Glossary

Section 73B: varying a permission under the 2023 Act

7 min readBy PlanScope Editorial Team

Section 73B of the 1990 Act, inserted by the Levelling-up and Regeneration Act 2023, allows a permission to be altered where the effect is not substantially different, including its description of development.

Section 73B of the Town and Country Planning Act 1990, inserted by the Levelling-up and Regeneration Act 2023, allows a local planning authority to grant planning permission that alters an existing permission, provided the effect of the new permission would not be substantially different from the effect of the one it varies. The change that matters is the reach: unlike section 73, the new power is not confined to conditions, so the description of development itself comes into play.

Before relying on it, check whether it is actually available to you. A section on the statute book is not the same as a section in force, and the new power needs the relevant provision to be brought into force together with secondary legislation setting the application procedure and the fee. Verify the current position on legislation.gov.uk and against the authority's own application forms rather than assuming, because the answer determines whether you have three routes or two.

What the new power adds

The existing toolkit has a gap, and practitioners have worked around it for years.

Section 96A deals with non-material amendments and cannot touch the description of development. Section 73 allows permission to be granted without complying with conditions, which in practice means varying or removing conditions, and the Court of Appeal in Finney v Welsh Ministers confirmed that it cannot be used to grant something that conflicts with the operative part of the permission. So a scheme whose description said "erection of 24 dwellings" could not become 26 dwellings by condition variation, however modest the change looked.

That left a full fresh application as the only route for a change that was more than non-material but less than a new scheme. Section 73B is aimed squarely at that space.

Route What it can change What it produces
Section 96A Non-material amendments only, not the description An amendment to the existing permission
Section 73 Conditions, within the limits of the operative part A new standalone permission
Section 73B Conditions and the operative part, if the effect is not substantially different A new permission altering the existing one
Fresh application Anything An entirely new permission

The substantially different effect test

The test asks about effect, not about scale of drafting change. A one word amendment to a description can have a large effect, and a long list of condition changes can have almost none.

As a new statutory formula it has no settled judicial interpretation, so the sensible working approach is to read it against the existing case law on the limits of section 73. The courts have consistently refused to allow condition variation to produce a radically altered development, and they have treated conflict with the operative part as fatal. Section 73B removes the second of those obstacles but keeps a version of the first, pitched as a comparison of effects.

Practically, that means the application has to be argued, not asserted. Set out the effect of the existing permission and the effect of the proposed permission, side by side, across the matters the original decision turned on: scale, layout, appearance, access, residential amenity, highway capacity, drainage, heritage and ecology. Then explain why the difference is not substantial.

The comparison is also where the threshold judgements familiar from other parts of the system become useful, since the reasoning about materiality in de minimis in planning judgments covers similar ground from a different angle.

How it differs from section 73 in practice

Three differences are worth planning around.

The first is description. Section 73B lets you propose a changed description, which section 73 does not, and that is the whole reason most practitioners will reach for it.

The second is the condition set. A new permission under either route can carry a fresh set of conditions, and an authority is entitled to revisit them. That is a risk as well as an opportunity, because conditions that were negotiated down three years ago may come back in their original form. Go through the existing conditions line by line and say in the application which should be carried forward unchanged.

The third is what happens to everything hanging off the original permission. Approvals already granted under conditions do not automatically attach to a new permission, so the discharge position needs restating, and the practical mechanics of that are the same as for any new consent, as covered in approval of details or discharge of conditions.

Conditions, obligations and the paperwork around the permission

A varied permission usually needs a varied section 106 agreement. Obligations are tied to the permission they were given for, and a deed of variation or a fresh agreement is normally required so that the obligations bind the new permission as well. Raise it with the authority's legal team early, because a deed of variation can take longer than the application.

Where the original permission was for development subject to environmental impact assessment, a variation can require further environmental information and, depending on the change, a fresh screening opinion. The question is whether the environmental effects of the altered scheme were assessed, which is not the same question as whether the planning effects are substantially different. The scope of that obligation is set out in environmental information under the EIA Regulations.

Community Infrastructure Levy liability is recalculated against the new permission, and a change in floorspace can change the charge even where the planning effect is modest.

Description of development and its limits

The operative part is now variable, but it is not unlimited. Two constraints apply in practice.

A description cannot be rewritten so that a different development is permitted, because that would be a substantially different effect by definition. And a description cannot be used to smuggle in matters that were outside the original application altogether, such as additional land, since nothing in the power extends the application site.

Where the original permission was an outline consent, the interaction with reserved matters needs thought. Varying an outline description can affect what remains to be approved, and the limits on what can be left for later are set out in what cannot be reserved for later approval.

Choosing between the available routes

Illustrative example, not a real case: a permission for 42 dwellings is built out to plot 30 when the housebuilder wants to substitute a different house type on the remaining 12 plots, increasing the total floorspace by about 4 per cent, moving two plots by 1.5 metres and changing the materials on one terrace. Under section 96A the materials and the plot shifts might go through, and the floorspace change probably would not. Section 73 could handle the approved drawings condition but not any change to the description. Section 73B, where available, allows the whole package in one application with a single effects comparison.

The decision tree is short.

  1. If the change is plainly trivial and does not touch the description, use section 96A.
  2. If the change can be delivered by varying a condition without conflicting with the operative part, use section 73.
  3. If the description has to change but the effect is not substantially different, use section 73B where it is in force.
  4. If the effect is substantially different, or if the certainty of a clean consent matters more than speed, make a fresh application.

But do not choose on cost alone. A refused section 73B application leaves you with the original permission and a lost programme, and on a site where the original consent is approaching its time limit that can be an expensive way to save a fee. Whether the new power can be used to alter the time limit condition itself is a point to check against the section as enacted, since section 73 expressly cannot be used for that purpose.

If you are preparing the supporting documents for a variation, the report types by category index is a reasonable way to work out which of the original submissions need updating rather than reissuing.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What does section 73B allow that section 73 does not?

It allows the operative part of the permission, including the description of development, to be altered, provided the effect of the new permission would not be substantially different. Section 73 is confined to granting permission without complying with conditions, and the Court of Appeal in Finney v Welsh Ministers confirmed it cannot produce something conflicting with the operative part.

Is section 73B in force?

Check before relying on it. The section was inserted into the Town and Country Planning Act 1990 by the Levelling-up and Regeneration Act 2023, and bringing it into effect requires the provision to be brought into force alongside secondary legislation setting the procedure and fee. Verify on legislation.gov.uk and against the authority's own application forms.

How is the substantially different effect test applied?

It compares effects rather than drafting changes, so a single word in a description can fail it while a long list of condition changes passes. There is no settled judicial interpretation of the new formula, so argue it by setting the effects of the existing and proposed permissions side by side across the matters the original decision turned on.

Does a section 73B permission need a new section 106 agreement?

Usually a deed of variation at least. Planning obligations bind the permission they were given for, so a new permission generally needs the obligations restated or varied to attach to it. Raise this with the authority's legal team at the outset, because a deed of variation often takes longer to complete than the application itself.

Can the conditions be reopened?

Yes, and that is a real risk. A new permission under either section 73 or section 73B carries its own condition set, and the authority is entitled to revisit it. Conditions negotiated down on the original application can return in their original form. Go through the existing conditions line by line and say which should carry forward unchanged.

Sources and further reading

section 73bsection 73planning permissionlevelling-up actvariationconditions

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary7 min read

Disaggregation of a use: when splitting a unit needs consent

Subdividing a shop, office or house into separately occupied units can amount to development even where the use class does not change. The test turns on the planning unit, not the activity.

Read article →
Glossary7 min read

Blue line land and what it signifies

The red line defines the permission. The blue line defines nothing, but it tells the officer how much land you hold and invites questions worth anticipating.

Read article →
Glossary7 min read

Severability of a planning permission

English law treats a planning permission as authorising one development, not a menu. Hillside confirmed the position, and it shapes how phased sites and drop-in permissions should be handled.

Read article →
Glossary7 min read

Revocation and modification orders explained

A council can revoke or modify a permission it has already granted, but the compensation liability under section 107 is why it almost never does.

Read article →
Glossary7 min read

Imperative reasons of overriding public interest

IROPI is the last-resort route to consent a scheme that will harm a habitats site. It only opens once alternatives are ruled out and compensation is secured.

Read article →
Glossary6 min read

Salami slicing and cumulative effects in EIA

Dividing a scheme into sub-threshold applications does not remove the assessment duty. How officers test for a single project and how cumulative effects are scoped.

Read article →