7 min readBy PlanScope Editorial Team

Two ways to regularise unauthorised development, with sequencing traps in sections 70C and 174(2A). Which route to pick before and after an enforcement notice lands.

If unauthorised work is already on the ground, you have two routes to regularise it, and choosing between a retrospective application vs ground a appeal is a decision with a deadline attached. A retrospective application under section 73A of the Town and Country Planning Act 1990 asks the council to grant permission for what has been built or started. An appeal on ground (a) of section 174 asks the Planning Inspectorate to grant it instead, after an enforcement notice has been issued.

The routes are not interchangeable, and running them in the wrong order can remove one of them altogether.

What each route puts before the decision maker

A section 73A application is an ordinary planning application in everything but tense. It needs the same drawings, the same supporting documents, the same ownership certificates. The council assesses it against the adopted local plan and national policy as it stands now, decides it under its scheme of delegation and issues a decision notice with a right of appeal if refused.

An appeal on ground (a) argues that planning permission ought to be granted for what is alleged in the notice, or that the condition complained of ought to be discharged. Section 177(5) treats the appeal as including a deemed application for permission, so the inspector is deciding a planning application as well as the notice.

That difference shapes the evidence. A section 73A application is read by a case officer who may negotiate amendments. A ground (a) appeal is read by an inspector who will not negotiate and who sees the breach, the council's enforcement case and your planning case at the same time.

Fees and determination periods

A retrospective application carries the normal fee for the category of development. A ground (a) appeal carries no appeal fee, but a fee is payable for the deemed application and the ground falls away if it is not paid. Both figures sit in the fee regulations and are indexed, so check the current schedule rather than relying on a figure from an old quote.

Section 73A application Ground (a) appeal
Who decides Local planning authority Planning Inspectorate, or Secretary of State if recovered
Fee Application fee for the category Deemed application fee, payable or the ground is lost
Target period 8 weeks for minor, 13 weeks for major Typically several months from valid appeal
Negotiation Possible through the case officer None
Further appeal Yes, against refusal No, only statutory review
Risk if it fails Notice may follow Notice is upheld and takes effect

The timing contrast is the practical one. An application has a determination period measured in weeks and can be amended as it goes. An appeal has a fixed deadline on the way in, because an enforcement notice appeal has to be made before the date the notice takes effect, and then runs to the Inspectorate's timetable rather than yours.

Deemed permission on a successful ground (a) appeal

Win on ground (a) and permission is granted for the matters stated in the notice, subject to any conditions the inspector imposes. The notice itself is quashed to that extent. Inspectors routinely grant something narrower than what was built: permission for the structure but not the use, or permission conditioned on reducing a height, replacing a material or restricting hours.

Partial success is common enough that you should plan for it. Decide in advance which elements you can live without, and say so in the statement of case rather than defending everything with equal force.

A deemed permission is a planning permission like any other. It can be varied later under section 73, and the conditions attached to it are enforceable in the ordinary way through a breach of condition notice.

Running both at once and the risks

This is where the sequencing traps sit, and both of them were put there deliberately.

Section 70C of the 1990 Act allows a local planning authority to decline to determine an application for permission for development that is already the subject of an enforcement notice, where the application overlaps with the matters stated in the notice. So once a notice is out, a retrospective application may simply be refused a hearing.

Running the other way, section 174(2A) removes ground (a) where the notice was issued after a related application was made and before the determination period for that application expired. Submitting an application and then receiving a notice inside the eight or thirteen weeks can therefore cost you the merits ground on appeal.

The practical rule is to pick a route and commit to it, early, in writing. Where a notice has already been served, ground (a) is usually the live route. Where nothing has been served and the council is still at the warning letter or planning contravention notice stage, the application route keeps more options open.

Evidence each route needs

Both routes need the same planning case: policy compliance, amenity, highway safety, design, and whatever the specific issue is. The difference is everything around it.

For a section 73A application, expect to supply as-built drawings rather than proposals, a survey of what exists, and a Planning Statement that deals with the fact of the breach without arguing about it. Councils are not supposed to treat the retrospective nature of an application as a reason for refusal in itself, and the statement should keep the assessment on the planning merits.

For a ground (a) appeal, add the notice itself, the schedule of alleged matters, the requirements, and a careful reading of whether the notice describes what is actually there. Where the notice overstates the breach, grounds (b), (c) or (f) may be stronger than (a), and most successful enforcement appeals turn on the drafting of the notice rather than on policy.

Whether a retrospective application goes to committee or is decided under delegated powers also affects the evidence you lead, and the difference between committee determination and a delegated decision is worth checking in the council's scheme of delegation before submission.

Immunity and the time limits

Before choosing either route, check whether enforcement action was open to the council at all. The Levelling-up and Regeneration Act 2023 moved the enforcement time limits in England towards a single ten year period for all breaches, replacing the previous four year rules for operational development and change of use to a single dwellinghouse. Commencement details and transitional arrangements matter here, so verify the current position on legislation.gov.uk before advising, and remember that a lawful development certificate under section 191 is the only formal way to confirm immunity.

Conditions imposed in each

Councils granting retrospective permission tend to impose conditions requiring remedial works within a stated period: a boundary treatment, a landscaping scheme, a surface water detail, restricted hours. Those conditions are negotiable in correspondence before the decision.

Inspectors granting permission on ground (a) impose conditions without discussion. They are drafted from the evidence in front of them, which is a reason to put a suggested list of conditions in your appeal statement. A suggested condition that solves the council's objection is often what turns a dismissal into a split decision.

Choosing a route after a notice is served

Read the notice first, and read it closely. Check the date it takes effect, because that is your appeal deadline and it is not extendable. Check the land it covers, the matters alleged, the steps required and the compliance period.

Then decide. If the notice is accurate and the development is defensible on policy, appeal on ground (a) and pay the deemed application fee. If the notice is inaccurate, lead on the technical grounds and keep (a) in reserve. If no notice exists and the council is open to discussion, a section 73A application with a pre-application conversation behind it is usually faster and costs less.

A draft can set out the policy case and the as-built description in a defensible structure, with missing site facts flagged rather than invented. Browse the PlanScope report types to see what a regularisation case usually needs, or see pricing before you start.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can I apply for permission for work already built?

Yes. Section 73A of the Town and Country Planning Act 1990 allows an application for development already carried out. It is an ordinary application with as-built drawings and the normal fee. The retrospective nature of the application is not itself a reason for refusal, and the council assesses it on current policy.

What is a ground (a) appeal?

It is an appeal against an enforcement notice arguing that planning permission ought to be granted for the matters alleged, or that the condition complained of ought to be discharged. Section 177(5) treats it as including a deemed planning application, so a fee is payable and the inspector decides the planning merits.

Can I run an application and an appeal at the same time?

It is risky. Section 70C lets the council decline to determine an application that overlaps with matters in an enforcement notice already issued. Section 174(2A) removes ground (a) where the notice was issued after a related application and before its determination period expired. Pick one route early.

When is the deadline to appeal an enforcement notice?

The appeal must be made before the date the notice takes effect, which is stated on the notice itself. That deadline is not extendable. If it passes, the notice takes effect and non-compliance becomes a criminal offence, so diarise the effective date as soon as the notice arrives.

Will an inspector grant permission for everything that was built?

Not necessarily. Inspectors frequently grant something narrower, such as the structure but not the use, or permission conditioned on a reduced height, a different material or restricted hours. Decide in advance which elements you can concede and set out suggested conditions in your statement of case.

Is it cheaper to apply or to appeal?

An application carries the fee for the category of development. A ground (a) appeal carries no appeal fee but does carry a fee for the deemed application, and the ground is lost if it is unpaid. Both sit in the fee regulations and are indexed, so check the current schedule.

Sources and further reading

enforcementsection 73aretrospective permissionappealscomparisonssection 174

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons7 min read

Extension of time against a fresh application for a lapsing consent

Time limit conditions cannot be extended by application in England. What counts as a material operation, why condition precedents defeat token starts, and when to reapply instead.

Read article →
Comparisons7 min read

Grampian condition against securing the same thing by obligation

Negative conditions cannot require money, land or rights, and obligations cannot bind a party who will not sign. How to pick the mechanism before the committee report does it for you.

Read article →
Comparisons8 min read

Use class F1 against F2 and which applies to a hall

A hall can sit in F1 or F2 depending on who uses it. The classification decides what you can change without permission, and the bookings diary is the evidence.

Read article →
Comparisons8 min read

Class Q prior approval or a full barn conversion scheme

Class Q converts an agricultural building within defined limits and refusal grounds. A full application frees the design and reopens the countryside policy test.

Read article →
Comparisons8 min read

Judicial review or the statutory planning appeal route

A section 78 appeal asks whether a decision was wrong. Judicial review asks whether it was lawful. Who can use each, and what each can actually deliver.

Read article →
Comparisons7 min read

Resubmit or appeal after a planning refusal

A fresh application lets you change the scheme and may be fee exempt. An appeal defends the scheme as refused. The refusal reasons tell you which route fits.

Read article →