Deeds of variation on a section 73 permission

6 min readBy PlanScope Editorial Team

The original deed often binds only the permission named in it. Here is how to check, which instrument to use, who has to be a party and when it must complete.

A section 73 permission is a new planning permission, not an amendment to the old one. That single point is the origin of almost every problem with a section 106 deed of variation on a section 73 application. If the original deed binds only the permission identified in it by date and reference number, and the section 73 application produces a permission with a new date and a new reference, the obligations may not bind development carried out under the new consent at all.

Councils know this. Their legal teams will not issue the section 73 decision until the position is fixed, which is why an application that looked like a three-month exercise sits waiting on conveyancing.

Why the original obligation may not bind the new permission

Read the definition clause. A deed that defines "the Permission" as "the planning permission to be granted pursuant to application reference 21/01234/FUL" captures one permission and nothing else. Development under a later section 73 consent is development under a different permission, and the covenants, which are usually expressed to apply to the carrying out of the Development pursuant to the Permission, are not engaged.

Some deeds are drafted better. A definition extending to "any permission granted pursuant to section 73 of the Act varying or amending the Permission" solves the problem before it arises, and it costs nothing at the drafting stage.

Others are ambiguous, which is the worst case, because it produces an argument between two sets of solicitors at the end of a determination period. Where the wording is unclear, the practical answer is usually to enter a supplemental deed rather than to argue the construction point.

Reading the definition of the permission in the deed

Work through four clauses before advising the client on cost or timing.

  1. The definition of the Permission and whether it extends to section 73 consents.
  2. The definition of the Development, which may be tied to specific approved drawings.
  3. The trigger events, which often refer to the start of development or to occupation of the Development as defined.
  4. Any clause dealing with subsequent permissions, sometimes buried in the general provisions.

The definition of Development matters as much as the definition of Permission. Where the obligations are triggered by occupation of a defined number of units, and the section 73 application changes that number, the triggers may no longer work even if the deed does bind the new permission.

Check the title as well. The deed binds the land, so a change of ownership or a new charge since the original agreement adds parties to the new document.

Supplemental deed against deed of variation

The two terms are used loosely in practice, and the distinction matters.

Deed of variation Supplemental deed
What it does Alters the terms of the existing obligations Extends the existing obligations to a further permission
Typical use Changing a contribution, trigger or tenure mix Binding a section 73 permission to the original deed
Effect on original Original deed continues as varied Original deed continues, with its scope widened
Complexity Depends on the change Usually short and standardised

For a straightforward section 73 that does not change the obligations themselves, the supplemental route is quicker. Where the variation also changes unit numbers or affordable housing provision, the council will often want the two documents combined, and the negotiation then reopens the substance.

Be clear with the council's solicitor at the outset which document you are proposing. Drafting the wrong instrument and sending it out costs a fortnight.

Who needs to be a party, including mortgagees

Every person with an interest in the land that could defeat the obligation should be a party. In practice that means the freeholder, any leaseholder with a long lease, and any mortgagee.

But mortgagee consent is the item that delays completion. A lender who took security four years ago has to be identified, contacted, and taken through an internal approval process that has nothing to do with the planning timetable. Start that conversation the week the section 73 application is submitted.

Where the land has been sold in part, or where a management company now owns common areas, there may be several parties. Pull an up to date official copy of the register before drafting, not after.

Guarantors and, on larger sites, a promoter or option holder may also need to join. The council's standard instructions usually name the categories it expects.

Timing against the decision date

The supplemental deed must be completed before the section 73 permission is issued, because once the decision has been issued the council has lost its bargaining position and the applicant has lost the incentive.

That creates a straightforward sequencing rule. Agree the form of the deed during the determination period, circulate engrossments for execution as the officer report is finalised, and hold the decision until completion. Most councils have a standard process for this.

Where an extension of time is needed, agree it early and in writing. A refusal issued because the deed was not completed within the statutory period is an avoidable outcome, and an appeal against it wastes six months.

The council will require an undertaking for its legal costs before its solicitor starts work. The undertaking is usually capped, and the cap should be agreed rather than accepted blind.

Budget for the applicant's own legal fees, the council's costs, the cost of obtaining mortgagee consent, and the land registry fees for registering the deed. On a small scheme these can exceed the cost of the section 73 application itself, which surprises clients who thought they were making a minor change.

Where obligations involve contributions that have already been paid or partly spent, the accounting position should be reflected in the new document, and the council's own infrastructure funding statement is a useful cross-check on what has been received and allocated.

Drafting that avoids the problem next time

Four provisions prevent most of this. Define the Permission to include any section 73 permission varying it. Define the Development by reference to the approved scheme generally rather than to a fixed drawing list. Draft triggers by reference to proportions or phases rather than absolute unit numbers. Include a mechanism for adding future permissions without a full renegotiation.

Also keep in mind that section 73 cannot be used to vary the description of development itself, following the Court of Appeal's decision in Finney v Welsh Ministers. Section 73B, introduced by the Levelling-up and Regeneration Act 2023 to provide a wider route for changes that are not substantially different, has its own timetable for coming into force, so check where that stands before advising on route.

Where the variation touches affordable housing, the tenure and mix in the original Affordable Housing Statement is the reference point, and any change there will be treated as a policy matter rather than a drafting one. The same is true where the original scheme was student accommodation, as discussed in student accommodation planning contributions.

A short covering note with the section 73 application, confirming that the applicant will enter a supplemental deed and naming the solicitors, gets the council's legal team engaged on day one. The Planning Statement is the natural place to say it.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Why does a section 73 permission need a new deed?

Because section 73 grants a new planning permission rather than amending the old one. Where the original deed defines the permission by reference to a specific application number, the obligations may not bind development carried out under the later consent. A supplemental deed extends the original obligations to the new permission.

What is the difference between a supplemental deed and a deed of variation?

A deed of variation alters the terms of the obligations themselves, for example changing a contribution or a trigger. A supplemental deed extends the existing obligations to a further permission without changing their substance. For a straightforward section 73 the supplemental route is quicker and usually standardised.

Does the mortgagee have to sign?

Normally yes, because a lender enforcing its security could otherwise take the land free of obligations entered into after the charge. Identifying the lender and working through its internal approval process is the most common cause of delay, so start it when the section 73 application is submitted rather than at the end.

When must the deed complete?

Before the section 73 decision is issued. Once permission has been granted the council has no bargaining position and the applicant has no incentive. Agree the form during the determination period, circulate engrossments as the officer report is finalised, and where necessary agree an extension of time in writing.

Can section 73 change the description of development?

No. Following the Court of Appeal's decision in Finney v Welsh Ministers, section 73 cannot be used to vary the description of development in the original permission. Section 73B, introduced by the Levelling-up and Regeneration Act 2023 for changes that are not substantially different, has its own timetable for coming into force, which should be checked.

Sources and further reading

section 73section 106deed of variationplanning obligationslegal

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial8 min read

Marriage value and site assembly in a viability appraisal

Assembly costs are real, but most of them do not reduce what a scheme can contribute. Where acquisition costs, ransom premiums and created marriage value each belong in the appraisal.

Read article →
Viability, Obligations and Commercial7 min read

Varying a planning obligation after five years

After the five year relevant period, a statutory application under section 106A replaces negotiation, and a refusal can be appealed under section 106B. What the authority can decide and what it cannot.

Read article →
Viability, Obligations and Commercial7 min read

Social infrastructure contributions and how they are justified

Contribution requests are built from a yield factor, a capacity claim and a published cost. The arithmetic is usually right, so the argument belongs on the capacity evidence and the statutory tests.

Read article →
Viability, Obligations and Commercial7 min read

Pooling restrictions and clawback in planning obligations

Regulation 123 and the five obligation pooling cap went in September 2019. What remains is the statutory test in regulation 122, the infrastructure funding statement, and careful drafting against duplication.

Read article →
Viability, Obligations and Commercial8 min read

Indexation of section 106 contributions and which index applies

The index family and the base date decide how far an indexed contribution moves. Name the series exactly, set the base date to the prices the figure is expressed in, and recalculate every demand.

Read article →
Viability, Obligations and Commercial8 min read

Phasing a scheme to manage section 106 triggers

Phasing moves when obligations fall due rather than how much they total. Define phases by land parcel, build in a revised phasing plan mechanism, and tie affordable delivery to occupation within each phase.

Read article →