Ecology, BNG and Protected Species

Timing vegetation clearance around the bird nesting season

7 min readBy PlanScope Editorial Team

The Wildlife and Countryside Act protects a nest while it is in use, whatever the date. How to check, supervise, record and programme site clearance.

Vegetation clearance and the bird nesting season is a programme problem, not a legal grey area. Section 1 of the Wildlife and Countryside Act 1981 makes it an offence to damage or destroy the nest of any wild bird while that nest is in use or being built, and to kill, injure or take a wild bird or its eggs. The offence applies whenever there is an active nest, so the familiar March to August window is a rule of thumb about when nests are likely rather than a period during which the law switches on.

What the law protects and for how long

The protection attaches to the nest, the eggs and the bird. A nest in use or under construction cannot lawfully be damaged or destroyed, whatever the date, and the birds using it cannot be killed, injured or taken.

Birds listed on Schedule 1 to the Act have further protection. For those species it is also an offence to disturb them while building a nest, or while in or near a nest containing eggs or young, and to disturb dependent young. Barn owl, kingfisher, little ringed plover, firecrest and others appear on that list, and the practical effect is that a Schedule 1 nest halts work over a much larger area and for longer.

There is no defence of not having looked. Clearing a hedge in June without checking it is exactly the situation the offence is drafted for, and the contractor with the flail as well as the person who instructed them can be liable.

The conventional season and why it is not a hard boundary

Most authorities condition clearance around 1 March to 31 August, and that window captures the majority of breeding activity in England.

It leaves gaps at both ends. Tawny owls and ravens begin early in the year. Barn owls and collared doves can produce broods almost any month. Feral and woodpigeons nest more or less continuously. So a September clearance is lower risk rather than no risk, and a February clearance in a mild year is not automatically safe.

The habitat matters as much as the date. Dense scrub, thick hedgerows, ivy-clad trees, reedbed, rough grassland used by ground-nesting species such as skylark, and buildings with open eaves all hold nests that a quick look from the cab will not find. Bare arable and close-mown amenity grass hold almost none.

Treat the calendar as a risk indicator and the check as the control.

Pre-clearance checks and who should do them

A pre-clearance nesting bird check is a targeted walkover of the vegetation to be removed, carried out by an ecologist or a suitably experienced person, immediately before the machinery arrives. Within 48 hours is the convention, because birds build fast.

What a proper check covers:

  1. Every section of hedge, scrub block, tree and ivy mass within the clearance area, inspected at close range rather than from a distance.
  2. Ground-nesting habitat walked in a pattern rather than skirted, in grassland, heath or fallow ground.
  3. Buildings and structures within the works, including eaves, soffits, ledges and open sheds.
  4. Behavioural indicators as well as nests themselves: alarm calling, repeated visits to one point, adults carrying food or nest material.
  5. The area beyond the works where a Schedule 1 species might be disturbed by noise or machinery.

The person doing it needs to know what a nest of each likely species looks like and where it sits. This is not the site manager's job, and a check recorded as "walked the hedge, saw nothing" will not help anyone later.

Where the site already has a Preliminary Ecological Appraisal, the habitats needing attention are already mapped, which makes the check quicker and less costly.

Supervised clearance and the written record

Where the check finds nothing, clearance can proceed under ecological supervision, with the ecologist present while the sensitive sections are cut and able to stop work.

The record is what protects you. It should state the date and times, the name and experience of the person who carried out the check, the weather, the exact extent inspected shown on a plan, the method, what was found, photographs, and the time clearance began and finished. Keep it with the site records rather than in an email.

Where a nest is found, stop in that section. Mark an exclusion buffer around it, sized to the species and the disturbance, and leave the vegetation until the young have fledged and the ecologist confirms the nest is no longer in use. Common hedgerow species may need only a few metres. A Schedule 1 nest may need tens of metres and a licence position considered.

Build the protocol into the Construction Management Plan so the contractor is bound by it rather than reminded of it.

Where a condition fixes the timing

Most permissions affecting hedgerows, trees or scrub carry a condition in a familiar form: no vegetation clearance during the bird nesting season, usually defined as 1 March to 31 August inclusive, unless a check by a suitably experienced ecologist immediately beforehand confirms no active nests are present and the results are submitted to the local planning authority.

Read the wording carefully, because the variations matter. Some conditions require the check to be submitted and approved in writing before clearance, which adds a determination period you have to programme for. Some require a named ecologist. Some prohibit clearance in the season outright, with no check exemption, which is unusual but not unknown.

Breaching a condition is a separate matter from the criminal offence under the 1981 Act, and the council can enforce on it even where no nest was present.

Consequences of clearing an active nest

The offence is prosecuted by the police, usually through a wildlife crime officer, on evidence that frequently comes from a neighbour's phone. Penalties include a fine and the possibility of imprisonment, and each nest, egg or bird can be treated as a separate offence, so a single hedge can generate a long charge sheet.

The planning consequences run in parallel. Expect a stop notice or at least an instruction to halt, a request for a remediation and replanting scheme, and a markedly less sympathetic reading of every subsequent application on that site.

There is also a biodiversity net gain trap. Where habitat is degraded by activities carried out after 30 January 2020, the Environment Act 2021 allows the pre-development biodiversity value to be assessed as at the earlier, undegraded state. Clearing a hedge to reduce the baseline before the Biodiversity Net Gain Assessment is prepared therefore achieves nothing except a larger obligation and a hostile case officer. The wider duty on authorities to have regard to biodiversity is explained in our note on the biodiversity duty and how councils must apply it.

Note that the statutory biodiversity metric must be completed by a competent person and the biodiversity gain plan approved by the local planning authority, so a draft is a starting point for that professional rather than a substitute.

Building the constraint into the construction programme

Work backwards from the clearance date.

  • Ideally, programme vegetation removal for September to February and treat any need to clear within the season as a change requiring a check and supervision.
  • Where the season cannot be avoided, allow a contingency of several weeks in the programme for a nest being found. Fledging periods for common hedgerow species run to a few weeks, and a second brood can follow.
  • Arrange the ecologist early. Good local ecologists are booked through spring and summer, and a check arranged at two days notice in June frequently cannot be resourced.
  • Separate the clearance from the enabling works in the contract so a delay in one section does not stop the site.
  • Deal with hedgerow removal consent separately. Removing a countryside hedgerow may require notice under the hedgerow regulations on its own timetable, and that is a different question from nesting birds.
  • Avoid netting hedges as a workaround. It attracts complaints, and birds trapped behind netting create the offence you were trying to avoid.

A last point on sequencing. Cutting hedges and scrub back hard in January, before birds settle, is lawful and reduces the chance of a nest appearing in March. Doing the same thing in April to deter nesting is not, and inspectors have little patience with it.

To see which ecology documents your site is likely to need before you fix a start date, enter your postcode on PlanScope and run the constraint check.

This is general guidance, not legal advice. Ecological work should be commissioned from a suitably qualified professional. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

When is the bird nesting season for planning conditions?

Conditions usually define it as 1 March to 31 August inclusive. The legal protection is not limited to those dates, because the offence relates to a nest that is in use or being built at any time of year. Treat the dates as a risk indicator and the pre-clearance check as the control.

Who can carry out a pre-clearance nesting bird check?

An ecologist or a suitably experienced person who can identify nests and the behaviour that indicates them. Conditions often specify a suitably experienced ecologist. It is not a task for the site manager, and a record reading simply that the hedge was walked and nothing seen will not stand up afterwards.

What happens if an active nest is found?

Stop clearance in that section, mark an exclusion buffer sized to the species and the disturbance, and leave the vegetation until the young have fledged and the ecologist confirms the nest is no longer in use. A Schedule 1 species needs a larger buffer and a licence position considered before any work nearby.

Can I clear vegetation early to reduce my biodiversity baseline?

No. Where habitat has been degraded by activities carried out after 30 January 2020, the Environment Act 2021 allows the pre-development biodiversity value to be assessed at the earlier, undegraded state. Clearing to lower the baseline produces a larger obligation and an unsympathetic case officer.

Is netting a hedge a lawful way to prevent nesting?

It is legally risky and practically unwise. Netting has to be installed before any nesting activity, maintained so that no bird can get behind it, and removed promptly. Birds trapped by netting create the very offence the netting was meant to avoid, and the practice attracts complaints and press attention.

Sources and further reading

ecologynesting birdssite clearancebiodiversity net gainconstruction

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Ecology, BNG and Protected Species

View all →
Ecology, BNG and Protected Species7 min read

Local nature recovery strategies and the metric multiplier

A habitat identified in a local nature recovery strategy attracts a higher strategic significance multiplier. That makes the local habitat map a layout document, not a submission document.

Read article →
Ecology, BNG and Protected Species8 min read

Ancient woodland buffers and the evidence behind them

A 15 metre buffer of semi-natural habitat is the starting point, measured from the woodland edge rather than the inventory polygon. The pressures it addresses and the evidence that moves the figure.

Read article →
Ecology, BNG and Protected Species7 min read

SSSI impact risk zones and what they actually trigger

An impact risk zone is a consultation trigger, not a designation. How to check the layer on MAGIC and planning.data.gov.uk, read the development categories, and give Natural England what it needs first time.

Read article →
Ecology, BNG and Protected Species7 min read

When a preliminary appraisal becomes an impact assessment

The appraisal is a constraints document and the assessment judges effects on important features. Which triggers force escalation, how the survey calendar differs, and how to write the brief.

Read article →
Ecology, BNG and Protected Species7 min read

Programming a scheme around bat survey seasons

A preliminary roost assessment can be done in any month, but emergence and re-entry surveys are limited to the maternity season. Survey effort by roost potential, and how to keep the rest of the scheme moving.

Read article →
Ecology, BNG and Protected Species8 min read

The degradation rule and your biodiversity net gain baseline

Schedule 7A to the Town and Country Planning Act 1990 reverts the pre-development biodiversity value to its pre-clearance level where habitat was degraded after 30 January 2020.

Read article →