Wales, Scotland and Northern Ireland

Section 76 planning agreements in Northern Ireland

6 min readBy PlanScope Editorial Team

Northern Ireland has no Community Infrastructure Levy. Every contribution a council seeks has to be secured through a section 76 agreement, which changes how you negotiate.

Planning agreements in Northern Ireland are made under section 76 of the Planning Act (Northern Ireland) 2011. A council, or the Department for Infrastructure where it is the decision maker, enters into an agreement with a person who has an interest in the land, and the agreement binds that land. Northern Ireland has no Community Infrastructure Levy equivalent, so every developer contribution a council seeks has to be negotiated into the agreement itself. This article covers Northern Ireland only and does not describe the position in England, Wales or Scotland.

That single structural difference changes the negotiation. In England a developer can point to a published charging schedule and argue about the rest. In Northern Ireland there is no schedule to point at.

The statutory basis

Section 76 allows an agreement to restrict the development or use of land, to require specified operations or activities, to require the land to be used in a specified way, or to require payments to be made, either as a lump sum or periodically. Those four headings cover everything a council can properly secure through this route.

The agreement runs with the land and is enforceable against successors in title, subject to the terms of the agreement itself. It is registered as a statutory charge, so a purchaser's solicitor will find it on the searches, and it will appear in the report on title long after the original developer has moved on.

Read the current text of the Act on legislation.gov.uk, because the 2011 Act has been amended since it came into operation and the sections dealing with modification and discharge sit alongside section 76 rather than inside it.

What contributions councils seek

Practice varies between the 11 councils, and each sets its expectations through its Local Development Plan and any supplementary guidance. The recurring headings are:

  • Affordable or social housing provision, either on site or as a financial contribution.
  • Open space, play provision and landscape management where the scheme does not provide enough on site.
  • Road and junction improvements, which often sit alongside separate highways consents.
  • Streetscape works and active travel measures.
  • Education or community facility contributions on larger schemes.
  • Management and maintenance arrangements for shared areas and drainage.

The test for what can properly be required is the familiar one of whether the obligation is necessary to make the development acceptable, related to the development, and reasonable in scale and kind. Ask for the policy basis in writing when a contribution is proposed, and ask what it will be spent on.

Why there is no levy equivalent

The Community Infrastructure Levy was introduced for England and Wales, and it was never extended to Northern Ireland. Developer contributions policy has been consulted on since the 2011 Act, but the agreement route remains the mechanism in use.

The practical effects are worth stating plainly. Contributions are negotiated scheme by scheme rather than set by a published rate, which produces less predictability at appraisal stage. Smaller schemes often carry no contribution at all, because the cost of negotiating and completing an agreement outweighs the sum involved. And there is no pooling restriction of the kind that applied in England, so councils are not constrained in the same way when several schemes contribute to one facility.

Budget for legal time rather than for a rate. On a scheme of any size, the agreement is the item most likely to delay the decision.

Drafting, sealing and registration

The sequence usually runs like this.

  1. Heads of terms agreed in principle during the assessment of the application, often through correspondence with the case officer.
  2. Draft agreement prepared, commonly by the council's solicitor, with the developer meeting the council's reasonable legal costs.
  3. Title checked, because every person with an interest in the land, including any mortgagee, normally has to be a party or to consent.
  4. Agreement engrossed, executed and sealed.
  5. Planning permission issued, typically the same day or immediately afterwards, with the decision often held until the agreement completes.
  6. Registration of the statutory charge.

Step three catches people out. A lender that has not agreed to be bound can hold the whole process up, and on a site with multiple owners, option agreements or a ransom strip the title work takes longer than the drafting.

Modification and discharge

Circumstances change. A scheme may become unviable, a facility the contribution was to fund may be built by someone else, or the land may be developed differently under a later permission.

The Act provides for an agreement to be modified or discharged by agreement between the parties at any time, and there is a further statutory route for seeking modification or discharge after a defined period has elapsed, with a right of appeal where a council refuses. Check the current provisions and the periods in the Act before relying on either, because the detail matters and it has been amended.

Where viability is the reason, expect to provide an open book appraisal and to have it scrutinised. A bare assertion that the scheme no longer works will not move a council.

Enforcement against later owners

Because the agreement binds the land, enforcement follows the land. A council can enforce a restriction by injunction, can recover sums due as a debt, and in some cases can enter the land, carry out operations and recover the cost.

For a purchaser this means due diligence on the agreement is not optional. Read every obligation, identify which ones have already been performed, and obtain evidence of performance rather than an assurance. A trigger expressed as "prior to occupation of the 50th dwelling" is easy to miss on a phased site that changed hands at unit 30.

Negotiating the heads of terms

A few habits that produce better agreements.

Get the heads of terms down to one page early, before the drafting starts. Tie every payment to a trigger you control, such as commencement of a phase, rather than to a calendar date. Ask for indexation to be stated explicitly, including the index and the base date, because an unindexed sum and an index applied from the wrong date are both arguments waiting to happen. Seek a longstop refund provision where a contribution is not spent within a defined period. And keep the obligations in the agreement out of the conditions, because duplicating the same requirement in both creates two enforcement routes and two discharge processes.

PlanScope's drafting is grounded in English national policy and English local plans, so a Northern Ireland application needs the reviewer to check the Planning Act (Northern Ireland) 2011, the Strategic Planning Policy Statement and the relevant Local Development Plan. The report types still give a structure for the supporting documents, and PlanScope pricing covers editing and versioning drafts while an agreement is negotiated. To see the document set your scheme is likely to need, start from the PlanScope home page.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This is general guidance, not legal advice; check the position with your council's planning service or a qualified professional before relying on it.

Frequently asked questions

Is there a Community Infrastructure Levy in Northern Ireland?

No. The levy applies in England and Wales and was never extended to Northern Ireland. Developer contributions are secured through planning agreements under section 76 of the Planning Act (Northern Ireland) 2011, negotiated scheme by scheme. That means there is no published charging rate to appraise against, so allow for negotiation time and legal cost instead.

Who can be a party to a section 76 agreement?

The council, or the Department for Infrastructure where it is the decision maker, together with persons who have an interest in the land. In practice that usually includes the freeholder, any leaseholder with a relevant interest and any mortgagee, since a lender that is not bound can undermine the agreement. Check the title early.

Does a section 76 agreement bind a future owner?

Yes. The agreement runs with the land and is enforceable against successors in title, subject to its own terms, and it is registered as a statutory charge so it appears on searches. A purchaser should read every obligation, identify which have been performed and obtain documentary evidence of performance rather than an assurance.

Can a section 76 agreement be changed later?

It can be modified or discharged by agreement between the parties at any time, and the Act also provides a statutory route to seek modification or discharge after a defined period, with an appeal where a council refuses. Where viability is the ground, expect to provide an open book appraisal that the council will scrutinise closely.

What can a council ask for in an agreement?

Section 76 allows restrictions on development or use, requirements to carry out specified operations or activities, requirements to use land in a specified way, and payments as a lump sum or periodically. The obligation should still be necessary to make the development acceptable, related to it and reasonable in scale, so ask for the policy basis in writing.

Sources and further reading

northern irelandsection 76planning agreementsdeveloper contributionsdevolved planningviability

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Wales, Scotland and Northern Ireland

View all →
Wales, Scotland and Northern Ireland7 min read

Householder permitted development in Northern Ireland

Extensions, outbuildings and dormers in Northern Ireland are governed by the Planning (General Permitted Development) Order (Northern Ireland) 2015, not the England Order. The differences are substantive.

Read article →
Wales, Scotland and Northern Ireland7 min read

The two tier planning system in Northern Ireland

Eleven councils determine most applications and the Department for Infrastructure takes the regionally significant ones. The category decides the consultation, the decision-maker and the appeal route.

Read article →
Wales, Scotland and Northern Ireland7 min read

Notification of planning applications to Scottish Ministers

Notification bites after a Scottish authority has decided to approve, not before. The categories that trigger it, what happens during the pause, and why withdrawing a statutory objection is the whole game.

Read article →
Wales, Scotland and Northern Ireland7 min read

The hierarchy of developments in Scotland explained

In Scotland the development category decides whether you must consult the community twelve weeks before applying, how long determination takes and where an appeal goes. Here is how to work out which category applies.

Read article →
Wales, Scotland and Northern Ireland7 min read

Listed building consent in Scotland: categories A, B and C

Scotland grades listed buildings A, B and C, protects interiors as standard and still requires a separate conservation area consent for demolition. Here is how the consent works and who must be consulted.

Read article →
Wales, Scotland and Northern Ireland7 min read

Local place plans in Scotland and what they change

The Planning (Scotland) Act 2019 gave communities a statutory route to set out proposals for land in their area. Registration matters, and so does the timetable.

Read article →