Trial trenching tests what the desk-based assessment predicted. Here is how sampling levels are justified, how layouts are designed and what each result means for the scheme.

Trial trenching answers one question: is there archaeology here, and if so, what is it, how well preserved is it, and how far does it extend. The county archaeologist sets the sampling level, commonly expressed as a percentage of the developable area, and negotiating that figure down without evidence is the fastest way to end up doing the work twice.

Two per cent, five per cent, ten per cent. Those numbers get quoted as if they were national standards. They are not, and the justification behind the figure matters more than the figure.

What an evaluation is meant to establish

Evaluation sits between the desk-based work and any mitigation. The Archaeological Desk-Based Assessment tells you what is recorded: previous finds, cropmarks, historic maps, the Historic Environment Record, and the archaeological character of the area. Evaluation tests that on the ground.

The output is a statement about presence, absence, date, character, extent, depth, preservation and significance. Those eight things drive every decision that follows, from whether the scheme needs redesigning to what the mitigation condition will say and what it will cost.

An evaluation that reports only presence or absence has not done the job. Depth and preservation matter as much, because features surviving 300 millimetres below a ploughsoil behave very differently from features sealed under a metre of alluvium.

Choosing between geophysics and trenching

Geophysical survey, usually magnetometry on open land, covers large areas quickly and at low cost relative to excavation. It works well on ditched enclosures, kilns and burnt features, and it is close to useless for timber structures, shallow features, burials without grave goods, and anything under made ground or on certain geologies.

Trenching is the definitive test. It is slower, it needs machine time and a supervising archaeologist, and it produces evidence that a curator will accept without further argument.

The usual sequence on a greenfield site is geophysics first, then targeted trenching over the anomalies plus a blank-area sample to test for features geophysics cannot see. Skipping the blank-area sample is a standard shortcut and a standard reason for a curator to ask for more work. On brownfield sites geophysics is often abandoned altogether, because services, made ground and rubble render it unreadable.

Ask the curator which they expect before commissioning either. The written scheme of investigation has to be approved by them in any event, and their view on methodology is the one that counts.

Sampling levels and how they are justified

The sampling level is the proportion of the developable area opened as trenches. It is agreed with the archaeological curator, and there is no national figure.

What moves it up or down:

  • the archaeological potential shown in the desk-based assessment, which is the single largest factor
  • whether geophysics has already targeted the trenching, which can allow a lower overall figure
  • the geology and depth of overburden, since deeper deposits need larger or stepped trenches
  • the scale and nature of the impact, with piled foundations treated differently from full excavation
  • previous investigation on or adjacent to the site
  • whether the site lies within an Archaeological Priority Area or similar local designation

Sampling levels rise sharply once something is found. A first phase at a modest percentage that turns up real features is often followed by a second phase targeted on them, and the budget should carry that contingency from the start.

Trench sizes are conventionally long and narrow, commonly 30 metres by 1.8 metres or 20 metres by 2 metres, because length intercepts linear features and width is governed by the bucket. State the dimensions in the scheme of investigation, because a percentage figure alone allows very different layouts.

Trench layout, access and constraints

Layout should be designed to test, not to avoid. A grid or a staggered array across the developable area is the default, adjusted to target geophysical anomalies and to sample areas the survey could not read.

Real sites impose constraints, and each one needs recording in the report:

  1. Live services, which need a utility search and scanning before machines move.
  2. Trees, with root protection areas to BS 5837 keeping trenches out of large parts of some sites.
  3. Standing buildings and hardstanding, where breaking out adds cost and may need separate permission.
  4. Protected species and habitat, since trenching in a bat foraging corridor or a reptile area needs its own method statement.
  5. Ground conditions, with waterlogging closing sites in winter and shrinkable clay needing shoring.
  6. Access for a tracked excavator and a dumper, which on a landlocked field is not a given.
  7. Ownership and tenancy, because a farm tenant has rights and crops have value.

Where trenches have to be moved, say so in the report and explain what that means for confidence. A curator reading a report that quietly omits a third of the site will assume the worst.

Reporting and the significance judgement

The evaluation report sets out the methodology, the trench records, the finds and environmental assessment, and a statement of the significance of what was found. That significance judgement is what feeds into the planning balance under national heritage policy, and it should be expressed in those terms rather than in purely archaeological ones.

Standards matter here. Councils expect the work to follow the Chartered Institute for Archaeologists standards and guidance for field evaluation, and to be carried out by an organisation or individual on the appropriate register. In a World Heritage Site or its buffer zone the bar rises again, as the note on World Heritage Sites and their buffer zones explains.

The report should be deposited with the Historic Environment Record and an appropriate digital archive. That deposition is often a condition, and it is often forgotten until someone tries to discharge it three years later.

Outcomes and what each means for the scheme

Four broad outcomes, with very different consequences.

Nothing found, across an adequate sample. The curator will normally accept that no further work is needed, sometimes with a watching brief on the groundworks as a precaution.

Low significance remains. Mitigation by record, usually a strip, map and sample exercise or a watching brief, secured by condition. Manageable cost, manageable programme.

Significant remains that can be avoided. Preservation in situ becomes the preferred approach, which usually means redesigning layout, foundations or drainage around the area, and securing it through a condition and sometimes a management plan.

Nationally important remains. This is the outcome that changes schemes. Where remains are of schedulable quality, national policy treats the loss as substantial harm to a designated asset in practical terms, and the scheme may have to be reworked from the layout up, or not proceed.

That last possibility is why the timing question matters so much, and the argument on each side is set out in the note on archaeological evaluation before or after determination.

Programming evaluation before determination

Curators increasingly ask for evaluation before determination on sites of any potential, and there is a principled reason for it. A decision maker cannot weigh harm to a heritage asset without knowing whether the asset exists.

Build the programme backwards from the target submission date:

  • utility searches and landowner access agreement, two to four weeks
  • written scheme of investigation drafted and submitted, one to two weeks
  • curator approval of the scheme, two to four weeks and longer in busy authorities
  • fieldwork, depending on sample size and machine availability
  • finds and environmental assessment, which is where reports usually slip
  • reporting and curator review, two to four weeks

Six to twelve weeks is a realistic total for a modest site with no complications, and complications are the norm. Winter fieldwork on clay is a particular risk, and crop cycles restrict access on arable land.

Where a heritage asset is also affected above ground, the evaluation sits alongside the Heritage Statement and the two should describe the same site, with the same significance language.

Enter your postcode on PlanScope to see which heritage and archaeology documents a site is likely to need before you commission fieldwork.

This is general guidance, not legal advice. Archaeological evaluation should be carried out by a suitably qualified organisation working to an approved written scheme of investigation, and councils usually expect a suitably qualified author. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What percentage of a site is trial trenched?

There is no national figure. The archaeological curator sets a sampling level for each site, informed by the desk-based assessment, the geology, any geophysical survey already carried out, the depth of impact and previous investigation nearby. Percentages quoted as standards are local conventions, and the justification behind the figure carries more weight than the number.

Is geophysical survey enough on its own?

Rarely. Magnetometry finds ditched enclosures, kilns and burnt features well, and it misses timber structures, shallow features and most burials, and it is unreadable through made ground and on some geologies. Curators normally expect trenching to target the anomalies plus a blank-area sample to test what the survey could not see.

How long does an archaeological evaluation take?

Six to twelve weeks for a modest site with no complications, covering utility searches and access agreement, drafting the written scheme of investigation, curator approval, fieldwork, finds and environmental assessment, reporting and curator review. Approval of the scheme and the finds assessment are where programmes usually slip, and winter conditions add risk.

What happens if significant archaeology is found?

It depends on the level. Low significance remains are normally dealt with by record through a strip, map and sample exercise or a watching brief. Significant remains that can be avoided lead to preservation in situ and a redesign of layout, foundations or drainage. Remains of schedulable quality can force a scheme to be reworked from the layout up.

Should evaluation happen before the application is determined?

Curators increasingly ask for it, and the reasoning is sound: a decision maker cannot weigh harm to a heritage asset without knowing whether the asset is there. Deferring the work to a condition leaves an unquantified risk on the scheme, which lenders and purchasers price accordingly.

Sources and further reading

archaeologytrial trenchingevaluationheritagedevelopment risk

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Heritage and Archaeology

View all →
Heritage and Archaeology8 min read

Historic paint analysis as evidence for redecoration

Paint analysis establishes a sequence of decorative generations and their approximate dates. It does not hand you a palette, and reports are routinely asked to support conclusions the samples do not reach.

Read article →
Heritage and Archaeology7 min read

Scrub and burrowing animals on a scheduled monument

Letting scrub colonise an earthwork damages it. Grubbing it out without consent is an offence. A managed programme agreed with Historic England resolves both.

Read article →
Heritage and Archaeology7 min read

Archaeological mitigation along a linear route

A working width samples archaeology by accident of alignment. Corridor evaluation, consistent recording and advance works keep the construction spread moving.

Read article →
Heritage and Archaeology7 min read

Palaeoenvironmental sampling and what it adds

Bulk, waterlogged, column and dating samples answer different questions. A strategy that pairs each sample type with a question is the one a reviewer can approve.

Read article →
Heritage and Archaeology7 min read

Watching brief or strip map and record: choosing mitigation

A watching brief records what the contractor's trench exposes. Strip map and record maps the whole impacted area. The choice turns on deposit survival and groundwork method.

Read article →
Heritage and Archaeology7 min read

Cellars, vaults and the extent of a listed building

Below ground fabric is where most unauthorised alteration of listed buildings happens. What the listing covers, and which consents a cellar project needs.

Read article →