Section 278 works and how they land in an appraisal

6 min readBy PlanScope Editorial Team

Highway works under section 278 arrive as nine cost lines, not one. What to budget, when the money leaves, and why the bond is released long after completion.

A section 278 agreement cost is rarely one number. It is a works figure, a design check fee, a supervision fee, a bond, a commuted maintenance sum, legal costs and a set of statutory undertaker diversions, spread across a period that starts before your first sale. Developers who carry a single line labelled "highways" in the appraisal are usually carrying about two thirds of the real cost, and the missing third tends to appear at technical approval stage when the layout is fixed.

What a section 278 agreement covers

Section 278 of the Highways Act 1980 lets a highway authority carry out, or allow a developer to carry out, works to the existing public highway where someone else pays for them. It is the mechanism for everything your development needs to do to the road outside it.

Typical scope includes a new priority junction or ghost island right turn, footway widening and crossing points, a relocated or new bus stop, alterations to traffic signals, street lighting, highway drainage, resurfacing across the frontage, traffic calming and the traffic regulation orders needed to change waiting restrictions.

Section 38 of the same Act deals with a different thing: the adoption of new streets inside your site as highway maintainable at public expense. A small scheme with a dropped kerb needs neither, and is dealt with under section 184 as a vehicle crossing application. Knowing which mechanism applies to which part of the work is the first step in pricing it.

Design, approval and supervision fees

The works cost is only the visible part. Highway authorities charge for the technical approval of your design and for supervising its construction, generally under a published schedule expressed as a percentage of the works value, and the percentage varies between authorities.

Get the authority's current schedule before you budget. Then add the items the schedule does not cover.

  • Your own designer's fees for the highway design, road safety audit responses and the technical approval submissions.
  • Road safety audits at the stages the authority requires, with designer responses to each.
  • Traffic regulation order costs, including advertising and the officer time to process objections.
  • Statutory undertaker diversions, quoted under the New Roads and Street Works Act 1991 process, which are frequently the largest single surprise.
  • Traffic management, road space booking charges and any out-of-hours working premium.

Utility diversions deserve a separate line and a separate contingency. A high pressure gas main or a fibre route under the footway can cost more than the junction, and the quotes take months to obtain.

Bonds, securities and the cost of capital

The authority will require security for the works, usually a surety bond or a cash deposit, so that it can complete the scheme if you do not. The bond amount is set against the works value plus the authority's fees, and the bond provider charges for it.

Two appraisal effects follow. The bond premium is a real cost that belongs in the cost plan. And the security is not released until the maintenance period has expired and the works have been certified, which is typically a year or more after completion, so the capital or facility supporting it is tied up beyond practical completion of the development.

A cash deposit is simpler to arrange and worse for cash flow. On a small scheme the difference is immaterial. On a scheme with a £600,000 junction it is not.

Commuted sums for future maintenance

Where the works include anything the authority would not normally maintain, it will ask for a commuted sum to cover future maintenance. Common triggers are non-standard paving materials, street trees in the highway, structures, signals, and drainage features that need cleaning.

Authorities publish rates for these sums and the periods they cover. The design lesson is direct: specify standard materials in the highway unless there is a design reason not to, because a block-paved crossing point can carry a maintenance sum out of all proportion to its construction cost. Where a council's design guidance pushes for the non-standard material, ask for the commuted sum figure at pre-application stage rather than discovering it in the draft agreement.

Interaction with section 38 adoption

Most residential schemes need both. Section 278 handles the connection to the existing network, section 38 handles the estate roads once built. They run on separate timetables with separate bonds, separate inspection regimes and separate maintenance periods.

Item Section 278 Section 38
Location Existing public highway New streets within the site
Trigger Works needed to accommodate development Adoption of internal roads
Security Bond or deposit, released after maintenance period Bond, released on final certificate
Timing pressure Usually before first occupation Usually at or after completion
Appraisal effect Early cash outflow before revenue Spread across the build programme

The sequencing problem is familiar to anyone who has built out a phased site. The junction has to be finished before the first plot is occupied, while the estate roads are adopted at the end, so the highway spend is front-loaded and the bond release is back-loaded.

Programme risk and cash flow

Technical approval is iterative. Each submission round takes weeks, safety audits generate changes, and a design that did not allow for a statutory undertaker's apparatus goes back to the start. Build a realistic number of rounds into the programme rather than one.

Then layer on the constraints that are outside your control. Road space bookings compete with other works, some authorities operate seasonal embargoes on works in retail areas, signal alterations need a road space booking and often night working, and a traffic regulation order that attracts objections can add months.

The appraisal consequence is a cost incurred before any revenue arrives, financed at the development rate. On schemes where the highway works are substantial, that finance cost deserves its own line rather than being absorbed into a blended contingency. Our note on infrastructure funding statements explains how councils report what they collect and spend, which is a useful check when you are asked for a contribution towards works you are also building.

Budgeting the item honestly

A section 278 line built from the following components will survive scrutiny better than a single allowance.

  1. Works construction cost, priced from the approved-in-principle drawing, not from the illustrative access sketch.
  2. Statutory undertaker diversions, quoted, with a stated contingency.
  3. Authority design check and supervision fees from the published schedule.
  4. Your designer's fees, including safety audit responses and approval submissions.
  5. Traffic regulation order costs.
  6. Bond premium or the cost of the deposited capital.
  7. Commuted maintenance sums.
  8. Legal fees for the agreement, both sides.
  9. Traffic management and road space charges.
  10. A contingency that reflects how far the design has progressed.

Where a Transport Assessment has identified junction capacity mitigation, price that mitigation at the same time as the assessment is written rather than after permission. And keep the figure consistent with the appraisal in any Viability Assessment, because a highway allowance that differs between the transport chapter and the viability appendix is the kind of inconsistency a council's reviewer finds quickly.

One point that catches smaller developers. Section 278 payments are not planning obligations, so they sit outside the section 106 negotiation, and a contribution sought for the same works under both routes should be challenged. Contributions to open space and play space are separate again, as set out in our note on open space and play space contributions on small schemes.

The worked figure above is illustrative. This is general guidance, not legal advice; highway costs should be confirmed with the highway authority and a qualified highway engineer. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the difference between section 278 and section 38?

Section 278 covers works to the existing public highway that your development requires, such as a new junction or footway widening. Section 38 covers adoption of new streets built inside the site. Most residential schemes need both, with separate bonds, inspection regimes and timetables, and the section 278 spend comes first.

How are highway authority fees calculated?

Generally as a percentage of the works value under the authority's published charging schedule, covering technical approval of the design and supervision during construction. The percentage varies between authorities, so take the figure from the current schedule. Those fees exclude your own designer's costs and road safety audit work.

Why does the bond matter to the appraisal?

Because it costs money and it ties up capital. The bond is sized against works value plus fees, the provider charges a premium, and the security is not released until the maintenance period ends and the works are certified, often a year or more after completion. A cash deposit is simpler but worse for cash flow.

What is a commuted sum for highway maintenance?

A payment covering the future maintenance of items the authority would not normally maintain, such as non-standard paving, street trees in the highway, structures, signals and drainage features. Authorities publish rates and periods. Specifying standard materials in the highway is the simplest way to avoid a sum out of proportion to the works.

Can a council ask for a section 106 contribution for the same works?

It should not. Section 278 payments are not planning obligations, so works you are funding and building under a highway agreement should not also be sought as a contribution through section 106. Check the draft heads of terms against the highway scope and raise any overlap before the agreement is engrossed.

Sources and further reading

section 278highwaysviabilitydevelopment appraisalinfrastructure

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial8 min read

Marriage value and site assembly in a viability appraisal

Assembly costs are real, but most of them do not reduce what a scheme can contribute. Where acquisition costs, ransom premiums and created marriage value each belong in the appraisal.

Read article →
Viability, Obligations and Commercial7 min read

Varying a planning obligation after five years

After the five year relevant period, a statutory application under section 106A replaces negotiation, and a refusal can be appealed under section 106B. What the authority can decide and what it cannot.

Read article →
Viability, Obligations and Commercial7 min read

Social infrastructure contributions and how they are justified

Contribution requests are built from a yield factor, a capacity claim and a published cost. The arithmetic is usually right, so the argument belongs on the capacity evidence and the statutory tests.

Read article →
Viability, Obligations and Commercial7 min read

Pooling restrictions and clawback in planning obligations

Regulation 123 and the five obligation pooling cap went in September 2019. What remains is the statutory test in regulation 122, the infrastructure funding statement, and careful drafting against duplication.

Read article →
Viability, Obligations and Commercial8 min read

Indexation of section 106 contributions and which index applies

The index family and the base date decide how far an indexed contribution moves. Name the series exactly, set the base date to the prices the figure is expressed in, and recalculate every demand.

Read article →
Viability, Obligations and Commercial8 min read

Phasing a scheme to manage section 106 triggers

Phasing moves when obligations fall due rather than how much they total. Define phases by land parcel, build in a revised phasing plan mechanism, and tie affordable delivery to occupation within each phase.

Read article →