Safe access and egress: dry routes and alternatives

7 min readBy PlanScope Editorial Team

A dry route is the benchmark for safe access and egress. Where one cannot be provided, the argument moves to hazard rating, refuge and evacuation, and the evidence has to be drawn rather than asserted.

Safe access and egress in flood risk terms means a route that people can use during the design flood event without being exposed to dangerous depths or velocities, and that emergency services can use to reach the site. It is assessed separately from the building itself, and it fails schemes that otherwise pass the sequential and exception tests. A dry route is the benchmark. Where a dry route cannot be provided, the argument moves to hazard rating, and that is where most negotiation happens.

The question a lead local flood authority asks is simple. If the design event happens at three in the morning, can people leave, and can a fire appliance get in.

What the guidance expects of a route

National flood risk guidance requires development to be safe for its lifetime, and access and egress is one limb of that. The assessment should look at the route from the building to a point outside the floodplain, in the design event including the relevant climate change allowance, and it should consider who is using it.

The design event depends on the source. For fluvial flooding it is normally the 1 per cent annual exceedance probability event with a climate change allowance applied; for tidal and coastal flooding it is the 0.5 per cent event with the appropriate allowance. Climate change allowances are revised periodically, so check the current published allowances for your river basin district and epoch rather than copying a figure from an older report.

Three outcomes are possible. A dry route, meaning no flooding along its length in the design event, which is what authorities prefer. A safe but wet route, where shallow slow water is crossed and the hazard rating supports use. Or no acceptable route, where the answer is either a redesign or a refusal.

Depth and velocity hazard ratings

The hazard rating used across England comes from Defra and Environment Agency research, and it combines depth with velocity and a debris factor:

hazard rating = depth × (velocity + 0.5) + debris factor

Depth is in metres, velocity in metres per second, and the debris factor reflects the likelihood of debris in the flow and the vulnerability of the people exposed. The resulting number falls into bands:

Hazard rating Description
Below 0.75 Very low hazard, caution advised
0.75 to 1.25 Danger for some, including children and less mobile people
1.25 to 2.5 Danger for most people
Above 2.5 Danger for all, including emergency services

For a residential scheme, expect the authority to want the route within the lowest band, or to accept the second band only with a good reason and supporting measures. Care homes, schools and anything with a vulnerable occupancy get pushed to the lowest band, because the bands themselves are keyed to mobility.

Velocity is the part people ignore. A 200 mm depth on a flat car park is a different proposition from 200 mm running across a road at 1.5 metres per second, and the rating shows that: the second case lands around 0.9 before any debris allowance.

Dry routes, safe refuge and assisted evacuation

A dry route is not always achievable on an infill site in a historic town, and the guidance does not treat that as automatically fatal. What it does is shift the weight of the argument.

Safe refuge within the building can support the case: sleeping accommodation above the design flood level, a floor area at that level able to hold the occupants, and a means of signalling to rescuers. Refuge works for a block of flats with upper floors. It works poorly for a bungalow, and for single-storey development in Flood Zone 3a many authorities simply refuse.

Assisted evacuation is the weakest argument available. National guidance is clear that the ability to evacuate people is not a substitute for locating development where it is safe, and fire and rescue services do not welcome being written into a developer's flood plan as a design feature. Use it as a residual measure, with a flood warning and evacuation plan, never as the primary answer.

Register the site for flood warnings and say so in the assessment. It costs nothing and it tells the officer you have thought about the operational side.

Routes crossing land you do not control

This one derails applications late. A route shown across the neighbouring supermarket car park is worthless unless you have a right to use it, and a condition cannot create one.

Acceptable routes are those over the public highway, over land within the application site, or over land where a recorded public right of way exists. Anything else needs an easement, and the authority may want it in place before permission rather than as a Grampian condition, because the flood safety case depends on it.

Check the highway extent properly. Adopted highway boundaries rarely match the kerb line, and an access strip that looks public on an aerial photograph is often in private ownership. Order the highway records at the same time as the topographic survey.

Vehicular access for emergency services

Pedestrian and vehicular access are assessed differently, and the second is where local practice varies most. Fire and rescue services want to bring an appliance close enough to work, and the depth at which that becomes impossible is a matter of local judgement rather than a national number.

What helps is asking early. Many authorities have a strategic flood risk assessment that sets local access criteria, and some fire services publish a position on operational access in flood conditions. Where a scheme depends on the answer, put the question to both the lead local flood authority and the fire service at pre-application stage and record the reply in the Flood Risk Assessment.

Where the access serves a basement, the case is harder again, for reasons we set out in basement development and the flood risk objection.

Where an authority will accept a compromise

Patterns emerge from decisions, and it is fair to describe them as indicative rather than as rules.

  • Redevelopment of a previously developed site in a town centre, where the sequential test has been passed on regeneration grounds, attracts more flexibility than a greenfield edge-of-settlement scheme.
  • Upper floor residential over commercial ground floor is easier to defend than ground floor living space, because refuge is built in.
  • A route that is dry for the 3.3 per cent event and shallow in the 1 per cent event is often accepted, particularly where flood warning lead times are long.
  • Fast-responding catchments with short warning times get treated more strictly, because evacuation before onset cannot be relied on.
  • Where the exception test is engaged, access and egress usually appears in the safety limb rather than as a separate matter, which we cover in the two limbs of the exception test.

Groundwater flooding sits outside this framework and needs its own treatment, since depths build slowly and velocities are low but duration is long. Our note on groundwater flooding evidence covers how to assess it.

Evidence and drawings to submit

Officers cannot accept an assertion that access is safe. Give them the working.

  1. A topographic survey with levels to Ordnance Datum along the whole route, not just at the site boundary.
  2. Design flood levels for the relevant events, from Environment Agency modelled data or site-specific modelling, with the source and date stated.
  3. A route plan showing depth at intervals along the route, with the exit point out of the floodplain marked.
  4. A longitudinal section of the route against the design flood level, which is the drawing that persuades.
  5. Hazard rating calculations at the controlling points, with the velocity source and debris factor stated.
  6. Land ownership or highway extent evidence for the route.
  7. A flood warning and evacuation plan where refuge or assisted evacuation forms part of the case.

The longitudinal section is the single most useful drawing and the one most often missing. It takes an afternoon to produce and it answers the officer's question directly.

One honest uncertainty: hazard rating thresholds are applied with judgement, and two neighbouring authorities can reach different conclusions on the same numbers. Where the margin is fine, get the question resolved at pre-application rather than discovering it in a consultation response eight weeks in.

Enter your postcode on PlanScope to see which reports your site is likely to need, including the drainage and flood documents that sit alongside the access case.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What counts as a dry route?

A route from the development to a point outside the floodplain that carries no flood water in the design event, including the applicable climate change allowance. It has to be demonstrated with levels along the whole route, not only at the site boundary, and the exit point out of the floodplain should be marked on the plan.

How is flood hazard to people calculated?

Using the Defra and Environment Agency formula, where hazard rating equals depth multiplied by velocity plus 0.5, with a debris factor added. Ratings below 0.75 are very low hazard, 0.75 to 1.25 is danger for some people, 1.25 to 2.5 is danger for most, and above 2.5 is danger for all.

Can I rely on people evacuating before the flood arrives?

Only as a residual measure. National guidance is clear that the ability to evacuate is not a substitute for siting development where it is safe, and fire and rescue services resist being written into a scheme as a design feature. Fast-responding catchments with short warning times are treated more strictly.

Can my escape route cross a neighbour's land?

Not unless you have a legal right to use it. Routes over the public highway, over land within the site, or over a recorded public right of way are acceptable. Anything else needs an easement, and authorities often want it secured before permission because the safety case depends on it.

What depth can a fire appliance drive through?

There is no single national figure, and it is treated as a matter of local judgement. Some strategic flood risk assessments set local access criteria and some fire services publish an operational position. Where a scheme turns on the answer, ask the lead local flood authority and the fire service at pre-application stage.

Which drawing makes the strongest case?

A longitudinal section of the escape route plotted against the design flood level. It shows at a glance where water crosses the route and how deep it gets. Most refusals on access and egress involve applications that submitted a plan with no section and no levels along the route.

Sources and further reading

flood risksafe accessegresshazard ratingflood risk assessment

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Local resilience forums and flood emergency planning

Flood emergency planning sits with local resilience forums under the Civil Contingencies Act, not with the planning system. Here is how the two meet.

Read article →
Flood, Drainage and SuDS8 min read

Sewerage design standards and sewer adoption approval

Adoptable sewers are designed to the sewerage undertaker's standards, not the council's. Here is what governs the layout, how the application runs and where the programme slips.

Read article →
Flood, Drainage and SuDS6 min read

Flood Re and what buyers will ask about

Homes built on or after 1 January 2009 cannot use Flood Re, so new build insurance rests on the open market. What to hand over at completion and what not to promise.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens and the liability they create

Screens protect a culvert and introduce a new flood risk upstream. How blockage is modelled, which designs degrade gracefully, and who maintains the structure afterwards.

Read article →
Flood, Drainage and SuDS7 min read

Car park change of use and surface water retrofit

An existing impermeable site protects you from a greenfield requirement but not from a betterment expectation. How to evidence the baseline discharge and what the strategy must show.

Read article →
Flood, Drainage and SuDS7 min read

Attenuation under an adopted highway: what is allowed

Highway authorities rarely accept attenuation storage under an adopted carriageway. The reasons, the technical bar where it is considered, and the alternatives that keep storage inside the site.

Read article →