Comparisons

Section 73 or section 96A: which amendment route

7 min readBy PlanScope Editorial Team

The difference sounds procedural and it is why most amendment decisions go wrong. A section 73 permission arrives with fresh conditions, a new levy calculation and no obligation attached.

Section 96A amends the permission you already have. Section 73 grants a new one. That difference sounds procedural and it is the reason most amendment decisions go wrong, because a section 73 permission comes with a fresh set of conditions, a fresh community infrastructure levy calculation, and a section 106 agreement that may not follow it across. If the change is small and uncontroversial, take the non-material route. If it touches a condition that has to move, take section 73 with your eyes open.

What each section actually does

Section 96A of the Town and Country Planning Act 1990 lets a local planning authority make a change to an existing planning permission where the change is non-material. The original permission survives, amended. The power includes imposing new conditions, and removing or altering existing ones, as part of the amendment.

Section 73 works differently. It is an application for planning permission for the development of land without complying with conditions previously attached. The authority considers only the question of the conditions. If it grants, the result is a new planning permission sitting alongside the original, and the applicant may implement either.

Section 96A Section 73
Result Original permission amended New permission alongside the original
Test Whether the change is non-material Whether the conditions should be imposed differently
Publicity Not required by statute Full application publicity and consultation
Determination 28 days 8 weeks minor, 13 weeks major
Description of development Cannot be changed Cannot be changed
Section 106 Continues to attach Usually needs a supplemental deed

The non-material test and who applies it

There is no statutory definition of non-material, which is deliberate. The Act requires the authority to have regard to the effect of the change, together with any previous changes made under the same section, and to decide.

That cumulative wording matters on long-running schemes. Four successive non-material amendments, each defensible alone, can add up to something the authority will not accept as the fifth. Keep a running schedule of amendments made and attach it to each new request, because an officer who has to reconstruct that history from the file will be less generous than one handed it.

What officers accept as non-material varies by authority and by scheme sensitivity. Fenestration adjustments, minor repositioning within the site, small dimensional changes, substitution of a material for a closely similar one, and correction of a drawing error are the usual territory. Anything that changes the appearance from a public viewpoint, alters the relationship with a neighbour, affects a protected asset, or engages a consultee's earlier advice is not. Ask the case officer informally before applying, since a refusal costs a fee and the calendar time anyway.

Why a section 73 creates a new permission

This is the point practitioners most often skip, and it has three consequences.

The new permission is a permission in its own right, with its own reference and its own decision notice. The original stays alive unless and until it expires or is superseded in fact by implementation of the other.

The authority must reimpose every condition it wants to keep. A section 73 decision notice that varies condition 4 and lists only condition 4 leaves the development with a single condition, because the conditions on the original permission do not carry across automatically. Check the draft decision notice before it is issued, and if conditions are missing, say so at once. This is a real and recurring source of dispute.

And the description of development cannot be changed through section 73. The authority is considering conditions, not the operative grant, so a condition cannot be varied in a way that conflicts with what the permission describes. Where the description itself is wrong, section 73 is the wrong tool.

The Levelling-up and Regeneration Act 2023 inserted a further power, section 73B, allowing permission to be granted for development already permitted where the effect is not substantially different from the existing permission. Check the commencement position and any regulations before relying on it, and state the date of your check in advice, because the position has moved more than once.

Conditions, time limits and the section 73 trap

The trap is the time limit, and it catches schemes every year.

A section 73 permission does not reset the implementation clock. The time limit condition on the new permission runs from the date of the original permission, so a variation obtained in year two of a three-year permission leaves one year to implement, not three. Where the original permission has already expired, section 73 cannot be used at all, because there is no extant permission whose conditions can be varied.

Two practical responses. Implement the original permission lawfully before applying, so that the development is under way whatever happens to the variation. Or accept that a fresh full application is the honest route, with the delay and cost that implies.

Watch pre-commencement conditions in particular. If the original permission was implemented after discharging a pre-commencement condition, and the section 73 permission carries a differently worded version of it, the discharge may not transfer.

Effect on a section 106 agreement and on CIL

A section 106 agreement attaches to the permission it was completed in respect of. Unless the deed was drafted to bind any subsequent permission for the same development, including one granted under section 73, the new permission arrives without the obligation attached.

Authorities know this and will usually require a supplemental deed or a deed of variation before issuing the section 73 permission. Build that into the programme, because engrossing a deed with multiple parties and a mortgagee's consent takes weeks rather than days. Check the wording of the original deed at the outset. Some are drafted to follow subsequent permissions and some are not, and the difference decides whether you need the lender in the room.

Community infrastructure levy liability is recalculated on a section 73 permission under the levy regulations, with credit given for the amount payable under the earlier permission. Where floorspace has increased, expect an additional charge. Where indexation has moved since the original, the arithmetic can surprise people, so run it before committing to the route. The treatment of fees for each route is covered in the note on section 73 or section 96A fees and when each applies.

Publicity and what it reopens

Section 96A requires no statutory publicity. Some authorities notify neighbours anyway as a matter of local practice, and a few consult the parish council.

Section 73 is a planning application. It is publicised, neighbours may comment, and statutory consultees may be reconsulted. The authority's consideration is limited to the conditions, so a neighbour objecting to the principle of the development is objecting to something outside the scope. But consultees whose earlier advice bore on the condition being varied will be asked again, and a highway authority that has changed its standards since the original grant may give different advice.

That is the risk to weigh. On a scheme where the local politics have shifted, reopening consultation can be more expensive than living with the condition.

Choosing the route

  1. Write down exactly what needs to change, in the words that would appear on a drawing or a condition.
  2. Check whether the change touches the description of development. If it does, neither section will help.
  3. Assess materiality honestly, including the cumulative effect of earlier amendments.
  4. Check the remaining life of the original permission and whether it has been implemented.
  5. Read the section 106 agreement for wording that follows subsequent permissions.
  6. Run the levy recalculation before applying.
  7. Ask the case officer which route they expect, and record the answer.

Where the amendment needs supporting narrative, a short Planning Statement explaining the change and its effects reads better than a covering letter. The limits of the non-material route are set out in section 96A non-material amendments and their limits, and the consequences of the fresh grant in section 73 variations and the new permission.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Does a section 73 permission reset the time limit?

No. The time limit condition on the new permission runs from the date of the original permission, so a variation obtained in year two of a three-year permission leaves one year to implement. Where the original has already expired, section 73 cannot be used at all, because there is no extant permission to vary.

Can the description of development be changed?

Not through either route. Section 73 allows the authority to consider the conditions rather than the operative grant, so a condition cannot be varied in a way that conflicts with the description. Where the description itself is wrong, a fresh full application is the honest route.

What counts as non-material?

There is no statutory definition. The authority must have regard to the effect of the change together with any previous changes made under the same section, and decide. Fenestration adjustments, small dimensional changes and drawing corrections usually pass. Anything altering the public view, a neighbour relationship or a consultee's earlier advice usually does not.

Does the section 106 agreement carry across to a section 73 permission?

Only if the deed was drafted to bind subsequent permissions for the same development. Otherwise the new permission arrives without the obligation attached, and the authority will normally require a supplemental deed or a deed of variation first. Check the original wording at the outset, because engrossing a deed takes weeks.

Does section 73 reopen public consultation?

Yes. It is a planning application, so it is publicised and consultees may be reconsulted. The authority's consideration is limited to the conditions, but a consultee whose earlier advice bore on the condition may give different advice now against changed standards. Section 96A requires no statutory publicity.

Sources and further reading

section 73section 96aplanning conditionsamendmentssection 106planning consultant

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →
Comparisons7 min read

Building notice or full plans application to building control

Two routes to building control approval under the Building Regulations 2010. What each involves, where a building notice is unavailable, and how completion certificates and regularisation work.

Read article →
Comparisons8 min read

Dropped kerb approval or permission for a front hardstanding

The crossover is licensed under the Highways Act 1980. The driveway behind it is permitted development only if it is porous or drains inside your boundary. Most people need both approvals.

Read article →
Comparisons7 min read

Strategic Environmental Assessment or Sustainability Appraisal

A local plan appraisal discharges two duties at once: strategic environmental assessment under the 2004 Regulations and sustainability appraisal under section 19(5). Only one has sharp legal teeth.

Read article →
Comparisons7 min read

Environmental permit or planning permission for a waste use

The Environment Agency permits the operation. The waste planning authority decides whether the use belongs there. Both are needed, and a registered exemption is not a planning permission.

Read article →