Templates, Checklists and Examples

Travel Plan outline with monitoring targets

6 min readBy PlanScope Editorial Team

Targets, a named coordinator, dated surveys and a written consequence for missing them are what make a travel plan enforceable. The rest is optional.

A travel plan outline that survives negotiation has measurable targets, a named person responsible for them, dated monitoring surveys and a written consequence for missing them. Everything else is optional. A plan that lists measures without targets cannot be monitored, and a plan that cannot be monitored cannot be secured through a planning obligation, which is why authorities reject them.

The sections below are the structure. The specific figures in any real plan come from the site's own baseline, so treat the numbers here as placeholders for something you have to measure.

Baseline accessibility and survey data

Start with what the site has, described in numbers rather than adjectives.

Set out the walking and cycling isochrones to local facilities, the bus stops and rail stations within a stated walking distance with their service frequencies and destinations, the accessibility rating where the authority uses one, and the condition of the routes. A footway that ends 200 metres from the site boundary is a fact the plan has to deal with.

Then establish the travel baseline. For a new development there is no existing travel behaviour, so the baseline is a modal split assumption taken from census or local travel data for comparable sites, stated as an assumption and identified as such. For an expansion or a change of use, survey the existing occupiers.

The Transport Assessment will have derived a modal split already. Use the same figures in both documents. Officers notice when they differ.

Objectives and measurable targets

Targets have to be expressed so that a survey five years later can say yes or no.

A workable target has four parts: the mode, the direction and size of the change, the baseline it is measured from, and the date by which it applies. So a target reads as a stated percentage point reduction in single-occupancy car mode share against the opening-year baseline, achieved by the fifth year after occupation.

Three drafting rules save trouble later.

  • Set targets on mode share, not on trip numbers, because trip numbers move with occupancy and vacancy.
  • Set an interim target as well as a final one, so that a shortfall is identified at year one rather than year five.
  • Do not set a target you have no measure for. A target about awareness of sustainable travel options with no survey question behind it is dead wording.

Measures by mode

List only measures that will actually be delivered, with the delivery mechanism and timing against each.

Walking: the routes to be improved, the lighting and surfacing works, wayfinding signage, and any off-site crossing or dropped kerb secured through a highway agreement.

Cycling: the number and type of cycle parking spaces, designed to the current national cycle infrastructure guidance rather than to a bare number, with the stand type, spacing and cover specified. For employment or education uses, showers, lockers and drying space. For residential, secure ground-floor storage that does not require carrying a bicycle up steps.

Public transport: any stop upgrade, shelter, real-time information display, service contribution or ticketing offer. Where a contribution to a bus service is proposed, say what it buys and for how long.

Car: the parking quantum and management arrangements, electric vehicle charging provision including passive provision, car club spaces with the operator arrangement, and a car sharing scheme with the platform named.

Servicing and deliveries: consolidation arrangements, delivery windows, and a parcel room for residential schemes, which removes a surprising number of van trips from the kerb.

Roles and the coordinator

Name the role rather than a person. A travel plan coordinator post, with the time allocation, the reporting line and a contact route that outlives staff changes.

The responsibilities to set out are: delivering the measures to the stated timetable, running the monitoring surveys, reporting results to the authority, proposing remedial measures where targets are missed, and being the point of contact for occupiers. Where the development has multiple occupiers or a management company, say which entity holds the role after the developer leaves.

This is the clause that fails in practice. A plan that makes the developer responsible for monitoring in year five, on a scheme the developer will have sold by year two, is unenforceable in substance even if the obligation is drafted correctly.

Monitoring surveys and their timing

Set out the survey programme with dates expressed relative to occupation.

  1. A baseline survey once occupation reaches a stated proportion, commonly around three quarters, and within a stated number of months of that point.
  2. Repeat surveys at fixed intervals after the baseline, typically at years one, three and five.
  3. Multi-modal counts at the site accesses on a neutral weekday, with the survey period and hours specified.
  4. An occupier travel questionnaire with a minimum response rate stated, and a method for chasing responses to reach it.
  5. A written report to the authority within a stated number of weeks of each survey, comparing results against the targets.

And specify the neutral survey periods, because a questionnaire circulated in August will produce a flattering result and a challengeable one. Specify what happens if the response rate is not met, since without that the whole monitoring structure can be defeated by silence.

Set out who pays for the surveys too. A monitoring fee paid to the authority covers its officer time, not the survey work itself, and the two are often conflated in negotiation.

Remedial measures if targets are missed

This is the section authorities read first. It needs a menu of additional measures held in reserve, an escalation sequence and a funding route.

The menu might include additional cycle parking, a longer car club subscription, a higher parking charge, a reduction in permits, additional real-time information, or a further contribution to a bus service. Each should be costed at the outset so the obligation can cap the liability.

The escalation sequence matters as much as the menu: a missed interim target triggers a review and an agreed additional measure, a missed final target triggers a further round. Without an escalation the authority's only remedy is enforcement of the obligation, which nobody wants.

Where a bond or a monitoring fee is proposed, say what triggers a draw-down and what releases the balance.

Securing the plan in an obligation

A framework or interim travel plan is usually submitted with the application and the full plan secured by condition or obligation for approval before occupation. The obligation is what makes the targets bite.

The drafting to get right: who holds the obligation after disposal, the monitoring fee and what it covers, the survey and reporting obligations with dates, the remedial measures menu with a financial cap, and the release mechanism when the final monitoring period ends. A plan with no end date is a liability that runs with the land indefinitely.

Where parking restraint is central to the plan, the authority may also want a Parking Survey of surrounding streets to establish that displaced parking will not cause a problem. Commission that in a neutral period.

Draft your Travel Plan in minutes and then send it for professional review. The drainage strategy outline applies the same section-by-section approach to a different discipline. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This is general guidance rather than legal advice, so check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

What makes a travel plan target enforceable?

Four elements: the mode it applies to, the direction and size of the change, the baseline it is measured from, and the date by which it applies. Set targets on mode share rather than trip numbers, because trip numbers move with occupancy. Add an interim target so a shortfall is caught at year one rather than year five.

When should the baseline monitoring survey be carried out?

Once occupation reaches a stated proportion, commonly around three quarters, and within a defined number of months of that point. Surveying too early gives a baseline that reflects an empty building, and surveying too late loses the comparison. Fix the trigger in the plan and in the obligation so it cannot drift.

Who holds the travel plan obligations after the developer sells?

Whoever the obligation names, which is why the drafting matters. On multi-occupier or managed schemes the management company usually takes the coordinator role and the monitoring duty. A plan that leaves year five monitoring with a developer who will have left the site by year two is unenforceable in substance whatever the wording says.

What should the remedial measures section contain?

A menu of additional measures held in reserve, each costed at the outset, an escalation sequence linking a missed target to a review and an agreed additional measure, and a funding route with a financial cap. Without an escalation the authority's only remedy is enforcing the obligation, which is slow and helps nobody.

Does a travel plan have to be submitted with the application?

A framework or interim plan usually is, with the full plan secured by condition or obligation for approval before occupation. Drafting it early pays off, because the measures it contains can be reflected in the transport assessment's modal split rather than appearing as an afterthought once the trip generation is fixed.

Sources and further reading

travel planmonitoringsection 106transporttemplates

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →