A reviewer's first job is to rebuild your residual from your inputs. The three documents to submit, how to handle publication and redaction, and the reconciliation table nobody provides.

A viability appraisal submission format that a reviewer can reproduce will save you weeks. The reviewer's first task is to rebuild your residual figure from your inputs, and if they cannot do that without asking questions, the questions arrive as a written request four weeks after submission and the negotiation starts a month late. Everything below is about removing that delay. None of it is about the assumptions themselves.

National guidance on viability sets the frame: assessments should be simple, transparent and proportionate, and prepared on the basis that they will be published. Write for publication and write for reconstruction, and most of the format questions answer themselves.

What a reviewer needs to reproduce the result

Four things, in this order. The inputs, with a source for each. The areas the inputs are applied to. The cashflow that turns them into a residual. And a statement of what is being asked for.

A reviewer who has those can test your figure against their own view and tell the council where the disagreement actually is. Without them, the exchange becomes a series of requests for information, and each round is a fortnight.

The most common gap is sources. A build cost of a stated amount per square metre means nothing on its own. The same figure attributed to a published cost index, at a stated date, rebased for location, with a stated allowance for externals and abnormals, is testable. Do that for every line.

The three documents to submit

Keep the submission to three parts, and label them.

The input schedule is a table of every assumption with its source and date: gross and net areas, unit mix, sales values per square metre by unit type, ground rent or commercial rent and yield, build cost per square metre, externals, abnormals, professional fees, contingency, finance rate and arrangement costs, marketing and sales costs, developer return and the basis it is expressed on, planning obligations, the levy liability, and the benchmark land value with its own derivation.

The cashflow shows the development programme and the timing: pre-construction period, construction period, sales or letting rate, and the drawdown and repayment of finance. It should be monthly or quarterly rather than annual, because finance cost on a two-year build is sensitive to phasing and an annual cashflow hides that.

The summary appraisal shows the residual result and the comparison with the benchmark land value, with a short sensitivity analysis on the two or three inputs that move the answer most.

Part Format Why
Input schedule Table, one line per assumption, with source and date The reviewer tests inputs, not conclusions
Cashflow Monthly or quarterly, showing finance drawdown Finance cost is sensitive to programme
Summary appraisal Residual against benchmark land value, plus sensitivity Shows where the deficit sits
Covering note Two or three pages Explains the ask and what changed

Model file or printed output

Submit both. A printed or PDF output fixes the version for the record and is what gets published. The live model file lets the reviewer test sensitivities without rebuilding your work, which is what shortens the process.

Where the appraisal was built in specialist software the reviewer may not hold a licence for, export a full printout including the input pages and the cashflow, and supply a spreadsheet version of the cashflow. Where it was built in a spreadsheet, leave the formulas live and unlocked. A locked workbook with hard-coded values invites the assumption that something is being hidden.

Name the file properly. Scheme name, document type, version number, date. A folder containing three files called "appraisal final" wastes somebody's afternoon.

Redaction and publication

National guidance expects viability assessments submitted with applications to be publicly available, with only limited scope to withhold material. Plan for that from the start.

The workable approach is two documents. A public version, redacted only where necessary, and a confidential annex containing the material you are asking to withhold, with a short justification for each item. Typical candidates are individual comparable transactions subject to confidentiality, contract sums under a signed building contract, and funding terms. A blanket claim over the whole appraisal will be refused and will cost you credibility.

The position at appeal is tighter again, which we cover in viability at appeal. Assume any document you submit may be read by an objector and by a local journalist.

Version control across negotiation rounds

Viability negotiations run for months and produce four or five iterations. Without discipline, nobody can say which version the committee report refers to.

  1. Number every version and date it, and never reissue a version number.
  2. Keep a change log: one line per change, with the previous value, the new value and the reason.
  3. Provide a reconciliation table between the previous version and the new one, showing the effect of each change on the residual.
  4. Change one thing at a time where you can. Reissuing an appraisal with eleven amendments makes the effect of each impossible to see.
  5. Keep the areas schedule constant unless the drawings change, and if the drawings change, say so explicitly.

That reconciliation table is the single most useful document in the whole exchange. Reviewers rarely get one, and they notice.

Reconciling the appraisal with the application

Inconsistency between the appraisal and the application documents is the fastest route to losing an argument you should have won.

Check that the gross internal area in the appraisal matches the area schedule on the drawings, and that the basis, gross internal or net internal or net sales area, is stated and used consistently. Check the unit mix matches the schedule of accommodation. Check the affordable housing numbers and tenure split match the draft heads of terms and the Affordable Housing Statement. Check the levy liability matches the form submitted with the application, including any relief claimed and any deduction for existing floorspace.

Then check the obligations. An appraisal carrying a figure for planning obligations that differs from the council's request needs a note explaining which version has been modelled. Where an obligation includes deferred or contingent payments, the cashflow has to show them at the right time, and the mechanism belongs in the agreement, which is where overage and clawback drafting comes in.

The covering note that saves weeks

Two or three pages at the front, and it should answer six questions without the reader opening the appraisal.

  • What is being asked for, in specific terms: the obligations offered, the ones being resisted, and the amounts.
  • What the residual result is, against what benchmark land value.
  • Which inputs drive the answer, and what happens to the result if each moves.
  • Where the figures come from, in one list.
  • What has changed since the last version, if this is not the first.
  • What is in the confidential annex and why.

Officers and reviewers read that note first. A good one earns the rest of the document a fair reading.

A Viability Assessment is a report councils expect from a suitably qualified author, normally RICS-qualified and working to the professional guidance on financial viability in planning, and professional review before submission is strongly advised. An AI-assisted draft can structure the document, set out the input schedule and draft the narrative. The valuation judgement, the comparables and the sign-off belong to the valuer.

One honest uncertainty: authorities differ on whether they want the live model at all, and some reviewers prefer to build their own from your inputs. Ask which the reviewing body prefers before you submit, because sending the wrong thing means sending it twice.

See PlanScope pricing: one free report, £50 per report, or Professional for unlimited reports.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Should I submit the live appraisal model?

Submit both a printed or PDF output, which fixes the version for the record and is what gets published, and the live file so the reviewer can test sensitivities without rebuilding your work. Ask the reviewing body what format it prefers first, because sending the wrong thing means sending it twice.

How detailed does the cashflow need to be?

Monthly or quarterly rather than annual. Finance cost on a two-year build is sensitive to the phasing of construction and sales, and an annual cashflow hides that. Show the pre-construction period, the build programme, the sales or letting rate, and the drawdown and repayment of finance.

Can I keep my appraisal confidential?

Only in limited respects. National guidance expects viability assessments submitted with applications to be publicly available. The workable approach is a public version plus a confidential annex holding specific items, such as confidential comparables or contract sums, each with a justification. Blanket claims are refused.

What is the most useful document in a negotiation?

A reconciliation table between appraisal versions, showing each change, the previous value, the new value, the reason, and the effect on the residual. Reviewers rarely receive one. Combine it with strict version numbering and a change log, and never reissue a version number with different contents.

Which inconsistencies cause the most trouble?

Floor areas that do not match the drawings, an area basis that is not stated or is used inconsistently, a unit mix that differs from the schedule of accommodation, affordable numbers that differ from the draft heads of terms, and a levy liability that does not match the form submitted with the application.

How long should the covering note be?

Two or three pages. It should state what is being asked for, the residual against the benchmark land value, the inputs that drive the answer, where the figures come from, what has changed since the last version, and what sits in the confidential annex and why. Officers read it first.

Sources and further reading

viabilityappraisalsection 106affordable housingsubmission format

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial8 min read

Marriage value and site assembly in a viability appraisal

Assembly costs are real, but most of them do not reduce what a scheme can contribute. Where acquisition costs, ransom premiums and created marriage value each belong in the appraisal.

Read article →
Viability, Obligations and Commercial7 min read

Varying a planning obligation after five years

After the five year relevant period, a statutory application under section 106A replaces negotiation, and a refusal can be appealed under section 106B. What the authority can decide and what it cannot.

Read article →
Viability, Obligations and Commercial7 min read

Social infrastructure contributions and how they are justified

Contribution requests are built from a yield factor, a capacity claim and a published cost. The arithmetic is usually right, so the argument belongs on the capacity evidence and the statutory tests.

Read article →
Viability, Obligations and Commercial7 min read

Pooling restrictions and clawback in planning obligations

Regulation 123 and the five obligation pooling cap went in September 2019. What remains is the statutory test in regulation 122, the infrastructure funding statement, and careful drafting against duplication.

Read article →
Viability, Obligations and Commercial8 min read

Indexation of section 106 contributions and which index applies

The index family and the base date decide how far an indexed contribution moves. Name the series exactly, set the base date to the prices the figure is expressed in, and recalculate every demand.

Read article →
Viability, Obligations and Commercial8 min read

Phasing a scheme to manage section 106 triggers

Phasing moves when obligations fall due rather than how much they total. Define phases by land parcel, build in a revised phasing plan mechanism, and tie affordable delivery to occupation within each phase.

Read article →