Temporary traffic orders for construction works

6 min readBy PlanScope Editorial Team

A construction programme usually needs four separate highway permissions, each under a different power. What each one covers, how long it lasts and what happens when works overrun.

A temporary traffic regulation order is not a planning document, and nobody at the council's planning service can grant you one. It comes from the highway authority's traffic team under section 14 of the Road Traffic Regulation Act 1984, on its own timetable, and a temporary traffic regulation order for construction typically needs weeks of lead time rather than days. Programme it alongside the discharge of conditions, not after.

Most sites need more than one permission. A closure order, a footway licence, a bay suspension and a skip permit are four separate applications to the same authority, each with its own fee and its own notice period.

What each permission actually covers

The vocabulary is worth getting right, because asking for the wrong instrument wastes a fortnight.

Instrument Power What it allows
Temporary traffic regulation order Road Traffic Regulation Act 1984 section 14(1) Closure, one-way working, prohibition of turns or waiting restrictions for works
Temporary notice Road Traffic Regulation Act 1984 section 14(2) Short-notice restriction for urgent works, with a much shorter maximum duration
Scaffolding licence Highways Act 1980 section 169 Scaffold, loading towers and gantries standing on the highway
Deposit of materials or skip permit Highways Act 1980 sections 171 and 139 Materials, plant or a builders skip placed in the carriageway or footway
Hoarding licence Highways Act 1980 section 172 A hoarding or fence enclosing the works next to the highway
Street works licence New Roads and Street Works Act 1991 section 50 Placing or connecting apparatus in the street
Parking bay suspension The authority's own traffic management order Suspending resident, pay and display or loading bays

Section 278 works to the highway itself sit outside this list. They follow the permission rather than the construction programme, and the sequencing is covered in our note on section 278 agreements and how they follow a permission.

Duration limits and the advertising you cannot skip

An order made under section 14(1) can run for a maximum of 18 months on a road. Where the restriction affects a footpath, bridleway or similar route, the maximum is six months. A temporary notice under section 14(2) is a short-term instrument for urgent work and cannot be stretched to cover a planned programme.

The procedure regulations require the authority to advertise the proposed order in a local newspaper before it comes into force, and to display notices on the affected lengths of street. Authorities publish their own lead times on top of that statutory minimum, usually to allow for consultation with the emergency services, bus operators and neighbouring authorities. Six to twelve weeks is a common published figure for a full order.

So the practical rule is simple. The date you want the road shut is not the date you apply.

Suspending parking bays

Bay suspensions are the least expensive permission to obtain and the one most often forgotten until the crane arrives. They are made under the authority's existing traffic management order rather than under section 14, which is why the process and the notice period differ from a closure.

Three points decide whether a suspension survives the works. First, the length suspended has to cover the actual swing and outrigger footprint, not the vehicle. Second, residents displaced from suspended bays will complain to the ward councillor, so a letter drop beyond the statutory notice is worth the stamp. Third, in a controlled parking zone the suspension charge is usually levied per bay per day, and a four-month suspension of six bays is a real number in the preliminaries.

Where the scheme's own parking position is contested, the evidence base is different again. A Parking Survey addresses on-street stress for the completed development, and it will not answer anything about the construction phase.

Footway closures and keeping people moving

Closing a footway is harder to justify than closing a traffic lane, and the authority will push back on a diversion that sends pedestrians across the road twice. Expect to be asked for a pedestrian management drawing showing the width maintained, tactile paving at any temporary crossing point, step-free routes, and how a wheelchair user or someone pushing a double buggy gets past the hoarding line.

The usual answer on a tight urban site is a licensed gantry: scaffold over the footway with a protected walkway beneath, lit, with a boarded deck and a solid fan above. It costs more than a closure and it removes the argument.

Where the footway cannot be kept open at all, a signed diversion needs the same drawing plus a note on bus stop access. Temporary bus stop suspensions are negotiated with the operator and the authority together and they take longer than everything else on the list.

Most permissions of any size carry a condition requiring a construction management plan or construction traffic plan to be approved before works start. That is where the highway instruments get named.

A Construction Traffic Management Plan should state which orders and licences are being sought, the routes heavy goods vehicles will use, holding arrangements so lorries do not queue on the public highway, wheel washing, and the banksman arrangements at the gate. A broader Construction Management Plan picks up hours, deliveries, dust and complaint handling.

Officers read these documents for consistency. A plan showing a two-way working arrangement while the traffic team is being asked for a full closure will be noticed, and the condition will not be discharged until the two match.

As an illustrative example, a nine-unit infill scheme on a bus route needed a lane closure with temporary signals for eleven weeks of substructure work, a scaffold licence for the full build, suspension of four resident bays, and a skip permit renewed monthly. Four applications, three fee accounts, one programme. The condition discharge referenced all of them.

When the works overrun

Overrun is the normal case, not the exception, and the instruments respond to it differently.

  1. A section 14(1) order can be extended, but an extension beyond the statutory maximum needs the Secretary of State's consent and that is not a routine request.
  2. Scaffold and hoarding licences are typically issued for a fixed period and renewed on application, with the fee recalculated for the new period.
  3. Bay suspensions are extended administratively, usually with a few working days notice, provided the charge is paid.
  4. Where a lane rental scheme applies to the street, charges accrue daily on the most sensitive routes and overrun becomes expensive quickly.

Build float into the order dates rather than the works dates. An order that expires before the works finish stops the site, because continuing to occupy the highway without authority is an offence and the authority can remove the obstruction and recharge you.

Check each instrument's published fee and lead time with the relevant highway authority at the outset, since both are set locally and reviewed annually. This is general guidance, not legal advice; confirm the position with the highway authority or a qualified professional before relying on it.

Browse all 66 PlanScope report types to see which construction-phase documents your conditions are likely to require.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How long does a temporary traffic regulation order take to obtain?

The statutory steps include newspaper advertisement and site notices before the order takes effect, and authorities add consultation time for emergency services, bus operators and neighbours. Published lead times of six to twelve weeks for a full order are common. Check the figure with the highway authority at the outset, because it is set locally and reviewed each year.

How long can a temporary traffic regulation order last?

An order under section 14(1) of the Road Traffic Regulation Act 1984 can run for up to 18 months on a road, and up to six months where it affects a footpath or bridleway. A temporary notice under section 14(2) is a short-notice instrument for urgent works with a far shorter maximum, and cannot be used to cover a planned programme.

Do I need a separate licence for scaffolding on the pavement?

Yes. Scaffolding, loading towers and gantries standing on the highway need a licence under section 169 of the Highways Act 1980. Hoardings need a separate licence under section 172, builders skips under section 139, and deposited materials under section 171. Each carries its own fee, period and renewal process with the highway authority.

Who suspends parking bays?

The highway authority, acting under its existing traffic management order rather than under section 14. Suspension is usually charged per bay per day in a controlled parking zone, so a long suspension of several bays is a real cost in the preliminaries. Suspend the length that covers the crane outriggers and swing, not just the vehicle.

What happens if the works overrun the order?

Occupying the highway without authority is an offence and the authority can remove the obstruction and recharge you, which stops the site. Licences and suspensions are extended administratively on payment, but extending an order beyond the statutory maximum needs the Secretary of State's consent. Build float into the order dates rather than the works dates.

Sources and further reading

construction traffichighwaysroad closuresttroparkingconditions

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking7 min read

Mobility hubs and shared transport secured by condition

A condition can require the bays and the power supply. It cannot fund an operator or make a car club viable. How to split the commitment so the scheme survives withdrawal.

Read article →
Transport, Highways and Parking7 min read

Network Rail consultation where a crossing is affected

Where a scheme adds movements across a level crossing, the rail operator's risk assessment governs the outcome rather than highway capacity. What the evidence has to show.

Read article →
Transport, Highways and Parking6 min read

Section 59 claims for extraordinary traffic damage

A section 59 claim arrives after the road has been resurfaced, by which point the only useful evidence is the baseline survey nobody took.

Read article →
Transport, Highways and Parking7 min read

Access onto a single track rural lane

On a single track lane the highway objection is about geometry and conflict rather than flow. What to survey, what to draw and how to make a passing bay offer deliverable.

Read article →
Transport, Highways and Parking7 min read

Committed development and cumulative impact in a TA

Agree the committed development list and the background growth factors with the highway authority before commissioning surveys, because the list usually decides the capacity conclusion.

Read article →
Transport, Highways and Parking7 min read

Pedestrian audits and crossing provision evidence

An audit that produces a located, priced schedule of defects and remedies is evidence. A page of photographs is not. How to choose routes, score them and link findings to mitigation.

Read article →