Statutory undertaker permitted development: Parts 13 and 15
Water, sewerage and electricity undertakers hold wide permitted development rights under Parts 13 and 15 of the GPDO 2015. A developer building the same infrastructure does not. Here is how that shapes a utilities programme.
Statutory undertaker permitted development rights belong to the undertaker, not to you. Parts 13 and 15 of Schedule 2 to the General Permitted Development Order 2015 let water undertakers, sewerage undertakers, drainage bodies and electricity undertakers carry out a wide range of works without applying for planning permission. A developer who builds the same substation or pumping station on their own land, in their own name, has no such right.
That distinction decides how you programme utilities on a site. Get the ownership and the sequence right and a connection happens under the undertaker's own rights. Get it wrong and you are adding a planning application to the critical path of a scheme that was supposed to be on site in March.
What Part 13 gives water and sewerage undertakers
Part 13 covers development by water undertakers, sewerage undertakers and drainage bodies. The broad shape of the rights is the laying, altering and repairing of mains, pipes and associated apparatus, works for the inspection, repair or renewal of existing apparatus, and the erection of buildings, plant and machinery on land already held as operational land for the purposes of the undertaking.
The limits are set out in the Part itself and they are specific about height, floor area and position relative to the boundary of the operational land. Read them in the Order rather than relying on a summary, including a summary like this one, because the conditions attached to each Class are where applications go wrong.
Drainage bodies acting under land drainage powers have their own Class, which matters on rural sites where a watercourse or an ordinary watercourse consent is in play. A land drainage consent from the lead local flood authority is a separate permission from planning and neither substitutes for the other.
What Part 15 gives electricity undertakers
Part 15 deals with power related development. An electricity undertaker can install, inspect, repair and alter electric lines, including overhead lines and the supports they sit on, and can carry out works for the purposes of its undertaking on operational land within stated limits. Substations, switching stations and cable sealing end compounds fall into this territory.
The practical boundary is voltage and scale. Overhead electric lines above the thresholds in the Electricity Act 1989 need consent under section 37 of that Act, which is a separate regime run by the Secretary of State rather than by the local planning authority, and large lines and generating stations fall into the nationally significant infrastructure process with a development consent order. None of those routes is planning permission under the 1990 Act, and a planning officer cannot grant or refuse them.
The operational land trap
Most of these rights are tied to operational land. Section 263 of the Town and Country Planning Act 1990 defines it as land used for the purposes of carrying on the undertaking, and section 264 restricts when land that an undertaker has merely acquired counts.
So a distribution network operator who takes a lease over a 15 by 15 metre plot inside your site does not instantly acquire Part 15 rights over it. The land has to be, or become, operational land in the statutory sense. In practice this is handled by including the substation in the planning application for the development, then transferring the completed structure, which is tidier than arguing about section 264 afterwards.
The same logic applies to a foul pumping station that a sewerage undertaker will eventually adopt. Until adoption, it is your structure on your land, and the authority will expect to see it on the layout with its own access, odour control and noise assessment. That is the point at which a foul sewage assessment earns its place in the submission, because it establishes the destination and the capacity before the pumping station is designed around it.
Consents that sit alongside planning
A single connection can touch four or five regimes. The ones that most often surprise a developer are the water and sewerage statutory powers, because they carry fixed procedures and cost allocations.
| Provision | What it does |
|---|---|
| Water Industry Act 1991 section 98 | Requisition of a public sewer, with a cost apportionment formula |
| Water Industry Act 1991 section 104 | Agreement for the undertaker to adopt new sewers once built to standard |
| Water Industry Act 1991 section 185 | Requisition to move or alter a main or sewer, at the developer's cost |
| Water Industry Act 1991 section 106 | Right to connect a drain or private sewer to the public sewer |
| Electricity Act 1989 Schedule 4 | Wayleaves and necessary wayleaves for lines crossing third party land |
| Highways Act 1980 sections 278 and 38 | Works in and adoption of the public highway |
A build-over agreement for a public sewer is a separate undertaker consent again, and it is not unusual for it to force a foundation redesign after planning permission has been granted. Check the sewer records before the layout is fixed, not after.
How these rights change a development programme
Three effects recur on sites of 10 to 100 units.
The first is diversion lead time. A section 185 diversion of a trunk main is designed and delivered by the undertaker to its own programme, and that programme is frequently measured in quarters rather than weeks. The right to require the diversion does not come with a right to require it quickly.
The second is that the undertaker's permitted development rights can run across land you do not control. A new cable route to serve your site may be installed under Part 15 through a neighbour's field with a wayleave, with no application and no consultation that you can influence. Useful when it works for you. Awkward when the chosen route crosses the part of the site you had earmarked for a sales suite.
The third is designated land. In National Parks, National Landscapes, conservation areas and World Heritage Sites, several of these rights are narrowed or made subject to prior approval. A rural scheme that needs a new overhead line to reach it should establish the designation position before the layout assumes an easy connection, and the same caution applies to rural conversions where the whole viability case depends on a low cost connection, as the evidence problems in proving a barn was in agricultural use show in a different context.
Where you have to apply instead
You will need planning permission, in your own name, for a substation or pumping station you build and own before any transfer, for a package treatment plant serving the development, for private water storage or borehole infrastructure, for a district heating energy centre, and for any compound or plant that is not for the purposes of a statutory undertaking at all.
Illustrative example, not a real scheme: a 48 dwelling site needs a new 11 kV substation, a foul pumping station and a 90 metre water main diversion. The substation and pumping station go on the planning layout and into the application, with the substation shown with a 2.4 metre high enclosure and the pumping station set back from the nearest plot with an odour and noise note. The diversion proceeds under section 185 with no planning application at all, because the undertaker carries it out under Part 13. One application, three pieces of infrastructure, two different legal routes.
Set this out plainly in the submission. A utilities assessment that names each connection, states who will build it, under which power, and when, answers questions the case officer would otherwise raise at week six. And the same material belongs in the planning statement where the scheme depends on infrastructure that is not part of the application.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. A Lawful Development Certificate under section 192 of the 1990 Act is the only formal way to confirm that proposed works are lawful without permission.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Can a developer rely on statutory undertaker permitted development rights?
No. Parts 13 and 15 of Schedule 2 to the General Permitted Development Order 2015 grant rights to the undertaker carrying out development for the purposes of its undertaking, usually on its operational land. A developer constructing a substation or pumping station in their own name needs planning permission, normally obtained by including the structure in the application for the wider scheme.
When does land become operational land?
Section 263 of the Town and Country Planning Act 1990 defines operational land as land used for the purposes of carrying on the undertaking, and section 264 limits when land an undertaker has merely acquired counts. Buying or leasing a plot inside a development site does not automatically confer the rights, which is why substations are usually consented with the scheme and transferred afterwards.
Do overhead electric lines need planning permission?
Lines above the thresholds in the Electricity Act 1989 are consented under section 37 of that Act by the Secretary of State rather than by the local planning authority, and the largest lines and generating stations go through the nationally significant infrastructure process with a development consent order. Smaller works by an electricity undertaker can fall within Part 15 of the GPDO 2015.
Who pays to divert a water main across a development site?
The developer. Section 185 of the Water Industry Act 1991 lets you require the undertaker to move or alter a main or sewer, and the costs fall on the person making the requisition. The undertaker designs and delivers the works to its own programme, which is often measured in quarters, so start the process before the layout is finalised.
Are these rights narrower in a conservation area or National Park?
Yes. Several Classes in Parts 13 and 15 are restricted or made subject to prior approval on designated land, which includes National Parks, National Landscapes, conservation areas and World Heritage Sites. On a rural or sensitive site, confirm the designation position before assuming that a new connection or overhead line can proceed without an application.