Transport, Highways and Parking

Road safety audit stages and who commissions each one

6 min readBy PlanScope Editorial Team

Stages 1 to 4 of a road safety audit follow the design and construction sequence, and the scheme promoter pays for all of them. The independence rules and the exception report are where the procedure earns its keep.

Road safety audit stages run from Stage 1 at preliminary design through to Stage 4 monitoring after the road has opened, and the scheme promoter commissions every one of them. That last point catches developers out. The audit is not something the highway authority does to you, it is something you pay for, on a brief the authority approves, carried out by a team that must be independent of your own designer.

On the strategic road network the governing document is National Highways standard GG 119. Local highway authorities generally apply their own procedure modelled on it, so the stage numbering and the independence rules will feel familiar wherever your scheme sits.

What each stage covers

The stages follow the design and construction sequence, and each looks at a different question.

Stage When What it examines
Stage 1 Completion of preliminary design Layout, alignment, junction form, whether the scheme concept creates hazards
Stage 2 Completion of detailed design Signing, lining, drainage, lighting, visibility splays, construction detail
Stage 3 Completion of construction, before opening What was actually built, on site, in daylight and after dark
Stage 4 After opening, using collision records Whether the scheme performs as expected in service

Small schemes are often audited as a combined Stage 1 and 2 exercise, which the overseeing organisation has to agree in the brief. That saves a round of fees and about three weeks of programme, and it is worth asking for on a single access or a minor junction improvement.

Stage 3 is the one people forget. It happens on site before the road opens to traffic, and it routinely picks up things the drawings never showed: a sign obscured by a newly planted hedge, a tactile paving layout built the wrong way round, a gully in the wheel track of a cycle lane. Build it into the programme ahead of any adoption certificate.

Stage 4 relies on recorded collision data over 12 and 36 month periods after opening, which is why the note on requesting and using STATS19 collision data matters at this end of the process as well as at the assessment stage.

Who commissions it and who pays

The scheme promoter commissions the audit, and the promoter pays. For a development access built under section 278 of the Highways Act 1980, that is the developer. For an estate road offered for adoption under a section 38 agreement, again the developer, and the audit sits alongside the technical approval process described in the note on section 38 agreements and the road adoption bond.

The overseeing organisation, meaning the highway authority or National Highways, sets or approves the audit brief. The brief defines the scheme extent, the design information to be audited, the accident data to be provided and any departures from standard already agreed. A vague brief produces a vague audit, and an audit that examines the wrong extent has to be redone.

One practical rule: get the brief agreed in writing before the audit team starts. Disputes about scope after a draft report lands are slow and awkward.

Independence rules for the audit team

Independence is the whole value of the exercise. The audit team must have had no involvement in the design of the scheme, and must not be part of the design team for that project. On the strategic road network GG 119 sets out competence requirements for the team leader and the team member, including recorded road safety audit training, current experience of safety audit work and, for the team leader, experience of leading audits.

An observer may attend, commonly someone from the design team or the client, to explain the design intent and to learn. Observers do not contribute to the findings.

Two organisational patterns work. Either the promoter appoints an audit firm directly, or the highway authority nominates one from its own framework and recharges the cost. The second is more common on local authority roads and gives the authority more comfort, at the price of less control over the timetable.

Where a designer has any doubt about whether a past involvement compromises independence, raise it before appointment. An audit later found to be non-independent has no value, and the authority will ask for it again.

The designer's response and exception reports

The audit report sets out problems and recommendations, each tied to a location and a mechanism of harm. It does not redesign the scheme, and a good audit team resists the temptation to.

The designer then produces a formal response to each recommendation, which records acceptance or non-acceptance with reasons. Where a recommendation is not accepted, the project sponsor or overseeing organisation signs an exception report accepting the residual risk. That signature is the point of the whole procedure, because it puts the decision to live with a hazard in front of a named person with authority.

  1. Audit team issues the report to the overseeing organisation and the promoter.
  2. Designer responds to each item, accepting, accepting in part, or rejecting with reasons.
  3. Disagreements are discussed, ideally in a short meeting rather than by email.
  4. Exception reports are prepared for rejected recommendations and signed at the required level.
  5. The audit report, the designer's response and any exception reports are kept together as the scheme record.

Keep that bundle. On adoption, on a bond release, and on any later claim, it is the evidence that the safety implications were considered.

Estate roads and private layouts

Audits are not limited to adoptable highway. Many councils now condition a road safety audit for larger private estate layouts, car park circulation and service yards, particularly where refuse vehicles, deliveries and pedestrians share space.

The useful discipline on private layouts is swept path analysis alongside the audit, because the most common audit findings there are about vehicles that cannot turn without mounting a footway. Construction phase movements raise the same issues, which is why a routing agreement with the authority, covered in the note on construction traffic routing agreements, usually goes hand in hand with the audit programme.

Cost and programme effects

Audit fees are modest against the cost of the works themselves. The programme risk is larger. Each stage needs the design information to be complete enough to audit, then a report period, then a response period, then sign-off. Two to four weeks per stage is a reasonable planning assumption on a straightforward scheme, and longer where the authority uses its own framework and has a queue.

The expensive failure is a Stage 1 audit that arrives after the planning application has been submitted and recommends a different junction form. Commission Stage 1 on the preliminary design you intend to submit, not after.

How findings reach the planning decision

Audits are a highway engineering procedure and sit outside the planning application, so audit reports are not usually validation requirements. They reach the decision indirectly. A highway authority consultee response will refer to audit findings where an audit exists, and conditions commonly require a scheme to be designed and constructed in accordance with a subsequent audit.

The transport evidence that does go into the application is the Transport Assessment or its shorter equivalent, which should describe the access arrangement and state where in the audit sequence the scheme has reached. Officers read that as a sign the highway work has been thought through.

PlanScope drafts the transport documents that accompany an application and does not produce road safety audits, which are commissioned separately from an independent audit team. Reports should be reviewed before submission, and for specialist technical reports qualified professional input may be required.

This is general guidance, not legal advice. Check the position with your local highway authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Who pays for a road safety audit on a development access?

The scheme promoter, which on a development access built under section 278 of the Highways Act 1980 means the developer. The highway authority or National Highways acts as the overseeing organisation, approves the brief and may nominate the audit team from its own framework and recharge the fee. Budget for all stages at the outset rather than stage by stage.

Can my own transport consultant carry out the audit?

Only if that firm and those individuals had no involvement in designing the scheme. The audit team must be independent of the design team, with recorded safety audit training and current experience. Someone from the design team may attend as an observer to explain design intent, without contributing to the findings. Raise any doubt about independence before appointment.

What is an exception report?

It is the formal record of a decision not to act on an audit recommendation. The designer states why the recommendation is not accepted, and the project sponsor or overseeing organisation signs to accept the residual risk at the appropriate level. Keep it with the audit report and the designer's response as part of the permanent scheme record.

Is a road safety audit needed before I submit a planning application?

It is rarely a validation requirement, but a Stage 1 audit on the preliminary design is worth having early. If the audit recommends a different junction form after submission, the access drawings and the transport evidence both have to change. The highway authority consultee response will refer to audit findings where an audit exists.

Do private estate roads need auditing?

Many authorities now condition an audit for larger private layouts, car park circulation and service yards where vehicles and pedestrians share space. Roads offered for adoption under a section 38 agreement are audited as part of technical approval. Pair the audit with swept path analysis, since most findings on private layouts concern vehicles that cannot turn cleanly.

Sources and further reading

road safety audithighwayssection 278transport assessmentdevelopment access

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking7 min read

Mobility hubs and shared transport secured by condition

A condition can require the bays and the power supply. It cannot fund an operator or make a car club viable. How to split the commitment so the scheme survives withdrawal.

Read article →
Transport, Highways and Parking7 min read

Network Rail consultation where a crossing is affected

Where a scheme adds movements across a level crossing, the rail operator's risk assessment governs the outcome rather than highway capacity. What the evidence has to show.

Read article →
Transport, Highways and Parking6 min read

Section 59 claims for extraordinary traffic damage

A section 59 claim arrives after the road has been resurfaced, by which point the only useful evidence is the baseline survey nobody took.

Read article →
Transport, Highways and Parking7 min read

Access onto a single track rural lane

On a single track lane the highway objection is about geometry and conflict rather than flow. What to survey, what to draw and how to make a passing bay offer deliverable.

Read article →
Transport, Highways and Parking7 min read

Committed development and cumulative impact in a TA

Agree the committed development list and the background growth factors with the highway authority before commissioning surveys, because the list usually decides the capacity conclusion.

Read article →
Transport, Highways and Parking7 min read

Pedestrian audits and crossing provision evidence

An audit that produces a located, priced schedule of defects and remedies is evidence. A page of photographs is not. How to choose routes, score them and link findings to mitigation.

Read article →