Comparisons

Schedule 1 against Schedule 2 EIA development

6 min readBy PlanScope Editorial Team

Schedule 1 makes assessment mandatory. Schedule 2 thresholds only decide whether the screening duty arises, and in a sensitive area those thresholds fall away entirely.

Schedule 1 development always needs an Environmental Impact Assessment. Schedule 2 development needs one only where the local planning authority, or the Secretary of State, decides it is likely to have effects on the environment of a scale that requires assessment. That is the whole of the schedule 1 vs schedule 2 EIA distinction, and everything else follows from it: the thresholds, the selection criteria, the screening request and the consequences of putting a project in the wrong box.

Schedule 1 is a short list of large projects. Schedule 2 is a much longer list with thresholds in a second column, and it is where almost every contested screening argument happens.

Mandatory assessment against a case by case test

The Schedule 1 list in the EIA Regulations 2017 covers projects whose effects are presumed, by their nature and scale, to require assessment. Crude oil refineries, thermal power stations of 300 megawatts or more, nuclear installations, integrated chemical works, motorways and express roads, long-distance railway lines, airports with a runway of 2,100 metres or more, major waste disposal installations, large dams and reservoirs, long large-diameter pipelines, quarries and open-cast mining over 25 hectares, peat extraction over 150 hectares, wastewater treatment plants serving 150,000 population equivalent, and intensive livestock units above stated bird and pig numbers.

Those figures are thresholds of definition rather than screening thresholds. Meet them and the project is EIA development. There is no discretion and no screening judgement to make.

Schedule 2 works differently. The schedule pairs a description of development with an applicable threshold or criterion, and development meeting the description and exceeding the threshold is Schedule 2 development that must be screened. Screening then asks whether the development is likely to have significant effects on the environment.

Thresholds and how they are applied

The Schedule 2 thresholds do not decide whether assessment is required. They decide whether the screening duty arises at all.

For urban development projects, the applicable thresholds are more than one hectare of urban development that is not dwellinghouse development, more than 150 dwellings, or an overall development area of more than five hectares. Industrial estate development has its own area threshold. Each of the other categories, from agriculture and aquaculture through extractive industry, energy, infrastructure and tourism, carries its own.

There is one important override. Where the development is in a sensitive area, the thresholds fall away and any development within the Schedule 2 description must be screened however small it is. Sensitive areas include sites of special scientific interest, National Parks, National Landscapes, World Heritage Sites, scheduled monuments and European sites.

Schedule 1 Schedule 2
Effect of meeting the description EIA mandatory Screening required
Role of the numbers Definition of the category Trigger for the screening duty
Sensitive area override Not applicable Thresholds disapplied
Typical outcome Environmental statement Often a negative screening opinion

The selection criteria that decide screening

Schedule 3 sets out what the authority must take into account: the characteristics of the development, its location, and the type and characteristics of the potential impact.

Characteristics of development covers size and design, cumulation with other development, use of natural resources, waste production, pollution and nuisances, risk of major accidents and risks to human health. Location covers the existing and approved land use, the abundance and regenerative capacity of natural resources, and the absorption capacity of the natural environment, with particular attention to wetlands, coastal zones, mountain and forest areas, nature reserves, densely populated areas and landscapes of historical importance.

Impact characteristics cover the magnitude and spatial extent of effects, their nature, their transboundary character, their intensity and complexity, their probability, and their expected onset, duration, frequency and reversibility.

Write the screening request against those headings. An officer working through Schedule 3 with your document open in the same order is far more likely to reach a negative opinion than one hunting for the relevant facts.

Cumulative effects and other development

Cumulation is where screening decisions most often come apart. The assessment has to consider the project together with other existing and approved development, and applicants routinely assess their scheme in isolation.

Identify the committed schemes yourself and list them: consented but unbuilt applications nearby, allocations with resolutions to grant, and any live application likely to be determined first. Then say why the combined effect does or does not change the answer.

Splitting a project to keep each part below a threshold does not work. Where the phases are functionally connected, the authority is entitled to screen the project as a whole, and a permission obtained by presenting a fragment of a larger scheme is vulnerable. A similar logic applies to the staged approach to ground investigation described in the note on contamination Phase 1 or Phase 2, where the trigger for the next stage depends on what the first one found.

Sensitive areas and lowered thresholds

The sensitive area rule catches small schemes. A modest development inside a National Park, or a small extraction operation adjoining a site of special scientific interest, can be Schedule 2 development requiring screening when the same proposal elsewhere would not be.

That does not mean an environmental statement follows. Most such screenings end negative, because a small scheme in a sensitive area often has no effect of the scale that triggers assessment. It does mean the screening step has to happen and be documented, and that the validation officer will look for it.

Where a scheme sits near rather than within a sensitive area, the threshold applies as normal but the location feeds into the Schedule 3 judgement. Proximity to a designated site is a location factor, not a trigger.

An illustrative case. A minerals operator proposes a two hectare sand extraction on land immediately adjoining a river site of special scientific interest. Two hectares would be well under the ordinary threshold, but the sensitive area rule means the proposal has to be screened, and the hydrological connection to the river is the factor the officer weighs. The scheme and the figures are illustrative rather than drawn from a real application.

Consequences of getting the category wrong

Granting permission for EIA development without an environmental statement leaves the permission open to challenge, and the courts have quashed permissions on that basis. That risk sits with the developer as much as the authority, because the quashed permission is yours.

The reverse error costs money rather than validity. Preparing an environmental statement for a project that never needed one adds cost and months to a programme, and the chapters rarely persuade anyone of anything the supporting documents would not have covered.

So screen deliberately. Ask for a formal opinion where the answer is arguable, keep the request proportionate where it is not, and record the reasoning either way. Where the answer is positive, remember that an Environmental Impact Assessment must be prepared by competent experts under the 2017 Regulations, and that an AI-assisted draft is a starting point for those experts rather than a replacement for them. Browse the full list of report types to see how the technical chapters map onto individual supporting documents, or enter your postcode on PlanScope to check what a site is likely to need.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the difference between Schedule 1 and Schedule 2?

Schedule 1 of the EIA Regulations 2017 lists projects for which assessment is mandatory, so meeting the description and figures makes the proposal EIA development with no discretion. Schedule 2 lists descriptions with applicable thresholds, and exceeding a threshold triggers a screening duty rather than a requirement to assess. Most Schedule 2 screenings end negative.

What are the urban development thresholds in Schedule 2?

More than one hectare of urban development that is not dwellinghouse development, more than 150 dwellings, or an overall development area exceeding five hectares. Meeting any of those makes the proposal Schedule 2 development requiring screening. Falling below all of them means the screening duty does not arise unless the site lies in a sensitive area.

What counts as a sensitive area?

Sites of special scientific interest, National Parks, the Broads, National Landscapes, World Heritage Sites, scheduled monuments and European sites, among others defined in the regulations. Where development falls within a Schedule 2 description and lies in a sensitive area, the applicable thresholds are disapplied and screening is required whatever the scale.

Can I split a project to stay below a threshold?

No. Where phases are functionally connected, the authority is entitled to screen the project as a whole, and a permission obtained by presenting part of a larger scheme is vulnerable to challenge. Describe the full project in the screening request and argue the effects, rather than trying to keep each phase under the line.

What happens if permission is granted without a required EIA?

The permission is open to legal challenge and the courts have quashed permissions on that ground. The commercial risk falls on the developer, because it is your permission that is lost. The opposite error, preparing an unnecessary environmental statement, costs money and programme time but does not put the decision at risk.

Sources and further reading

eiascreeningthresholdsmajor developmentenvironmental statement

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →
Comparisons7 min read

Building notice or full plans application to building control

Two routes to building control approval under the Building Regulations 2010. What each involves, where a building notice is unavailable, and how completion certificates and regularisation work.

Read article →
Comparisons8 min read

Dropped kerb approval or permission for a front hardstanding

The crossover is licensed under the Highways Act 1980. The driveway behind it is permitted development only if it is porous or drains inside your boundary. Most people need both approvals.

Read article →
Comparisons7 min read

Strategic Environmental Assessment or Sustainability Appraisal

A local plan appraisal discharges two duties at once: strategic environmental assessment under the 2004 Regulations and sustainability appraisal under section 19(5). Only one has sharp legal teeth.

Read article →
Comparisons7 min read

Environmental permit or planning permission for a waste use

The Environment Agency permits the operation. The waste planning authority decides whether the use belongs there. Both are needed, and a registered exemption is not a planning permission.

Read article →