carbon6 min read

Rooftop solar on commercial buildings and the grid limit

Planning is usually the easy part of a commercial rooftop solar scheme. The Part 14 limits, the safeguarding questions and the connection offer that sets array size.

Read article →
Energy, Sustainability and Carbon7 min read

Showing be lean savings separately in an energy statement

A single combined carbon percentage does not demonstrate compliance. How to separate demand reduction, efficient supply and renewables, and what to tabulate.

Read article →
Energy, Sustainability and Carbon7 min read

Part O routes: simplified method against TM59 modelling

Approved Document O offers a simplified method and a dynamic modelling route. Which designs fit each, where noise forces the issue, and what councils ask to see.

Read article →
Energy, Sustainability and Carbon7 min read

The be seen requirement and post-construction reporting

The be seen stage of the London Plan energy hierarchy requires as-built and in-use energy data after completion. The metering strategy and the ownership of the obligation decide whether it can be met.

Read article →
Energy, Sustainability and Carbon7 min read

Part L 2021 carbon factors and the heat pump sums

Grid electricity fell from 0.519 to around 0.136 kgCO2 per kWh between SAP 2012 and SAP 10.2 while gas barely moved. That one change reversed the compliance arithmetic for heating systems.

Read article →